Project Scheduling: Networks, Duration Estimation, and Critical Path

Slides:



Advertisements
Similar presentations
Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Advertisements

Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 6: Developing a Project Plan
Project Management 6e..
Chapter 17 Project Management McGraw-Hill/Irwin
Developing the Project Plan
Where We Are Now Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved.
Project Management Project Management
Developing a Project Plan
Project Scheduling: Lagging, Crashing, and Activity Networks
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2.
Developing a Project Plan
1 University of Wales Bachelor of Science (Industrial Engineering and Management) Year 3 Copyright © 2012 MDIS. All rights reserved.Section
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Chapter 4: Schedule, cost, and situation analysis (pt. 1) ISE 443 / ETM 543 Fall 2013.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 © 2007 Pearson Education.
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
ELC 347 project management
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 15.
Project Scheduling: Networks, Duration estimation, and Critical Path
Project Time Management
Operations Management Contemporary Concepts and Cases Chapter Fourteen Project Planning and Scheduling Copyright © 2011 by The McGraw-Hill Companies,
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6.
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall8-1 Cost Estimation and Budgeting.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Developing a Project Plan
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Chapter 4 MIS Project Management Lecturer Sihem Smida Sihem Smida Developing a project plan.
9-1 ELC 347 project management Day 19. Agenda Integrative Project –Part 4 Due –Part 5 Due Nov 24 (page 342) –Any of the first five sections can be resubmitted.
Managing the Information Systems Project Cont’d
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management MGT 30725
Project Scheduling KULIAH 10 Magister Sistem Informasi
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
P.I.I.M.T American University of Leadership
Project Scheduling KULIAH 10 Magister Manajemen
Project Planning & Scheduling
Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Developing a Project Plan
Project Scheduling: networks, duration estimation, and critical path
PROJECT SCOPE, SCHEDULE, AND RESOURCE MANAGEMENT
ENM448-Project Planning and Management
Project Time Management
Project Scheduling: Lagging, Crashing and Activity Networks
Project Time Management
ELC 347 project management
Lecture 5: Project Time Planning (Precedence Diagramming Technique)
Slides Prepared by JOHN LOUCKS
Project Time Management
Project Time Management
Planning and Managing Projects
Project Time Management
Presentation transcript:

Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Project Scheduling: Networks, Duration Estimation, and Critical Path

Chapter 9 Learning Objectives After completing this chapter, students will be able to: Understand and apply key scheduling terminology. Apply the logic used to create activity networks, including predecessor and successor tasks. Develop an activity network using Activity-on-Node (AON) techniques. Perform activity duration estimation based on the use of probabilistic estimating techniques.

Chapter 9 Learning Objectives After completing this chapter, students will be able to: Construct the critical path for a project schedule network using forward and backward passes. Identify activity float and the manner in which it is determined. Calculate the probability of a project finishing on time under PERT estimates. Understand the steps that can be employed to reduce the critical path.

Project Scheduling Project scheduling requires us to follow some carefully laid-out steps, in order, for the schedule to take shape. Project planning, as it relates to the scheduling process, has been defined by the PMBoK as: The identification of the project objectives and the ordered activity necessary to complete the project including the identification of resource types and quantities required to carry out each activity or task.

Project Scheduling Terms Successors Predecessors Network diagram Serial activities Concurrent activities E D C B A F

Project Scheduling Terms Merge activities Burst activities Node Path Critical Path E D C B A F

Network Diagrams FIGURE 9.2  Alternative Activity Networks for Term Paper Assignment Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

AOA Versus AON …and activities on node. The same mini-project is shown with activities on arc… E C D B F …and activities on node. C E D B F

Node Labels Early Start Activity Float Activity Descriptor Late Start ID Number Activity Duration Late Finish Early Finish

Activity Node Labels Using MS Project 2010 FIGURE 9.4   Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Serial Activities Serial activities are those that flow from one to the next, in sequence. FIGURE 9.5   Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Activities Linked in Parallel (Concurrent) When the nature of the work allows for more than one activity to be accomplished at the same time, these activities are called concurrent and parallel project paths are constructed through the network. FIGURE 9.6   Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Merge Activity FIGURE 9.7  Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Burst Activity FIGURE 9.8  Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Complete Activity Network FIGURE 9.10  Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Developing the Activity Network Using MS Project 2010 FIGURE 9.11  Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Duration Estimation Methods Past experience Expert opinion Mathematical derivation – Beta distribution Most likely (m) Most pessimistic (b) Most optimistic (a) Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

FIGURE 9.14 Symmetrical (Normal) Distribution for Activity Duration Estimation Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

FIGURE 9.15  Asymmetrical (Beta) Distribution for Activity Duration Estimation Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Activity Duration and Variance Table 9.2 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Constructing the Critical Path Forward pass – an additive move through the network from start to finish Backward pass – a subtractive move through the network from finish to start Critical path – the longest path from end to end which determines the shortest project length

Rules for Forward/Backward Pass Forward Pass Rules (ES & EF) ES + Duration = EF EF of predecessor = ES of successor Largest preceding EF at a merge point becomes EF for successor Backward Pass Rules (LS & LF) LF – Duration = LS LS of successor = LF of predecessor Smallest succeeding LS at a burst point becomes LF for predecessor

Project Delta Information Table 9.4 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

FIGURE 9.16 Partial Project Activity Network with Task Durations Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

FIGURE 9.18 Activity Network with Forward Pass Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

FIGURE 9.19 Activity Network with Backward Pass Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

FIGURE 9.20 Project Network with Activity Slack and Critical Path Note: Critical path is indicated with bold arrows. Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

AON Network with Laddering Effect FIGURE 9.24  Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Laddering Activities ABC=18 days Laddered ABC=12 days Project ABC can be completed more efficiently if subtasks are used ABC=18 days A(3) B(6) C(9) A1(1) A2(1) A3(1) B1(2) B2(2) B3(2) C1(3) C2(3) C3(3) Laddered ABC=12 days

Example of a Hammock Activity FIGURE 9.25   Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Reducing the Critical Path Eliminate tasks on the CP Convert serial paths to parallel when possible Overlap sequential tasks Shorten the duration on critical path tasks Shorten early tasks longest tasks easiest tasks tasks that cost the least to speed up

Summary Understand and apply key scheduling terminology. Apply the logic used to create activity networks, including predecessor and successor tasks. Develop an activity network using Activity-on-Node (AON) techniques. Perform activity duration estimation based on the use of probabilistic estimating techniques.

Summary Construct the critical path for a project schedule network using forward and backward passes. Identify activity float and the manner in which it is determined. Calculate the probability of a project finishing on time under PERT estimates. Understand the steps that can be employed to reduce the critical path.

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall