ColUSM #51 30 th January, 2015 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, Q. Deliege, V. Baglin, F. Savary.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

19th – 20th of September 2007Cryogenic Expert Meeting at GSI, Jan Patrick Meier1/11 Cryogenic Experts Meeting at GSI, 2007 The SIS 100 Cryogenic Jumper.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
F. Savary on behalf of the WP11 team Input from V. Baglin, D. Ramos.
CRYO PIPING & INTER-MODULE CONNECTIONS Yun He, Daniel Sabol, Joe Conway External Review of MLC Daniel Sabol, MLC External Review 10/3/2012.
1 Integration of collimators in the dispersion suppressors Status of 11 T cryo- assembly integration Dec 17, 2013
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
REVIEW OF THE CRYOGENIC BY-PASS FOR THE LHC DS COLLIMATORS ELECTRICAL CIRCUIT MODIFICATION, INCLUDING OPERATIONAL CONSIDERATIONS PRESENTED BY A. SIEMKO.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
Possible HTS wire implementation Amalia Ballarino Care HHH Working Meeting LHC beam-beam effects and beam-beam interaction CERN, 28 th August 2008.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
H. Prin, F. Savary, D. Duarte Ramos, L. Grand- Clement, C. Mucher, A. Temporal.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
SCU Layout Concept - Minimal Segmentation Joel Fuerst (ANL) SCU 3-Lab Review Meeting Dec. 16, 2014.
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
1 Hi-Lumi WP3 meeting Update on the Q1 to D1 cryostat Jan 28, 2014  Outline  Cryostat cross section options  Elliptical interconnect.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve.
The Stripping Foil Test Stand in the Linac4 Transfer Line
12th HL-LHC Parameter and Layout Committee meeting.
C. Garion Presentation Outline  Overview of the inner triplet interconnections  Q1/Q2, Q2/Q3 interconnections  General view  Working conditions  Compensation.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
Cryostat & LHC Tunnel Slava Yakovlev on behalf of the FNAL team: Nikolay Solyak, Tom Peterson, Ivan Gonin, and Timergali Khabibouline The 6 th LHC-CC webex.
Vacuum, Surfaces & Coatings Group Technology Department 22 nd January 2015 C. Garion2 Beam Line Interconnection: snapshot of present design principles.
The integration of 420 m detectors into the LHC
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
HL-LHC 11 T Dipole for DS Collimation 8 th to10 th December, 2014 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, F. Savary,
Quadrupoles and orbit correctors bus bars routing along the inner triplet string MQXF Workshop at CERN– February the 3 rd 2016 H. Prin With acknowledgements.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
Target Systems and Monolith Design Update Rikard Linander Group Leader Monolith and Handling April 2, 2014.
QXF magnet integration Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
1 Status of the 11T cryo-assembly design and integration Presented at ColUSM #34, February 21, 2014
Two-beam module layout
Cryostats for superconducting magnets
SPL RF coupler: integration aspects
News and Introduction from CERN June 15th, 2005
D. Ramos, H. Prin, M. Moretti, C. Eymin, A. Temporal, V. Parma, S
Cold mass design, assembly plans and QA/QC at CERN
HL-LHC IT STRING and Series test of SC link
Roadmap for triplet cryostats
Status of triplet cryostat and magnet support scheme
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
Cryostat procurement, status and plan, QA/QC
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Cryo-assembly design D. Ramos, V. Parma, C. Mucher, H. Prin, M. Souchet, J. Hrivnak, M. Moretti, L. Mora, F. Savary, L. Gentini Review of the 11T Dipoles.
Status of cryostat integration and conceptual design
Comparison between 1) HL-LHC BASELINE: Q5 at point 6 at 1
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
From Design to Installation courtesy R. Folch S. Atieh TS / MME
The 11T cryo-assembly: summary of design and integration aspects
UK RFD Pre-Series cryomodule
WP3 Meeting – December the 10th 2015 H. Prin
Cryostats Some ideas for the new Q1 to Q3 Hi-Lumi WP3 meeting
Magnetic shielding and thermal shielding
IR Beam Transport Status
Status of QQXF cryostat
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

ColUSM #51 30 th January, 2015 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, Q. Deliege, V. Baglin, F. Savary

Click here to add footer 2 Outline Specifications, constraints and goals As-installed magnet length Continuity of cryogenics and powering (how did we got to the current layout) Beam vacuum components and achievable collimator length Conclusion and comments on eventual specification changes

Click here to add footer 3 Specifications, constraints and goals Compatibility with installation and transport constraints: not larger than existing cryostat (ø1055 mm) Create a room temperature vacuum sector in the LHC continuous cryostat Cold to warm transitions (CWT) Sector valve after each CWT for vacuum separation during magnet cooldown or collimator bakeout. RF- shielded gate valves and bellows for impedance reasons DN35 ports on the cold sectors to send an RF emitter ball through the full arc after warm up and before cooldown Compatibility with existing cryogenic and electrical systems, ensuring their continuity Prevent loss of alignment during evacuation with independent supports for collimator and cryostat Minimise changes to other magnets: keep interconnects standard if possible Collimator Vacuum enclosure Magnet 1.8K Heat exchanger Beam vacuum Lines E, C’, K RF emitter Bus bars

