VISTA: The Telescope challenge Systems Engineering the Solution?

Slides:



Advertisements
Similar presentations
Options appraisal, the business case & procurement
Advertisements

© 2013 Cairn India Limited MEASURES TO BE TAKEN AT DESIGN STAGE FOR IMPROVING QUALITY GATED PROCESS Anirban Ghosh Senior Manager- Quality Assurance CAIRN.
PROJECT TITLE Project Leader: Team: Executive Project Sponsor (As Required): Date: Month/Day/Year 110/17/2014 V1.
S Y S T E M S E N G I N E E R I N G.
Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
VISTA as seen by the Prime Contractor Adrian Russell.
The System Development Life Cycle
© 2007 COPLAN AND COMPANY. All Rights Reserved. Permission granted for use by HIMSS membership. 1 Procurement Management Scott R. Coplan, PMP Educational.
All these Sky Pixels Are Yours The evolution of telescopes and CCD Arrays: The Coming Data Nightmare.
All these Sky Pixels Are Yours The evolution of telescopes and CCD Arrays: The Coming Data Nightmare.
System-wide issues Before we get to the telescope System integration and verification at the telescope Operations Maintenance and support.
NIR LOWFS for Keck and TMT Roger Smith & David Hale.
1 NGAO Instrumentation Studies Overview By Sean Adkins November 14, 2006.
1 DOE Annual Review -June 15,2005 An Overview of Conventional Facilities (Civil Construction) U. S. ILC Civil studies and cost issues for Snowmass Fred.
Software Engineering For Beginners. General Information Lecturer, Patricia O’Byrne, office K115A. –
Software Engineering For Beginners. General Information Lecturer, Patricia O’Byrne. – Times: –See noticeboard outside.
Pertemuan Matakuliah: A0214/Audit Sistem Informasi Tahun: 2007.
4. 2Object-Oriented Analysis and Design with the Unified Process Objectives  Explain the elements of project management and the responsibilities of a.
Sharif University of Technology Session # 4.  Contents  Systems Analysis and Design Sharif University of Technology MIS (Management Information System),
PMSS Final SOW May 22 nd, Statement of Work 2 GLENN RESEARCH CENTER PROJECT MANAGEMENT SUPPORT SERVICES (PMSS) The Contractor shall provide expert.
Microsoft Office Project Portfolio Server
 A project is “a unique endeavor to produce a set of deliverables within clearly specified time, cost and quality constraints”
The Software Development Life Cycle: An Overview
Sense of Initiative and Entrepreneurship This project has been funded with support from the European Commission. This [publication] communication reflects.
S/W Project Management
Introduction to RUP Spring Sharif Univ. of Tech.2 Outlines What is RUP? RUP Phases –Inception –Elaboration –Construction –Transition.
Utilities Planning Group CIP Tracking System Jim Broome, PE Chief Engineer.
Using IBM Rational Unified Process for software maintenance
Presentation EddiCam consortium, FF, Madrid 13/06/2002 Eddington programmatic status Fully approved by SPC as part of ESA’s science program as project.
CS 360 Lecture 3.  The software process is a structured set of activities required to develop a software system.  Fundamental Assumption:  Good software.
EARTO – working group on quality issues – 2 nd session Anneli Karttunen, Quality Manager VTT Technical Research Centre of Finland This presentation.
PROJECT TITLE Project Leader: Team: Executive Project Sponsor (As Required): Date: Month/Day/Year 6/25/2015 V2.
Workshop Mark Heggli Innovative Hydrology, Inc. Consultant to the World Bank Expert Real-time Hydrology Information Systems Module 6: Training, Operations.
MD Digital Government Summit, June 26, Maryland Project Management Oversight & System Development Life Cycle (SDLC) Robert Krauss MD Digital Government.
ALMA Software B.E. Glendenning (NRAO). 2 ALMA “High Frequency VLA” in Chile Presently a European/North American Project –Japan is almost certainly joining.
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
2 nd convergence workshop: introduction R. T. Schilizzi Penticton 22 July 2004.
PLANNING ENGINEERING AND PROJECT MANAGEMENT By Lec. Junaid Arshad 1 Lecture#03 DEPARTMENT OF ENGINEERING MANAGEMENT.
Writing requirements specifications. Why we need requirements specifications To give structure to your desires To avoid waste of resources To avoid slippage.
Sessions VI and VII Conclusions and summary Francois Besnus Session Chair Cape Town July 6, 2007.
GBT Focal Plane Array Development Program Steven White Program Manager.
A global approach to ELT instrument developments J.-G. Cuby for the French ELT WG.
FELT 1 Study of the capability and configuration of a fixed mirror Extremely Large Telescope (FELT) Low cost path to large telescope Primary concern is.
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
AURA New Initiatives Office. GSMT SWG Meeting L. Stepp, July 30, 2002 NSF Science Working Group Support Available from AURA NIO Available Personnel Current.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Department of Energy Office of Science  FY 2007 Request for Office of Science is 14% above FY 2006 Appropriation  FY 2007 Request for HEP is 8% above.
Software Requirements Specification Document (SRS)
Local Supports to IDR Discussion ATLAS Upgrade Week November 2014.
Project Management Processes for a Project
The SALT Development Committee Recommendations Regarding New Instruments (Matt Bershady) Rob Fesen Janusz Kaluzny Wolfram Kollatschney Darragh O’Donoghue.
Software Development Process CS 360 Lecture 3. Software Process The software process is a structured set of activities required to develop a software.
Lecture Notes - Richard Ssembatya1 Information System Project Management Lecture Five By Richard Ssembatya MSc. Cs, BSc CS, CCNA, IT Essentials, ICDL Institute.
Continual Service Improvement Methods & Techniques.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
AST3-NIR camera for the AST3-3 telescope for the Kunlun Infrared Sky Survey (KISS) Management and planning Julia Tims, Jon Lawrence 20 August 2015.
LECTURE 5 Nangwonvuma M/ Byansi D. Components, interfaces and integration Infrastructure, Middleware and Platforms Techniques – Data warehouses, extending.
Information Technology Project Management, Seventh Edition.
Localisation of Council Tax Support. Council Tax Support Purpose of the Report  Remind members of the background to the national abolition of Council.
Rob Connatser NSS Instrument Work Packages and XLPM.
Request for Information (RFI) for the provision of a Turnkey Project for an Enhanced Unattended Transmission Substation CORP3430 Date: 4th March 2016.
The System Development Life Cycle
Software Configuration Management
The Systems Engineering Context
The System Development Life Cycle
Lockheed Martin Canada’s SMB Mentoring Program
Systems Engineering for Mission-Driven Modeling
September 2015 – September 2017 Contractual obligations fulfilled & project on schedule and budget GA approval for both years 1st periodic report ‘approved’
MAORY Status of the project
Presentation transcript:

VISTA: The Telescope challenge Systems Engineering the Solution?

Systems Engineering at the Core of VISTA Design UK ATC Project Office Proposal “The purpose of VISTA is to conduct large-scale semi- automated surveys of the sky at IR and visible wavelengths. Our concept of VISTA is not a conventional 4m telescope with instruments. We regard VISTA as a single integrated camera with an IR and a Visible channel, in which the "telescope" is really the fore-optics.”

Phase A and Phase B Phase A proposal –Can VISTA actually be achieved for the Money? –Develop designs to level to demonstrate compliance with Science Requirements –Determine the best strategy for maximising functionality within budget and timescales –Agree Strategy and Deliverables before starting Phase B Phase B –Follows successful Phase A –Same personnel –Procurement –Testing –Integration –Commissioning Enhanced VISTA –Additional funding for full functionality

Cost v’s Change v’s Time 12 Dec 2000Scrutiny Panel Presentation4

Cost v’s Change v’s Time 12 Dec 2000Scrutiny Panel Presentation5 End Phase A

Cost v’s Change v’s Time 12 Dec 2000Scrutiny Panel Presentation6 End Phase A By the end of Phase A the design is essentially locked in

12 Dec 2000Scrutiny Panel Presentation 7 Design Development JIF Design Baseline resulting in f/2.5 primary Brainstorm of various layouts f/1 identified as potential cost saver f/1 and f/2.5 progressed to level demonstrating a clear advantage to the f/1 design Need to concentrate on one design MO recommended proceeding with f/1 design –scheduled Design Validation Review –VEB approved development of f/1 in interim as long lead procurement

12 Dec 2000Scrutiny Panel Presentation 8 VISTA Designs f/2.5 “ JIF design ” f/1 with both instruments mounted at cassegrain focus f/1 was clearly more cost effective –f/1 has tolerance issues on M2 Design still based on 3x3 array

12 Dec 2000Scrutiny Panel Presentation 9 The Design Validation Review Purpose –Review choice of design MO has identified f/1 type design as most suitable for VISTA Close out all design other optical layouts –Determine of choice is correct –Identify any issues in adopting this approach

The ESO involvement Who’s the Customer? Vista Consortium? ESO? Pros and Cons –Site –Standards Requirements SOWs Software definition Hardware definition –3x3 to 4x4 focal plane 12 Dec 2000Scrutiny Panel Presentation10

