Arrowhead  Weston Transmission Line Project Dave Van House Minnesota Power.

Slides:



Advertisements
Similar presentations
Central California Clean Energy Transmission Project PCC Meeting Vancouver, BC October 24, 2007.
Advertisements

NERC Footnote b / 12 – Load Loss
Chapter 12 Transformers. Chapter 12 Transformers.
Study Committee Representatives Annual Report December, 2012
Presented to PGDTF February 11, 2015
ERCOT VRT Study, Phase I ERCOT ROS Meeting December 10, 2009.
Connection of Wind Farms to Weak AC networks – ERCOT Experience and Challenges Shun-Hsien (Fred) Huang ERCOT System Planning CIGRE WG B4.62 Meeting June.
Protection against Lightning Overvoltages Overvoltages due to lightning strokes can be avoided or minimized in practice by (d) shielding the overhead lines.
Tucson Area Reliability Mike Flores Control Area Operations Tucson Electric Power May 2000.
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
Dynamic VAR’s [D-VAR] What are D-VAR Devices? Dynamic VARs… Fully integrated modular STATCOM with proprietary 3X overload Instantaneously injects precise.
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
Jeffery J. Gust IOWA INDUSTRIAL ENERGY GROUP FALL CONFERENCE Tuesday, October 14, 2014 MidAmerican Energy Company.
AUGUST 19, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
Disconnect Switches There are many purposes for disconnect switches in substations and power lines. They are used to isolate or deenergize equipment for.
Lec. (4) Chapter (2) AC- circuits Capacitors and transient current 1.
2001 & 2002 Energy Preparedness Tucson Electric Power February 16, 2001 Michael Flores, Manager Control Area Operations David Hutchens, Manager Wholesale.
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
ACTION PROPOSAL FOR FLYWHEEL ENERGY TECHNOLOGY Enhance future grid reliability, interoperability, & extreme event protection In 20 years, the flywheel.
THE TRES AMIGAS SUPERSTATION Southwest Renewable Energy Conference Santa Fe, NMSeptember 16 th 2010 UNITING THE NATION’S ELECTRIC POWER GRID.
By A.D.Thirumoorthy Tamil Nadu Electricity Board India.
1 Power Quality Mary Santori, P.E. Senior Engineer September 12, 2013.
Houston Area Dynamic Reactive Project March 11,
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
“Reactive Power Management and Voltage Stability” Sharma Kolluri, IEEE Fellow Manager of Transmission Planning Entergy Services Inc Presentation at 2012.
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
ISO Exhibit 13 Federal Energy Regulatory Commission Technical Conference on Connecticut Infrastructure Reliability and Operability Committee Update Hartford,
1 Cheng-Ting Hsu Chao-Shun Chen Islanding Operations for the Distribution Systems with Dispersed Generation Systems Department of Electrical Engineering.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
APPA RELIABILITY STANDARDS & COMPLIANCE SYMPOSIUM Case Study: City Utilities of Springfield, MO January 11, 2007.
Managing West Texas Wind SWEDE 2008 Conference May 2, 2008 Presented by Paul Hassink AEPSC Texas Transmission Planning.
Freeport Generating Project Project Description Modernization projects at Power Plant #2 Developers – Freeport Electric and Selected Development Company.
Lyndonville Electric Department Feasibility Analysis Review December 2,
1 TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE April 17, 2007 New Mexico Transmission System Overview.
1 Mid-Continent Area Power Pool Wind Integration Studies Edward P. Weber August 16, 2007.
MISO Northwest Exploratory Study Presented to National Wind Coordinating Committee Participants in study – MISO, Various utilities in Minnesota, North.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
Utility Engineers, PC.  Generation  Transmission  Distribution.
POWER HOUSE.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
Voltage Control Brad Calhoun Consultant, Sr. Trainer Spring 2016.
1 Transmission of Electrical Energy Electrical energy is carries by conductors such as overhead transmission lines and underground cables. The conductors.
Power Quality By Using FACTS. CONTENTS INTRODUCTION WHAT IS FACTS? FOR WHAT PURPOSE FACTS ARE USED? BASIC TYPES OF FACTS CONTROLLERS BENEFITS OF UTILISING.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
SEMINAR PRESENATATION ON WIDEAREA BLACKOUT (AN ELECTRICAL DISASTER) BY:Madhusmita Mohanty Electrical Engineering 7TH Semester Regd No
1 NPCC – A-2 Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006 Presented to the NYSRC-RRS.
Power Quality at Solar Distributed Generation Facilities
Agenda TSOG 8th November
Transmission Planning in ERCOT- Overview
HVDC LIGHT:- NEW TECHNOLOGY FOR A BETTER ENVIRONMENT
Black Start Overview.
IG BASED WINDFARMS USING STATCOM
Phase Angle Limitations
PSCAD models.
Presented by: LADWP November 14, 2017
Introduction To Reactive Power
Passive Shunt Compensation
Transmission Lines EE 4501 S.R.Norr and D. Van House.
POWER SYSTEM ANALYSIS INTRODUCTION.
DEC System Voltage Planning - June 2018
Mid-Continent Area Power Pool
EHV Transmission Equipments
Palo Verde-COI RAS Retirement
Palo Verde-COI RAS Retirement
Presentation transcript:

Arrowhead  Weston Transmission Line Project Dave Van House Minnesota Power

Description & Overview  220 mile 345,000 volt electric transmission line  Approved by the Minnesota and Wisconsin regulators in 2001  Construction Began in Minnesota February 2004  Construction to Begin in Wisconsin Fall 2004  Construction scheduled to be completed in 2008

Why was it proposed? Reliability!!  Improves Regional System Security  Provides Maintenance & Operational Flexibility  Allows Customers Greater Access to Generation Sources

Minnesota  Minnesota’s electric network is tied to neighboring states.  If Wisconsin has a problem, Minnesota has a problem.  Minnesota Power customers have been knocked off line by electric system disturbances related to the weak Minnesota- Wisconsin connection.

Recent Regional Problems  June 11, 1997  June 25, 1998  June 10, 1999

IMPACT OF June 25, 1998 DISTURBANCE  IN MAPP ■ 60+ TRANSMISSION LINES TRIPPED ■ 4,000+ MW OF GENERATION LOST ■ More Than 39,000+ CUSTOMERS AFFECTED  IN NW ONTARIO ■ BLACK OUT TO 113,000 CUSTOMERS ■ 650 MW OF LOAD LOST ■ 270 MW OF Generation Lost

Wisconsin Actions  1997 events raise concerns about electric supply reliability in Wisconsin  Wisconsin utilities and regulators form Wisconsin Reliability Assessment Organization (WRAO)  WRAO forms engineering group to study alternatives - WIRES group

PERFORMANCE EVALUATION  DETAILED POWER FLOWS SIMULATION  GENERATOR RESPONSE  DYNAMIC STABILITY  VOLTAGE STABILITY  IMPACT ON MAPP  CONSTRUCTION COSTS  LOSS EVALUATION

Power Flow Analysis  Reactive Voltage Support Requirements  Steady State Maximum Transfer capability  Sensitivity to Modeling Assumptions  Transmission System Loss Analysis

Generator Response  Mechanical Stress on Weston Generator Shaft ■ Large Phase Angle Across MAPP MAIN Interface ■ Eau Claire Arpin Line Switching ■ Instanteous change in Power output

Dynamic Stability  Ability of Systems Generators to remain synchronized and recover from Major System Disturbance  MAPP WUMS Disturbances  Loss of New Facilities  Impact on Existing Limiting Conditions  Dynamic Reactive Support Requirements

Voltage Stability  Ability of the System to Maintain Adequate Voltage Following a Disturbance  Without Adequate Voltage Support System can Experience ■ Increased Current Demand (P = VI) ■ Slowly Declining Voltage ■ Loss of Voltage Sensitive Loads ■ Voltage Collapse

Engineering to Support Permitting  Calculation of; ■ AUDIBLE NOISE ■ ELECTRIC FIELD ■ MAGNETIC FIELD  Analysis of Potential Farm Impacts ■ Stray Voltage ■ Earth Currents

 Magnetic Field  Electric Field  Spark Discharge  Multiple Routes  Multiple Structures  Multiple Circuits  Multiple Flows  Future Years EMF Issues

Transmission Line Noise  Due to Corona Discharge ■ Electric Field at surface of the conductor exceeds the breakdown strength of air ■ Generates light, audible noise radio noise and energy losses  Mitigation ■ Increase Conductor Surface area Larger Conductors Multiple conductors

Substation Noise Monitoring  Long Term  Short Term  Existing Equipment  Impact of Additions

Arrowhead Substation Noise

Other Engineering Issues  Differential GPS Interference ( Precision Farming )  Electric & Magnetic Field ■ Impacts on Pacemakers and implantable Defibulators ■ Impacts on Railroad, Pipeline and AM Radio Transmitter sites

Opposition to the project: l Save Our Unique Lands l Citizens Utility Board l Wisconsin Environmental Decade l North American Water Office l Hillside Dairy l World Organization of Landowner Freedom

Common Utility Corridor

Visual Impact Of Crossing

Existing 161 kV H-Frame

954 ACSR 2-Conductor Bundle with Shield Wire

Single 3M Composite Conductor

Post Permit Studies  Equipment Specification  Construction Support Analysis  Operating studies

Equipment Specifications  Transient studies ■ Breaker Switching Duties Shunt Reactor Shunt Capacitor 345 & 230 kV line breakers ■ Capacitor Bank Switching Issues Voltage Magnification ■ Insulation Coordination Surge Arrester rating & placement Equipment BIL requirements Line Insulation

Construction Impact Studies  Constructability ■ Line outage concerns ■ Maintenance issues ■ Ownership Issues  Increased Cost  Landowner Opposition

Operating Studies  Determination of Operating Limits ■ Reactive Support Requirements Shunt Capacitor location optimization ■ Line Loadability Issues System Intact and Post Contingency ■ Phase Shifter Requirements Line load sharing optimization Post Contingency requirements ■ New Flow-Gate Limits System Intact and Post Contingency

Summary  Operating experience has shown there is a significant risk to electrical reliability in the upper Midwest and Wisconsin  Engineering study commissioned through Assembly Act 204  WRAO recommendation Arrowhead Weston 345 kV Line

Summary  The Arrowhead-Weston Project will substantially alleviate the reliability problems being experienced due to the weak electrical tie between the upper Midwest and Wisconsin.  It will also provide import capability for Wisconsin to meet its emergency power supply requirements.