Click here to add footer 4 Layout options (January 2013) New end covers may be made to route the bus bars in a way to provide enough space for the collimator. The “price” is loss of interchangeability betwen cold masses… Retained Additional module needed to create a standard interconnect interface and thermal compensation. Interference with W sleeve. Not possible to fit the collimator nor sector valves between standard bus bar lines. New routing needed to make vertical space for the collimator

Click here to add footer 5 As installed magnet length i.e. ~3.1 m availabe for collimator, interconnects and remainder equipment

Click here to add footer 6 1 st Concept (Dec 2013) Independently cryostated and handled cold masses, linked through two short transfer lines Transfer lines with expansion joints mechanically decouple cryostats A and B Splice and piping interfonnect in the tunnel, all other work prior to installation Can use the existing TCLD collimator design with modified the supports Collimator Lines M, E, N, K, C’ Reinforced jacks to widstand vacuum forces Cold mass ACold mass B Line X Independently supported collimator Busbar splice and interconnect done in the tunnel Flexible S-shaped busbar stabiliser Busbar lyra

Click here to add footer 7 1 st Concept (Dec 2013) 800 mm Collimator Compatible with the collimator design developed in 2010 (TCLD) Starting assumption: busbar bypass can be made in the shadow of the beam screens and CWT

Click here to add footer 8 After long months of idea generation and testing The busbar routing proved to be a major challenge! Six busbars in one duct: how to route lyras, large bellows, space for an extra interconnect at the exit of the CM External MQ busbars: How to connect to the existing magnets, space for the interconnect at the exit of the CM for line M3 Three separate ducts for each pair of bus bars: better but length to accomodate the pipe bends and interconnect length still an issue Busbar bypass can be made in the shadow of the beam screens and CWT Can Not

Technology Department Present layout Current working design Design proposal 2 nd Concept: 2 magnets in one cold mass “QTC-like” short bypass module upstream of 11T Two-in-one cold masses imply moving several magnets radially or using orbit correctors to compensate for the fact that the cold mass is straight Still not possible to route the busbars without taking more length than required by the beam vacuum components Hervé Prin, April 2014

Click here to add footer 10 May 2014: A new approach QRL side K2 M2 V2 W Y M1 M3 E C’ V1 K1 X N

Click here to add footer 11 3 rd Concept (current baseline) Same mm length between interconnect planes as an LHC MB Connection cryostat between two 11 T magnets to integrate the collimator LHC MB replaced by 3 cryostats + collimator, all independently supported and aligned: Same interfaces at the extremities: no changes to nearby magnets, standard interconnection procedures & tooling

Click here to add footer 12 Connection cryostat for collimator integration Collimator support jacks Cryostat support jacks Cold mass enlarged to Ø750 on the collimator side Constant LHC arc outer flange diameter: Ø1055 Flexible interconnects for alignment independency and thermal contraction Interconnects usestandard componentsand tooling despite thenew compact layout Busbar routing is now in the shadow of the beam screens and CWT!

Click here to add footer 13 Cross section of the connection cryostat and collimator Dedicated collimator design. One collimator design fits both beam lines M2 W Y M1 M3 E C’ X N Collimator supported directly on the concrete slab Larger cold mass extremity to open up space for the collimator

Click here to add footer 14 Beam vacuum & Collimator length (1) 600 mm Collimator Warm drift vacuum chamber Possibility of getting extra 50 mm but the interconnects will not have the same length: 2 vacuum vessel variants or 2 interc. sleeve variants Transitions needed to allow installation of sector valves Very tight integration

Click here to add footer 15 Beam vacuum & Collimator length (2) Interconnects become longer because of the beamscreens Very compact cold line because of the sector valve RF shielding Transitions avoided because there are no sector valves on the other beam lines Cold drift vacuum chamber 650 mm Collimator

Click here to add footer 16 Conclusion The present baseline layout allows to connect busbars and cryogenic lines without impact on the length of the collimator Beam vacuum, design for RF impedance, minimised radiation to personnel and beam line inspection with emitter ball impose a minimum length of beam line components, thus defining the collimator length Detailed design studies revealed the constraints imposed by the beam line without collimator Both warm and cold versions of that line require validate with physical mockups/prototypes (preparation starting the coming weeks) Should the outcome be positive, the collimator active length can be 650 mm.

Click here to add footer 17 More space for the collimator implies compromising No ports for RF ball test: +130 mm (applies to both versions) No beamscreen on line without collimator: +120 mm (applies to cold version only) Ex. no RF ball ports + no beamscreen + no quick flange: +310 mm (applies to cold version only) No quick flange on collimator: +60 mm (applies to both versions)

Click here to add footer 19 Current leads for the trim circuit 2x 300 A conduction cooled leads Only one location is possible Integration and design to be started Gas cooled leads not possible both for lack of space and cryogenics Conduction cooled leads: about 3.6 W/kA to 1.9 K (c.f. A. Ballarino) Local solution: applicable everywhere in the LHC RT copper cables  towards power converter Similar to a Dipole Corrector Feedthrough in the SSS (EDMS )

Click here to add footer 20 Before the 11 T magnet development: QTC (2010) Main drawback: extensive machine layout changes to create space 4.0 m m interc. = 4.5 m installation length

Click here to add footer 21 Could the QTC cryostat concept be “extended”? Can only be finished after cryostating Dealing with welding distortions is a major issue Distortions amplified with length Adjustment of cold supports posts is required Complicated assembly procedure Longitudinal butt-welds Cover closure w/ fillet welds New approach needed