The ESO involvement Who’s the Customer? Vista Consortium? ESO? Pros and Cons –Site –Standards Requirements SOWs Software definition Hardware definition –3x3 to 4x4 focal plane 12 Dec 2000Scrutiny Panel Presentation11 Consortium ESO

The ESO involvement Who’s the Customer? Vista Consortium? ESO? Pros and Cons –Site –Standards Requirements SOWs Software definition Hardware definition –3x3 to 4x4 focal plane 12 Dec 2000Scrutiny Panel Presentation12 Consortium ESO

Filming “OO7: Quantum of Solace”

12 Dec 2000Scrutiny Panel Presentation 14 Paranal Geology Where is the bedrock? –Plateau 20m excavation –NTT 5m leveling What about construction? –Plateau: Dust, noise pollution What about Utilities? –Plateau £0.3m –NTT £0.5m

12 Dec 2000Scrutiny Panel Presentation15

The ESO involvement Who’s the Customer? Vista Consortium? ESO? Pros and Cons –Site –Standards Requirements SOWs Software definition Hardware definition –3x3 to 4x4 focal plane 12 Dec 2000Scrutiny Panel Presentation17 Consortium ESO

Requirements All requirements: –Shall be unambiguous and tied to performance metrics that are verifiable, achievable and realistic. –Shall not be solution specific, vague or impossible to verify. 12 Dec 2000Scrutiny Panel Presentation18

and Goals? Goals are not requirements. –Though they may become requirements Logical development (with additional resources, funding etc.) By osmosis – Spec creep Goals: –shall not be needed to achieve the science performance (that is a requirement). –Each goal must have an underlying requirement. –As soon as cost and/or schedule are compromised by a goal, the goal is either amended or dropped. –The only benefit of including a goal is during in the early stages of development, steering choices between design options. 12 Dec 2000Scrutiny Panel Presentation19

12 Dec 2000Scrutiny Panel Presentation20

The ESO involvement Who’s the Customer? Vista Consortium? ESO? Pros and Cons –Site –Standards Requirements SOWs Software definition Hardware definition –3x3 to 4x4 NIR focal plane 12 Dec 2000Scrutiny Panel Presentation21 Consortium ESO

Spec creep? 12 Dec 2000Scrutiny Panel Presentation22

Spec creep? 12 Dec 2000Scrutiny Panel Presentation23 It was not the size of the focal plane but the cold stop re-imaging requirement that made this a technical issue. ( not to mention cost of detectors and controllers)

12 Dec 2000Scrutiny Panel Presentation 24 VISTA Designs f/2.5 “ JIF design ” f/1 with both instruments mounted at cassegrain focus f/1 was clearly more cost effective –f/1 has tolerance issues on M2 Design still based on 3x3 array

12 Dec 2000Scrutiny Panel Presentation 25 VISTA Designs “The purpose of VISTA is to conduct large-scale semi-automated surveys of the sky at IR and visible wavelengths. Our concept of VISTA is not a conventional 4m telescope with instruments. We regard VISTA as a single integrated camera with an IR and a Visible channel, in which the "telescope" is really the fore-optics.”

12 Dec 2000Scrutiny Panel Presentation 26 VISTA Designs “The purpose of VISTA is to conduct large-scale semi-automated surveys of the sky at IR and visible wavelengths. Our concept of VISTA is not a conventional 4m telescope with instruments. We regard VISTA as a single integrated camera with an IR and a Visible channel, in which the "telescope" is really the fore-optics.” End Phase A

12 Dec 2000Scrutiny Panel Presentation 27 On Axis IR camera - cold baffles

12 Dec 2000Scrutiny Panel Presentation28

12 Dec 2000Scrutiny Panel Presentation 29 Encircled Energy at Ks

VISTA Field of View

12 Dec 2000Scrutiny Panel Presentation31

12 Dec 2000Scrutiny Panel Presentation32 End Phase A By the end of Phase A the design was essentially locked in

12 Dec 2000Scrutiny Panel Presentation33

12 Dec 2000Scrutiny Panel Presentation34

12 Dec 2000Scrutiny Panel Presentation35

12 Dec 2000Scrutiny Panel Presentation36

12 Dec 2000Scrutiny Panel Presentation37

12 Dec 2000Scrutiny Panel Presentation38

Acknowledgements 12 Dec 2000Scrutiny Panel Presentation40 Key players –Adrian Russell –Jim Emerson –Will Sutherland VISTA f/1 guilty party –Mark Casalli –Eli Atad –Martin Fisher –Stefano Stangellini Presentation –Andy Born