1.040/1.401 Project Management Spring 2007 Lecture 7 Dr. SangHyun Lee Department of Civil and Environmental Engineering Massachusetts Institute.

Slides:



Advertisements
Similar presentations
Construction Contracting
Advertisements

HEAT TRACING SPECIALIST
WBS-Construction of House (Example) WBS Dictionary
Construction Management. Players Owner – owns project upon completion of construction –Private – owner owns land and pays for construction of facility.
Project Activity Planning
CIVL202 Construction Engineering I Tutorial 8 T1Mon11:00 – 11:50 T2Wed09:00 – 09:50.
MANAGEMENT OF ENGINEERING PROJECT MANAGEMENT
NEES Project Management Workshop June 16 June 18 1 Segment 3.
John Boon ZUT November Procurement Systems The organisation of the interaction between the purchaser of a new building and the suppliers of goods.
Skyscraper Construction
Work Breakdown Structure.
Project Scope Management
/1.401/ESD.018 Project Management Lecture 20 Project Reporting Project Close-out Samuel Labi and Fred Moavenzadeh Massachusetts Institute of Technology.
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
Chapter 5: Project Scope Management
Project Management Session 7
Chapter 5: Project Scope Management
Types of Drawings University of Palestine Eng. Nagham Ali Hasan
Project Scheduling & Budgeting CEE 402 Engineers Without Frontiers Lecture 6 February 26, 2003.
PROJECT SCOPE, SCHEDULE, AND RESOURCE MANAGEMENT
XII- COST CONTROL, MONITORING & ACCOUNTING
Spring 2008, King Saud University Engineering Administration Dr. Khalid Al-Gahtani 1 What is a Project? “A Project is a one-shot, time-limited, goal- directed,
LSU 07/24/2004Defining Project Tasks1 Defining the Project Tasks Project Management Unit, Lecture 4.
Project Scope Management J. S. Chou, P.E., PhD.
Part II Project Planning © 2012 John Wiley & Sons Inc.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
CAPITAL COST ESTIMATES INSTALLED EQUIPMENT COSTS.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
1 Lecture 3.1: Project Planning: Work Breakdown Structure (WBS) [SEF Ch 9] Dr. John MacCarthy UMBC CMSC 615 Fall, 2006.
Module 6 Session 6.1 Visual 1 Module 6 Preparing the Work Breakdown Structure (WBS), Responsibility Matrix, and Master Summary Schedule Session 6.1 Preparing.
Chapter 5: Project Scope Management Information Technology Project Management.
1 Project Planning Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week 4 2 nd Semester 2008/2009 UP Copyrights 2008 Construction.
PLANNING AND SCHEDULING
© 2012 Cengage Learning. All Rights Reserved. This edition is intended for use outside of the U.S. only, with content that may be different from the U.S.
Switch off your Mobiles Phones or Change Profile to Silent Mode.
Managing Engineering Design - Infrastructure. Presentation Overview 1.Tools and Techniques 2.Design and Documentation 3.Estimating and Scheduling.
Rev. 0 CONFIDENTIAL Mod.19 02/00 Rev.2 Mobile Terminals S.p.A. Trieste Author: M.Fragiacomo, D.Protti, M.Torelli 31 Project Idea Feasibility.
Chapter 15 Construction Scheduling. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Identify.
Work Breakdown Structure (WBS) Development
Management & Development of Complex Projects Course Code - 706
Topic1b: Project Life Cycle
Lecture 6. Review of Lecture 5 Company strategic planning: mission and objective statements and competitive strategy. Planning Methods: Top-down, Bottom-up.
Resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 4 Project Scope Management.
Work Breakdown Structure Use and Demo
What is Project Management? What makes it different from a process, service or program?
Preparing the Bid Package (A Developers Perspective)
Copyright 2009 John Wiley & Sons, Inc. Chapter 6 Project Activity Planning.
Chapter 13 Project Management. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Define and give.
Project Management “Project Planning & Scheduling” Lecture 07 Resource Person: M. Adeel Anjum.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
GE 121 – Engineering Design Engineering Design GE121 Managing The Design Process Part II Lecture 11B.
SCOPE DEFINITION,VERIFICATION AND CONTROL Ashima Wadhwa.
CVE 4070 Construction Engineering Project Budget & Cost Control Prof. Ralph V. Locurcio, PE.
WBS Work Breakdown Structure © Unitec New Zealand.
Asset accounting-29.pptx This course will give an overview of the following Workbreakdown Structure Network Project Builder Project Planning.
SOFTWARE PROJECT MANAGEMENT
Copyright 2012 John Wiley & Sons, Inc. Part II Project Planning.
VARIOUS STAGES OF PROJECT THINKING PLANNING & SCHEDULING DATA COLLECTION STATUS UPDATING THROUGH NETWORK AND GIVING EARLY WARNINGS PAVE A PATH FOR SUCCESSFUL.
What is a Project? “ Unique process consisting of a set of coordinated and controlled activities with start and finish dates, undertaken to achieve an.
Estimating and Scheduling CEE 492
Copyright 2015 John Wiley & Sons, Inc. Project Planning Part II.
TECM 3200 Dr. Lam.  Students will know how to complete a work breakdown structure (WBS)  Students will know how to complete a project schedule.
Fundamentals of Project Management and Schedule Development.
Creating a Work Breakdown Structure with Microsoft Project.
MENG 446 : Management of Engineering Projects
Module nine PMP® Mastery 2016 APMG Create WBS
Project Management BBA & MBA
1.040/1.401 Project Management Spring Supporting Information for AS #3
Presentation transcript:

1.040/1.401 Project Management Spring 2007 Lecture 7 Dr. SangHyun Lee Department of Civil and Environmental Engineering Massachusetts Institute of Technology Planning Basics

Project Management Phase FEASIBILITY CLOSEOUT DEVELOPMENT OPERATIONS Fin.&Eval. Risk Estimating Planning DESIGNPLANNING Organization

Outline  Planning – Hierarchical Project Structures  Work Breakdown Structure  Organization Breakdown Structure  Cost Breakdown Structure

Planning Components What: Work Breakdown Structure What: Work Breakdown Structure How: Plans and Specifications How: Plans and Specifications Who: Organization Breakdown Structure Who: Organization Breakdown Structure How much: Cost Breakdown Structure (via estimate) How much: Cost Breakdown Structure (via estimate) When: Schedule When: Schedule

Outline  Planning – Hierarchical Project Structures  Work Breakdown Structure  Organization Breakdown Structure  Cost Breakdown Structure

Work Breakdown Structure A WBS is a deliverable-oriented grouping of project components that organizes and defines the total scope of the project A WBS is a deliverable-oriented grouping of project components that organizes and defines the total scope of the project Work not in the WBS is outside the scope of the project Work not in the WBS is outside the scope of the project WBS is usually an operative tool used by contractors WBS is usually an operative tool used by contractors First step towards constructing a schedule First step towards constructing a schedule Central role in project monitoring and control Central role in project monitoring and control

WBS: Example Source: Shtub et al., 1994 different summary level

Work Package Lowest level Lowest level Distinguish from Others Distinguish from Others Single Responsible Organization Single Responsible Organization Assigned Start and Finish Assigned Start and Finish Assigned Budget Assigned Budget Limited Duration Limited Duration

Types of WBS Project WBS Project WBS Operative tool for monitoring and control contractor work Operative tool for monitoring and control contractor work Contractual WBS Contractual WBS Defines the level of reporting that the seller will provide the buyer Defines the level of reporting that the seller will provide the buyer May include less detail than Project WBS May include less detail than Project WBS Agreed between owner and contractor Agreed between owner and contractor

level 0 level 1 level 2 level 3 level 4 level 5 Functional Approach GAS-STEAM COMBINED POWER PLANT MAIN FUNCTIONS OF PLANT UNITS GAS INTERFACES STEAM TURBINE COMPRESSION STATION GENERATOR COMPRESSORS ENCLOSURE GAS TREATMENT SUB-UNITS WORK PACKAGES ITEMS COMPRESSOR 1 FOUNDATIONS COMPRESSOR 2 DESIGN INSTALLATION PROCUREMENT

Physical Space Approach Project Project Main building Main building 1st floor 1st floor Structures Structures Plumbings Plumbings Electrical Electrical HVAC HVAC 2nd floor 2nd floor Service building Service building Structures Structures Plumbings Plumbings Electrical Electrical HVAC HVAC

Procedure Approach Project Project Feasibility Feasibility Design Design Basic Basic Detail Detail Bid documents Bid documents Shop drawings Shop drawings Bid Bid Construction Construction Foundations subcontract Foundations subcontract Main building Main building Piles Piles Concrete foundations Concrete foundations Service building Service building Piles Piles Concrete foundations Concrete foundations Steel erection Steel erection Finishings Finishings Commissioning Commissioning

WBS: CSI Master Format - Example Source: Schaufelberger et al., 2002 Sample

Outline  Planning – Hierarchical Project Structures Work Breakdown Structure Work Breakdown Structure  Organization Breakdown Structure  Cost Breakdown Structure

Organization Breakdown Structure Decomposition of necessary resources to perform job Decomposition of necessary resources to perform job Identification & organization of the resources responsible with carrying out activities associated with the project Identification & organization of the resources responsible with carrying out activities associated with the project Used to keep track of specific work assignments & resource allocations Used to keep track of specific work assignments & resource allocations

Organization Breakdown Structure Project resources Project resources Project management team Project management team Project manager Project manager Construction superintendent Construction superintendent Field superintendent Field superintendent Office manager Office manager Scheduler Scheduler Accounter/controller Accounter/controller Field engineer Field engineer Construction force Construction force Worker Worker Subcontractor Subcontractor Electrical Electrical Plumbing Plumbing Insulation Insulation Tankage Tankage Roads Roads

OBS/WBS Linkages Source: Shtub et al., 1994

Outline  Planning – Hierarchical Project Structures Work Breakdown Structure Work Breakdown Structure Organization Breakdown Structure Organization Breakdown Structure  Cost Breakdown Structure

Cost Breakdown Structure (CBS) Breakdown of the costs of the various components of the structure including all work done by the subcontractors Breakdown of the costs of the various components of the structure including all work done by the subcontractors Serves as a basis for subsequent monthly pay requests by the contractor Serves as a basis for subsequent monthly pay requests by the contractor Used to continuously compare costs as they actually occur with the budget Used to continuously compare costs as they actually occur with the budget

Cost Breakdown Structure (CBS) Source: Shtub et al., 1994

Two Main Approaches CBS = WBS CBS = WBS CBS is the project cost control structure CBS is the project cost control structure CBS ≠ WBS CBS ≠ WBS CBS is the corporate multi-project cost control structure CBS is the corporate multi-project cost control structure Usually the case of a firm that has an integrated cost control system Usually the case of a firm that has an integrated cost control system

Diverse Combinations WBS + OBS: Task assignments WBS + OBS: Task assignments CBS + OBS: Budget monitoring of crews, etc. CBS + OBS: Budget monitoring of crews, etc. OBS + Schedule: Time-specific crew assignments OBS + Schedule: Time-specific crew assignments CBS + Schedule: Cost monitoring CBS + Schedule: Cost monitoring