Construction Cost Estimating Class #5 - Concrete Prof. Ralph V. Locurcio, PE.

Slides:



Advertisements
Similar presentations
RETAINED SOIL WALL SYSTEM™
Advertisements

Estimating the Cost for the Concrete Pad
FORMWORK Prof Awad S. Hanna.
Estimating & Tendering. Estimating work involves dealing with Measurements and quantities Pricing and rates Subcontract packages Tender preparation.
Click to edit Master title style The Adkins Project … and the third little pig made his home from concrete treated with FIBERMESH ®. No huffing and puffing.
2.2 STRUCTURAL ELEMENT Reinforced Concrete Slabs
Copyright © by NCCER, Published by Pearson Education, Inc. Carpentry Fundamentals Level One Module National Center for Construction Education.
Prof Awad S. Hanna Concrete Structures Concrete Structures.
Measuring Concrete Work
Commercial Framing C D Prints Unit 13.
Portland Cement and Concrete
Reinforced Concrete QTO Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
CONCRETE MIX-DESIGN ACI
Estimating the Cost for a Foundation and Footing.
Chapter 12 Pricing Masonry Carpentry, and Finishes Work.
Concrete
Chapter 6 Measuring Masonry and Finishes. Masonry Work Generally It includes clay bricks, concrete bricks and blocks, clay tiles, and natural and artificial.
Construction Cost Estimating Class #7 - Masonry Prof. Ralph V. Locurcio, PE.
Estimating Waste Week 3 CTC-415. What is waste Waste is material that needs to be supplied but may not be used All material items except steel beams and.
Bell Work: Becky reduced the size of the image on the computer screen by 40%. By what percent was the area of the image reduced?
CON 4003, CVE 4073, CVE 5073 Construction Estimating Prof R. V. Locurcio, PE.
Calculating board Feet linear feet
Construction Estimating Using Excel Professor Locurcio CON4003, CVE4073, CVE5073.
Calculating board Feet linear feet square feet
It’s more than adding and subtracting..  Before bidding, the site should be examined for the following:  Distance from the office  Site conditions.
Chapter 18 Foundations.
Topic : MIX DESIGN OF CONCRETE Properties of concrete Submitted To: DR. AYUB ELAHI Submitted By: SOHAIB NASEER 2K9-scet-29/CIVIL M.ZAEEM FAKHAR 2K9-scet-03/CIVIL.
Construction Cost Estimanting 4003 Cost Estimating/ Engineering Concrete Structures Prepared by: Ebrahim A Alkooheji Instructor: Proff. Locurcio.
Concrete Construction
March 13, 2007 DRILL Architecture Styles and Vocabulary QUIZ tomorrow
Measuring Masonry Work
CON 4003 Construction Estimating Prof R. V. Locurcio.
Chapter 11 Pricing Concrete Work. Objectives Upon completion of this chapter, you will be able to: –Describe the job factors and the labor and management.
Chapter 4 Measuring Concrete Work
Sinking in Concrete Calculating materials for a concrete job.
Chapter 12 Concrete Construction Part 3 1CE 417, King Saud University.
Intro to Concrete 18.0 & 19.0 Class notes.
Detailed Quantity Estimating Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Concrete Unit 24 Carpentry and Building Construction.
1 HVACR116 – Trade Skills Structural Drawings. 2.
BILL OF MATERIALS. BEGINNING THOUGHTS ► IDENTIFY ONE MACHINE THAT YOU WILL USE TO BULID YOUR CONCRETE FLOAT? ► WHY MUST YOU USE A RULER WHILE BUILDING.
HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE.
CON 4003 Construction Estimating Prof R. V. Locurcio.
How to Calculate Landscape Estimates and Quotes 2.01 Apply procedures to perform calculations used in estimates and quotes.
CON 4003 Construction Estimating Prof R. V. Locurcio.
Objective Calculate the amount of materials needed for a construction project.
8-10 Scaling Three-Dimensional Figures Course 3 Warm Up Warm Up Problem of the Day Problem of the Day Lesson Presentation Lesson Presentation.
Construction Estimating Using Excel Professor Locurcio CON4003, CVE4073, CVE5073.
CON 4003 Construction Estimating Prof R. V. Locurcio.
Now that I built it, How much did it Cost?
Estimating Concrete Construction and Material Cost
ESTIMATING STEEL FOR CONCRETE POURS. REBAR -Estimated by the pound or ton -Must know the size of steel bar needed -Must know linear feet needed -Bars.
Demonstrate Concrete Skills Form A wood or metal structure that confines concrete to the desired shape until it hardens.
8-10 Scaling Three-Dimensional Figures Warm Up Problem of the Day
Estimating the Cost of a Concrete Pad & Rebar (Revised: )
FORMWORK DR. Nabil Dmaidi.
Drawing Interpretation
Estimating the Cost for the Concrete Pad
Planning and Placing Concrete
Estimating the Cost for the Concrete Pad
Estimating the Cost for the Concrete Pad
Concrete Structures DR. Nabil Dmaidi.
Warm Up Problem of the Day Lesson Presentation Lesson Quizzes.
Estimating the Cost for the Concrete Pad
Construction Engineering Change Order - 2 Prof. Ralph V. Locurcio, PE
Construction Engineering Change Order - 2 Prof. Ralph V. Locurcio, PE
Concrete A structural material made by combining cement, sand, aggregate, and water.
Estimating the Cost for the Concrete Pad
Estimating the Cost for the Concrete Pad
8-10 Scaling Three-Dimensional Figures Warm Up Problem of the Day
Presentation transcript:

Construction Cost Estimating Class #5 - Concrete Prof. Ralph V. Locurcio, PE

 Forms  Reinforcing  Concrete  Spread Footings  Columns  Foundation Walls  Beams  Slab  Conclusion

 May be bid by itemization  Based on square footage rather than linear  SFCA = square foot contact area  Quantity of form material & labor

 Rebar  Welded wire fabric  Purchase  Small amounts by lineal foot (20’)  Large amounts by pound/ton  Fabricated  Fabricated in the field, lengths of ft  Large jobs fabricated and shipped

 Rebar sizes

 Various types based specs & strength  Type I = normal cement  Type II = moderate-sulfate resistance cement  Type III = high-early-strength cement  Type IV = low-heat-of-hydration  Type V = high-sulfate –resistance cement  Mixes  Add-mixtures are included for certain physical properties

 Costs  Best place to get prices is from concrete suppliers  Bid by cubic yard  Labor for placement and finishing (use RS Means)  Placement  From truck with chute  Concrete bucket  Concrete pump

 Spread Footings  Package includes: footings, forms, horizontal rebar in the footings and the dowles  Continuous footings  Similar to spread footing but a much longer than they are wide

Figure 5-1

Volume Calculation

Linear Calculation

Concrete column as volumetric good

Figure 5-1

 Lots of examples  Any questions?