February 2009 Summary of Chamonix 09 Steve Myers.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
February 2009 Summary of Chamonix 09 Steve Myers.
CERN: important events Restart of the LHC: –First beam on 20 November at 0.45 TeV –First collisions on 23 November, followed by slowly ramping up the beam.
1 Where to Search for the Higgs  A direct search for the Higgs was carried out by the four LEP experiments from CMS energy of GeV The.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
The LHC: an Accelerated Overview Jonathan Walsh May 2, 2006.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Expected Quench Levels of the Machine without Beam: Starting at 7 TeV ? P. Pugnat CERN, Geneva, Switzerland LHC Project Workshop Chamonix XV, Tuesday 24.
WLCG Collaboration Workshop, “Gotham City”, May 2012 Introduction WLCG Collaboration Workshop, “Gotham City”, May 2012 Introduction.
6 February 2009 Summary of Chamonix 09 S. Myers. Topics for Discussion/Decisions –Road Map and Schedule –Repair Scenarios (two) –Dipole Field for Operation.
LHC Status ReportLHC Status Report Lyn Evans 96 th LHCC meeting, CERN 19 th November 2008.
A. Verweij, TE-MPE. 3 Feb 2009, LHC Performance Workshop – Chamonix 2009 Arjan Verweij TE-MPE - joint stability - what was wrong with the ‘old’ bus-bar.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
Eric Prebys APC/LARP The truth is out there! 2/9/2009.
Introduction to availability modelling in ELMAS Arto Niemi.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
LHC Performance Workshop - Chamonix February 2009 Jim Strait Fermilab Risk Analysis for the Different Consolidation Proposals.
Linac2 Review  L2 operated with 99 % uptime in 2010 and 98% in the last 10 years  Systems review: all under control even for L2 till LS2 if ‘nightmare’
1 Copper Stabilizer Continuity Measurement Project Copper Stabilizer Continuity Measurement Status & Plans – May 2011 MPE-TM – 12 May 2011 M. Koratzinos,
India-CERN Meeting in Mumbai (Visions for Future Collaborations) Steve Myers Director of Accelerators and Technology CERN.
Preparation of Review R. Assmann et al CWG, CWG R. Assmann.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, slides  Status of LHC: electrical connections  Description of shunt.
Consolidation and Upgrade plans for the LHC Vacuum System
Session 7: I-LHC Organization: Chamonix Summary Session7; Oliver Brüning 1 -session organized in collaboration with D. Manglunki and all speakers.
LHC Enhanced Quench Protection System Review 24 – 26 February 2009.
M. POJER, ON BEHALF OF THE USUAL BUNCH OF SUSPECTS… S UPERCONDUCTING CIRCUITS RE - COMMISSIONING AFTER THE 2011 C HRISTMAS BREAK.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Running scenario 2009/10 Run through components – and then synthesis.
T. LeCompte Argonne National Laboratory Evolution of the Run Plan.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
Eric Prebys/LARP 2/17/2016.  CERN has taken unprecedented steps to control information about this event, including altering the electronic LHC log to.
1 LHC and CMS Status Robert M. Harris Fermilab Fermilab All Experimenters Meeting Nov. 10, 2008.
J.M. Jowett, S. Maury, PANIC05 HI Satellite meeting, 23/11/ LHC as a Heavy-Ion Collider An update John M. Jowett, Stephan Maury I-LHC Project CERN.
[R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] HWC Workshop ( ) Consolidation and major changes that have impact on the powering circuits.
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
1 LHC Status LHCC 23 rd September 2009 Steve Myers.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
TE-CRG Activities D. Delikaris, TE-CRG.
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
LHCf collaboration meeting, Nagoya, January 2009A. L. Perrot LHC news A. L. Perrot CERN, EN/MEF-LE LHCf collaboration meeting, Catania, 6 th July 2009.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
1 Chamonix 09 Highlights J. Wenninger BE-OP Chamonix 09 Highlights.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
LHC Operation with Beam and Chamonix Outcome (on behalf of the LHC team) LHCC February 17, 2010 (most slides from Steve Myers, LHCC )
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
HL-LHC IT STRING and Series test of SC link
S. Roesler (on behalf of DGS-RP)
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
LHC schedule.
12 October 2009 RRB Plenary R.-D. Heuer
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
Accelerator and Experiment Interface Session: LS2, LS3
LS2 session J.M Jimenez, J.-P. Tock, K. Foraz 24/11/2017
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
LHC Beam Operations Past, Present and Future
MEIC Cost Estimate Overview
LHC status & 2009/2010 operations
Review of hardware commissioning
Presentation transcript:

February 2009 Summary of Chamonix 09 Steve Myers

Topics for Discussion/Decisions –Schedule –Repair Scenarios –Dipole Field for Operation –“Precautions for Running” –Beam Conditions for Physics –Future Improvements for increased availability

With Strictly No running of the machines in the winter months –Present baseline schedule schedule allows very limited physics in 2009/2010 (24 weeks) Any slip of >1 month in the S34 repair will delay first LHC physics till August/September 2010!! Repair schedule has no contingency Must have the possibility of running during winter months Physics Running Time

Gains 20 weeks of LHC physics (independent of “slip”) Schedule with running in winter months

Today’s cheapest applicable EDF Tariff Planned Operation Today’s Operation

Electrical Costs!! –Assuming Full running through December to February – dedicated running of the injectors during winter and –reduced cryo power from 8MW to 5MW → additional electricity bill of 8MEuros (+ possible 8%) Impact on Scheduled Shutdown Work on other CERN accelerators »POPS (PS motor Generator) »LINAC4 connection to PSB »… Impact on Necessary Maintenance »Cooling towers »Electrical Network Impacts of Running During Winter Months ( )

FIRST PROPOSAL Pay for Electricity for Running in Winter

DN200 Pressure Relief Valves in Arcs December 2008 Repair Scenarios Enhanced Quench Protection (Detection) Busbar Detection (Protection) “Symmetric” quench protection The FULL Quench System must be operational for beam collisions in (unanimously agreed) B: Installation 8 sectors (09-10) + reduced amount of collateral damage in event of a splice problem in reduced additional electricity bill + reduced overall shutdown time + reduced ALARA problems (2 nd order) A: install 4 sectors (09-10) + 4 sectors (10-11) + present schedule allows calorimetry measurements in 23, 45 much sooner + first physics sooner: detectors debugging.. earlier warning + first beam sooner: ramp, squeeze,.. Sooner... earlier warning + focuses attention of repair teams No consensus in Chamonix

–Key Drivers for schedule; –Safety constraints, access, transport,… –Helium storage –Maintenance: cooling towers, electrical network… –Cryo maintenance, PIMs… Discussion on Schedule We are working on these issues both for the present shutdown and future ones

Summary on Schedule Here it is assumed that these shutdowns will be long enough in case of problems seen during the prededing PH running Here it is assumed that these shutdowns will be long enough in case of problems seen during the preceding PH running Earlier PH may be possible due to changes in safety constraints and additional shifts for power testing Immediately after Chamonix the management decided on scenario A

Dipole field which can be reached Time needed, reliability, and efficiency Risks associated with operating at field Splices stability (thermal runaway…) Detection of poor splices (see later) Operational efficiency of other systems Cryo recovery time etc Energy Level for Operation

A. Verweij, Sector 1 st training quench [A] I_max [A] # training quenches Starting in: # ALS# ANS# NOE (bus) Dipole quenches during HWC Excluding S34, all sectors reached 8965 A (5.3TeV) without a quench Excluding S34, all sectors reached 9310 A (5.5TeV) with 1 quench

A. Verweij, Sector Number of magnetsNumber of quenches 6 TeV 6.5 TeV (±30%) Total Estimated dipole training to reach 6 and 6.5 TeV Estimated 11 (84) quenches to reach 6 (6.5) TeV

A. Verweij Setting for the new QPS upgrade 5TeV (~60) 4TeV 6TeV (~40) Remember 1V previously! This simulation result is critical for our decision and should be independently confirmed 5TeV 4TeV 220nOhms

Beam Conditions for Physics Conclusion 5TeV/beam for Physics Machine Protection will be Tested with beam (at 0.5TeV energy levels) 4 TeV “on the way” to 5TeV (limited in 2010) Estimated integrated luminosity during first 100 days of operation.. ≈ 100pb-1 »Peak L of η (overall) = 10% gives 0.5pb-1/day »Peak L of η (overall) = 10% gives 2.0pb-1/day During next 100 days of operation.. ≈ 200pb-1? Then towards end of year ions (to be planned in detail soon)

Precautions before Running with Beam Pre-detection of Poor splices in untested sectors –Analysis of SM18 data + calorimetry at 7kA –Early running of S23 and S45 (weekend calorimetric run in April/May??) QPS fully operational ☺ QPS in event of trip of UPS ☺ Quench Protection during magnet ramp down ☺ Pressure valves in DFBs and inner triplets Protect RF and injection kickers (vacuum valves) Water cooled cables Anomalies in electric circuits (K-H. Mess) Xray machine available Aug/Sept ?sooner Undulator (left of point 4) availability and necessity

Precautions for Running 2 Long Straight sessions: clarification ? Automation of the calorimetry measurements Complete set of Omhic measurements of all splices during Power Tests and Cold check-out MQM praying hands splices? Change ?

Future Improvements Spares, spares, spares SEU; continuation of protection Helium storage ARCOM-RAMSES replacement Improvement in controlled access system MQM praying hands splice to be replaced Cooling Tower maintenance (LEP/LHC HVAC) Vacuum consolidation to reduce collateral damage in case of splice rupture Clamping of busbar splices, development followed by campaign of replacements? Use of new xray machine Centralised radiation workshop

Closing Remarks The Chamonix yearly retreat is crucial –Seeds planted for several collaborations machine-physics groups Strong Recommendations –Beam physics running during winter –Long running period of 11 months is possible –Enhanced QPS system fully operations for run –10TeV cm; > 200pb-1 (goodbye to competition) –Ions at the end of the proton run Future Work-Plan established –Preparation for run (safely and reliably) –Longer term to convert LHC into an “operational” machine Chamonix 2010 already planned!