Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach1 ILC Detector Strategy Questions Some of us have been wondering about the fundamental.

Slides:



Advertisements
Similar presentations
SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Advertisements

K. Potter RADWG & RADMON Workshop 1 Dec WELCOME TO THE 4th RADWG & RADMON WORKSHOP 1 December 2004.
Considerations on ILC Crossing Angle K. Yokoya LCWS13, BDS, Tokyo Univ. 2013/11/12 LCWS Yokoya1 Motivation Gamma-gamma collider CLIC.
Positron Source Update Jim Clarke Deepa Angal-Kalinin James Jones Norbert Collomb At Daresbury Laboratory and Cockroft Institute 21/07/2009.
Global Design Effort Goals and Introduction Andrei Seryi, SLAC, September 17, 2007.
SiD assembly Marco Oriunno (SLAC), May. 14, 2014 ALCW 2014, Fermilab Infrastructures & Timeline for Hybrid Access.
Global Design Effort Detector concept # Plenary introductory talk IRENG07 Name September 17, 2007.
1 DOE Annual Review -June 15,2005 An Overview of Conventional Facilities (Civil Construction) U. S. ILC Civil studies and cost issues for Snowmass Fred.
Fringe Field in DH Marco Oriunno (SLAC), January 13, 2015 SID Workshop 2015, SLAC.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
Construction and Installation of the CLIC Experimental Area
Status of ILC Barry Barish Caltech / GDE 17-Aug-07.
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
1 GLD Surface Assembly Y. Sugimoto KEK
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
CES Status J.Osborne 6 November 2009 Status Report from Civil Engineering and Services Working Group J.Osborne GS/SEM for CES Working Group.
1 Alternative assembly option of ILD Y.Sugimoto 2010/10/18 ILD Integration
Experimental hall in Japanese mountain site Y. Sugimoto 1.
1. Civil Engineering works for Linear Colliders* : -Brief introduction on the overall machine layout (just for CLIC at this stage) -Experimental Area.
October 13, 2006 Global Design Effort 1 International Linear Collider Machine Detector Interface Materials for discussion at Engineering Forum: experiences.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
September 18, 2007H. J. Krebs1 SiD Collaboration One Piece End Door Design Concept plus Forward Equipment Interfaces H. James Krebs SLAC September 18,
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
KEK Hiroshi Yamaoka Task list for Magnet/Iron yoke Solenoid magnet Iron yoke Experimental hall and other facilities May 11, ’05.
Date Event Global Design Effort 1 ILC UPDATE Vancouver to Valencia Ewan Paterson Personal Report to SiD Collaboration Oct 27, 2006.
MEA Machine and Experiment Assembly 1 Norbert Meyners, MEA Engineering Forum at CERN 12.Okt Thoughts about LDC Hall and Assembly (Work is not finished.
Si D in 14mrad/14mrad/z=0 ILC T. Markiewicz/SLAC SiD Advisory Group 14 August 2006.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions Ewan Paterson Technical Board June 23,
ORKA Preservation Task Force ORKA Preservation Task Force first meeting Wednesday, February 8, Notes by Peter H. Garbincius Notes from meeting are.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
1 BDS and Detector schedules for discussion at MDI meeting August 15, 2006 Andrei Seryi with input from Martin Gastal, Yasuhiro Sugimoto et al.
A. Hervé - 17 Oct CLIC-Workshop CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN.
1 SiD Push-pull Plans Marco Oriunno, SLAC International Workshop on Linear Colliders 2010 Geneva, October 2010 M.Oriunno, IWLC10 – Geneva, Oct.2010.
Global Design Effort - CFS TILC08 Working Group 1 - March 5, CFS Cost Reductions Conventional Facilities and Siting Group A. Enomoto, V.
1 Target Station Design for Neutrino Superbeams Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory NBI 2012, CERN.
RICH1 Gas Enclosure Installation. Experimental Area Meeting at CERN on 21st June 2006 Bill Cameron (Imperial College London) on behalf of the RICH1 team.
3/20/11 ALCPG11 Global Design Effort 1 CFS Detector Hall Considerations Tom Lackowski.
Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.
MEA Machine and Experiment Assembly Norbert Meyners, MEA 17. Sept. 2007ILC IRENG07; SLAC1 LDC Engineering Design (Status)
Global Design Effort - CFS DESY Accelerator Design and Integration Meeting 1 ACCELERATOR INTEGRATION AND DESIGN MEETING CONVENTIONAL FACILITIES.
GLD experimental hall and detector assembly Y.Sugimoto KEK 27 Sep
Philip Burrows MDI Panel Meeting 15/08/06 Philip Burrows John Adams Institute Oxford University SiD and IR/MDI Issues.
1 May 22, Y.Sugimoto Update of detector hall in mountain region.
CLIC MODULE TRANSPORT AND INSTALLATION Keith Kershaw CES, 8 October 2008.
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
LARP Review, June 12-14, 2006 Prebys, Todesco, Zisman 1 Accelerator Systems Eric Prebys Ezio Todesco Mike Zisman.
PHG - Detector Estimates - Daresbury - July 12-13, 2010 ILC - Global Design Effort 1 What is included in the Cost Estimates for the ILC Detectors? Peter.
MEA Machine and Experiment Assembly Norbert Meyners, MEA 12. July 2007ILC IRENG07 WG-A1 LDC Engineering Design (Status) Introduction General Design Detector.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
12 July 2007IRENG07 WG-A M. Breidenbach1 SiD Concept SiD is relatively modest in scale compared to the LHC detectors, and comparable to SLD: Tracker Radius.
Implication of gamma-gamma on 14mr tunnels discussion (questions for discussion with WG-C and WG-A) Valery Telnov Budker INP IRENG07, Sept.19, 2007, SLAC.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
SuperB Experimental hall General considerations on the Babar experimental area Preliminary space requirements hall proposal. A floor plan. Specification.
An idea of ILD general assembly plan 2015/10/8 Yasuhiro Integration Meeting 1.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
Experimental Hall in Mountain Regions
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
Marco Oriunno (SLAC), March 12, 2014 MDI WG
Experimental hall design in Japanese site
Interaction Region Alternative Layouts
Integration Ideas for the Central Region Some old some new
Accelerator and Experiment Interface Session: LS2, LS3
Detector hall in mountain regions
CLIC Civil Engineering Update
Detector hall in mountain regions
Extract from today’s talk given to DCB
RDR Baseline Layouts for Interaction Region
Some of the Points Raised During my JLAB Visit
Presentation transcript:

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach1 ILC Detector Strategy Questions Some of us have been wondering about the fundamental assumptions that seem to have been accepted – and are shaping the thinking about the interaction region for ILC. This is an early and perhaps biased set of questions… … and I (Norbert) have tried to answer.

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach2 Beneficial Occupancy We have been assuming that useful occupancy of the underground volume does not occur until shortly before beam. Why??? We were forced by the civil engineers. Be aware that both tunnel boring machines end in the experimental hall. What are the overall economics of having the collision hall available for detector assembly and beamline assembly 2 to 3 years before beam? –We have been assuming that magnetic measurements (which may be somewhat distinct from coil testing) occurs on the surface, and then the detector gets moved – in some set of pieces – to the hall. Maybe this is not a great idea? With a surface assembly a la CMS I am not so much concerned. (You have to open the detector for maintenance anyhow.) But with a GLD style surface assembly I share your doubts. –Would underground assembly have real advantages if the facility was available early enough? YES!

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach3 Large Shaft –We have been assuming that huge shafts are needed to lower big detector systems. Consider MINOs: MINOS is a neutrino detector constructed deep underground at the Soudan mine. Minos has ~5.4 KT of iron. The Soudan shaft is inclined at 7 0. The Soudan cage has a base of ~1.2 m by 1.9 m, and a capacity of ~6T. –The largest SiD unit appears to be the solenoid. It would fit down a shaft 6 x 7 m, and weighs ~160 Tonnes. –The barrel iron segments would fit this shaft, and weigh ~375 Tonnes. –An early, preliminary possibility is that a small shaft and 400 Tonne cranes above and below might be adequate.

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach4 Cavern Shape and Configuration How much of thinking of the underground shape of the cavern is based on CERN geology? Would larger cranes cost less in other rock? It would surprise me! Are two shafts required for safety? Yes and availability! Could the secondary escape way be into a beam line? Not today after the experience of several accidents in tunnels (Mont-Blanc-Tunnel (24. March 1999), Kaprun/Kitzsteinhorn (11. Nov. 2000), …) Could the shafts (if there are two) be over the garage position? NO! Is the major reason for offsetting the shaft safety? YES! And the stairs in the shaft!

