1 Second Safety Council Meeting Tucson, AZ April 10-11, 2014 Name of Meeting Location Date - Change in Slide Master The Dome Project Bill Gressler Telescope.

Slides:



Advertisements
Similar presentations
Extra Large Telescope Wind Engineering. Wind and Large Optical Telescopes Wind is a key factor in the design of large telescopes: larger wind-induced.
Advertisements

Contracting for Laboratory Services Ann Mullin Cleveland US Geological Survey Presented to the Environmental Protection Agency Science Advisory Board April.
1 PROJECT MANAGEMENT ROLE OF KEY PERSONNEL Bernd Madauss International Space University Strasbourg February, 2011
CMSC 2006 Orlando Active Alignment System for the LSST William J. Gressler LSST Project National Optical Astronomy Observatory (NOAO) Scott Sandwith New.
WIYN Planning Meeting, February 28, 2013 Wisconsin, Indiana Yale, NOAO 0.9m Half Degree Imager – First Light.
1 Second Safety Council Meeting Tucson April 2014 Name of Meeting Location Date - Change in Slide Master Dome Hazard Analysis Discussion Jacques.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION South Cascade Drive/Miller Road (Formerly Route 219)/ Cattaraugus Creek Design-Build Project (PIN ,
Observations of Active Galactic Nuclei via a Student Operated Remote Observatory Whitney Wills Michael Carini-Faculty Mentor Department of Physics and.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Route 110 over Route 27 Design-Build Project (PIN , D900027) Town of Babylon, Suffolk County Request.
Red Light Safety Camera Program Update Presented by Public Works Department Traffic Engineering Division Board of County Commissioners June 19, 2012.
1 Piney Branch Drainage Area Piney Branch Tunnel Rock Creek 049 Piney Branch Stream Rock Creek Current Plan Proposed Plan 049 CSO Outfall 16 th St Irving.
CONSTRUCTION BLUEPRINT READING
Safety Council Meeting Tucson Arizona 10 – 11 April Safety Council Meeting Tucson Arizona 10 – 11 April 2014 LSST Project Status Victor L. Krabbendam.
Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time.
TEMPO Mission Project July 23, 2013 Project Manager: Alan Little.
1 IT Services Through the Invitation To Qualify (ITQ) Procurement Process Paul Bluhm ITQ Program Manager.
Standard WBS Version 1.0 WBS2-3.pptPage 1 Standard Work Breakdown Structure Legend = Decomposes to lower level WBS elements 4.0 Implementation 4.0 Implementation.
M2 Status & Near Term Major Milestones C. Araujo/B. Gressler 1.
From Research Prototype to Production
4/25/11 G v3 1 Facility Modifications and Preparations (FMP) Technical Status Annual NSF Review of Advanced LIGO Project April , 2011 John.
Monday Morning J. Sebag T&S Systems Engineer. Close Past… 2 M1M3 acceptance and transportation to storage Reviews and RFPs (Dome, Software, Coating Plant,
Sandrine Thomas (T&S Project Scientist) & Telescope and Site Team.
How RISKY Is This??. How RISKY is This?? Buy a lottery ticket Only 3 will be sold Cost for a ticket $80 million Jackpot $2,000,000,000 Where is the
Telescope Integration and Tests Tuesday Afternoon.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
M1M3 Status & Near Future Milestones C.Araujo/ J. Sebag 1.
Project History and Background. Senate Bill Directed UDOT to Implement Traffic Traffic Signal Coordination Systems Established a Traffic Signal.
1 Second Safety Council Meeting Tucson, AZ April 10-11, 2014 Name of Meeting Location Date - Change in Slide Master Safety in the Procurement Process Bill.
Westinghouse/Southern/SCANA – New Build Configuration Management
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
Mechanical Integrity Training. Lesson Objectives  Describe MI Training Required  Describe How to Conduct Training  Describe Requirements for Maintaining.
8am: start testing the corner cube mounts on DX cells.
Project Management Process Transition & Closure Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team.
DIVISION OF PROCUREMENT SERVICES procurement.sc.gov/PS/PS-index.phtm Project Acquisition Under the Consolidated Procurement Code John St. C. White State.
Volusia County Purchasing & Contracts Division 2012 National Procurement Institute Achievement of Excellence in Procurement.
Pre-Proposal Conference July 8, 2009 Step 1 Instructions RFQ for Medical Equipment Planning.
ESS WP 12 Project Management & Capabilities Overview Neil Bliss Projects & Mechanical Engineering Group Leader ESS PDR, Lund, 10 th November 2015.
8:30am: start of activities in clean room: sticking foam pads to SX covers.
Status Report of Taiwan Two Meter Telescope Yi Chou Graduate Institute of Astronomy National Central University 2016/1/ 兩岸天文儀器會議.
H.E.S.S. - MAGIC – CTA meeting Technical aspects of current & future instrumentation Telescope structures Camera designs Photon detectors Mirrors.
COSMO Large Coronagraph Preliminary Design Review
SC Project Review of NCSX, April 8-10, 2008 Plant Design Integration, General Arrangement Drawings E. D. Perry.
SPIE 2014 Montreal, Quebec, Canada June 22 nd - June 27 th, LSST Telescope and Site Status William J. Gressler Telescope and Site Manager J. Andrew,
WMATA Project Implementation Manual (PIM) Stage 3, Construction Chapter 200, Authority Representative, Responsibilities and Functions Presenters: David.
C2 Systems To Go Deployable Command and Control Systems for the Future of Naval Warfare.
Project Budget Review _ Control Developed by: Daniel J. Renna 3/16/20161.
ITS Device Standards & Procurement Project PURPOSE  Develop a series of Standards & Strategies designed to guide and provide consistency across the development.
Energy Huntsville Opportunity Report and Government Collaboration April 2016.
IV&V Facility 7/28/20041 IV&V in NASA Pre-Solicitation Conference/ Industry Day NASA IV&V FACILITY July 28, 2004.
Visualizations for the Public from the LSST Integrated Model Suzanne Jacoby, Bill Schoening, John Andrew, Chris Smith … August 18,
1 Board Telescope & Site Tucson, Arizona July 18-20, 2011 LLST Control Software Review Resources Tucson, January
1 OBSERVATORY CONTROL SYSTEM (OCS) FRANCISCO DELGADO OCS CAM.
Agenda ComCam planning and scheduling (James & Jacques) CCS & CCS-TCS Interface (Tony) Software to use ComCam Software to get data out of ComCam (Mike)
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
Alternative Dome Enclosure concept Maunakea Spectroscopic Explorer
Energy Huntsville Opportunity Report June 2017
LSST Commissioning: FY18 Planning
Facility Concept Design and Study
ETS For ACTR 9the April 2015 R.Tighe april 2011 april /04/2015
Chuck F Claver LSST System Scientist & Commissioning Lead
Camera to Top End Assembly Integration Travis Lange Camera I&T M. E
UK RFD Pre-Series cryomodule
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
Management Breakout: MREFC Budget Summary Victor L
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
CONVENTIONAL FACILITIES LCLS Office Space
CONVENTIONAL FACILITIES LCLS Office Space Procurement
East Hall under construction
Presentation transcript:

1 Second Safety Council Meeting Tucson, AZ April 10-11, 2014 Name of Meeting Location Date - Change in Slide Master The Dome Project Bill Gressler Telescope & Site Manager April 10, 2014 Second Safety Council Meeting April 10-11, 2014 | LSST Project Office N550

2 Second Safety Council Meeting Tucson, AZ April 10-11, The Telescope and Site Team has developed an Observatory System to perform the LSST Mission 1,380m 2 Service and Maintenance Facility Summit Facility Controls Survey Captures Light Calibrates Conditions Control Room Camera Clean Room Coating Chamber 1.2-m Atmospheric Telescope 30-m Dome 350-ton Telescope Base Facility Operations Support Data Access Center WBS Name 04CTelescope and Site Construction 04C.00T&S Level 2 Milestones 04C.01Telescope System Management 04C.02Telescope System Engineering 04C.03Summit Facilities and Infrastructure 04C.04Dome 04C.05Telescope Mount 04C.06Mirror Systems 04C.07Wavefront and Alignment Systems 04C.08Calibration System 04C.09Reflective Coating System 04C.10Observatory Control System 04C.11Telescope Control System 04C.12Utilities and Support Equipment 04C.13Base Facility and Infrastructure 04C.14Telescope Integration and Test

3 Second Safety Council Meeting Tucson, AZ April 10-11, The Dome System

4 Second Safety Council Meeting Tucson, AZ April 10-11, Numerous design shapes analyzed during the development cycle − Roll-off/retracting design rejected due to stray light − Rectangular too inefficient; Calotte deemed too risky − Final comparison of carousel vs. spherical − Carousel design chosen after analysis – Simplified fabrication/erection & cost effective – Better dome ventilation

5 Second Safety Council Meeting Tucson, AZ April 10-11, Baseline design sized to safely support all handling operations via 20-ton crane M1M3 Mirror Cell on Cart with cover above

6 Second Safety Council Meeting Tucson, AZ April 10-11, Design improvements included after discussions with potential vendors − Camera removal similar to VISTA instrument procedure − Remove through back doors to maintain aperture integrity

7 Second Safety Council Meeting Tucson, AZ April 10-11, Dome system to be procured via fixed price design/build contract − Design review May − RFP in July − Award in late 2014 − Design review cycles in SOW − Performance specification − Merge contract into PMCS shedule