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach5 Deep Caverns This is politically incorrect – so please do not pay any attention to this slide. –Is it only politics that we are limited to deep sites? Good question! Lack of interest and manpower? (at DESY?) –A first look at radiation indicates that a slightly buried linac – ie the top of the housing at grade, with the housing then buried under the excavated soil, is adequate for normal beam loss and accident scenarios. This would require a very flat site. This might save money. The unofficial statement was that the shallow DESY sample site would cost the same as a deep site. (It’s hard to believe this! People that had worked on the TESLA proposal were surprised.) Such a site is not on the approved list. In one of the last ILC news Barry made the point that it will be a task for the RDR. This might permit a shallow hall. –Especially with the need of a service tunnel for the klystrons and modulator a SLAC-like solution looks very charming.

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach6 LHC Influence The LHC has enormous issues of radiation and rates, and makes the LHC detectors very challenging. ILC should have rate and radiation issues only very far forward where e + e - pairs are an issue, and should have a low rate, low radiation environment elsewhere. Except the beam dumps! Are there any issues with self-shielding? –A concern is that the detector endcaps nominally are planes normal to the beam. The detector volumes ~look at the beamline. Is this an issue if the beam were to target a beamline component? –Are there other issues? Self-shielding would work! Holes or gaps can be covered by chicanes. Large cable plants coming off the detector are natural at the LHC. Are such plants needed for detectors at the ILC? At least some! (Do not under estimate the supply lines (power, gas, cooling)) Separate shielded areas for support facilities (e.g. power supplies) are needed at LHC. Not for all! At CMS a lot of power supplies are at yoke! Can they be more closely associated with the detector structures at ILC? Yes, but where is the space? What about vibrations? It would appear that all data from a detector could be transmitted on modest numbers of fibers? Yes! Should detector control rooms be located on the surface? Yes or Elsewhere? (“Global Experiment Network”)

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach7 Platforms and Push-Pull Platforms seem to make the interface issues easier, but they increase the depth of the hall below beamline. Depending on the site you may get it for free! Are there technical risks that are increased by the platform approach – assuming that cable plants and other services are small. The risks lie in the push-pull approach! As the time required to effect a detector interchange increases, the frequency of interchange will decrease to maximize luminosity. When do the sociological issues become problematic? They are already a problem, but we have not yet notice because we do not have real collaborations. Does a slow interchange push towards an eventual one detector outcome? Yes! What are the fundamental limits for interchange time? Reliable and safe moving! –Is it obvious that a detector solenoid must be run down? No!

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach8 ILC Beams The ILC beams are quite small transversely. Is adequate attention being paid to vibration? Not yet! The ILC beam is quite short longitudinally. Is adequate attention being paid to EMI? People are aware of the problem!

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach9 Seismicity We do not have a site yet. What if ILC winds up in Japan? Or California? We will be happy to build it and solve all the problems we identify beforehand. Have you ever seen a machine that has reached its single design values (vibration, alignment, etc.)? But most of them reached their goals in the important terms like luminosity, results or discoveries. Or?

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach10 Detector Maintenance What scale of maintenance should be possible on beamline? –Access to the exterior of the detector during operation has been assumed by SiD. –Door opening of ~2 m is assumed. Is this adequate, particularly if there is a shift to “plug” style door? May be not! It’s tight! Might this affect hall width? Of course! What scale of maintenance should be possible off beamline? –If a detector requires major maintenance, can it interfere with the other detector? Depends on the hall size! –It seems that the ability to access the VXD is required, and this probably means removing the tracker. Is this the limit of major maintenance, YES! or should there be the possibility of even removing the solenoid? No, but there might be sufficient space! –Will crane motion interfere with machine operation? Hopefully not! It’s a point for the vibration list!

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach11 Summary These are a few questions that have been worrying us. There will be more. These seem to affect fundamental strategy for the IR. At this time, should we be making decisions or developing options? We should develop options to prepare decisions!

Replies by N.Meyners (in green) 27 August 2007ILC Questions M. Breidenbach12 Summary (N.Meyners) You did not question the fundamental assumptions that are the base for the push-pull solution: –That it would take days to re-establish a beam line –It is not possible to serve two detectors on a train by train base (i.e. 5Hz) –That we need to save ~500 Million ILC-units (~6% of total cost ) The detectors are half of the game. If they do not work or can not be maintained, repaired and upgraded the whole accelerator is or becomes nearly useless! So I do not understand why the detector have to go to the limit in saving money. –We even try to save money before we know costs and consequences? –Why do we have to discuss extensively hall width and depth at this stage of the project? (We need some assumptions for the costs, but this is do for the moment. And we save 500Mbugs I am not willing to discuss some kbugs at the moment.) We should at the moment concentrate on technical issues. Develop solutions, validate them and continue with the one, two, three most convincing one or?