NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Monthly Progress Report on NTDCL Development Projects for September, 2013.

Slides:



Advertisements
Similar presentations
ABA CLEAN ENERGY CARBON PROJECT Bruce Johnston
Advertisements

POWERLINKS TRANSMISSION LIMITED a joint venture of TATA POWER &POWERGRID.
East West Interconnector Background Security Of Supply Promote Competition in The Electricity Sector Accommodate Growth Of Renewable Energy Reduce Dependence.
FUTURE NTDC PROJECTS UPTO
Monthly Progress Report on NTDC Development Projects for May, 2013
NTDC Projects for which Financing is Required
Development of Ventspils District Heating System in Latvia 2005/LV/16/C/PE/001.
SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSION LINES ESTIMATED COST (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO-
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER MONTHLY PROGRESS REPORT on NTDC DEVELOPMENT PROJECTS for January, 2013.
1 Presentation on Indian Power Sector : Key Issues By R.V. SHAHI Secretary (Power), Government of India November 16, 2006 Power Ministers’ Conference on.
Bangladesh-India Friendship Power Company (Pvt.) Limited (A Joint Venture of NTPC Ltd and BPDB) Registered Office : Bidyut Bhaban (14th Floor), 1 Abdul.
PAKISTAN POWER SECTOR BACK-GROUND, PRESENT SITUATION & FUTURE PLANS.
Brief on HVDC 2015 Brief on HVDC 2015
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
SR #. NAME OF NEW SUBSTATIONS T/F CAP. (MVA) ASSOCIATED TRANSMISSION LINES ESTIMATE D COST* (Rs.in Million) Eqt. US$ in Million REQUIRED YEAR OF COMMISSIO-
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
Interconnection of Distributed Generation
FUTURE NTDC PROJECTS UPTO
Module 6/7: DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED QUARTERLY REPORT ON FUTURE NTDC PROJECTS UPTO For The Quarter Ending Dec.2012 PLANNING POWER.
Quarterly Report on NTDC Development Projects
DEVELOPMENT OF A REGIONAL ENERGY MARKET IN THE MEKONG AREA by Piyasvasti Amranand National Energy Policy Office, Thailand ENERGY WEEK April 1999,
TRANSMISSION SYSTEM KERALA K ASOKAN DIRECTOR INSTITUTE FOR SUSTAINABLE DEVELOPMENT AND ENERGY STUDIES (InSDES)
111 TAG Meeting June 8, 2015 Teleconference / Webinar FINAL.
Bangladesh-India Friendship Power Company (Pvt.) Limited (A Joint Venture of NTPC Ltd and BPDB) Registered Office : Bidyut Bhaban (14th Floor), 1 Abdul.
NATIONAL TRANSMISSION AND DESPATCH COMPANY (NTDC) NTDC DEVELOPMENT PROGRAM PLANNING POWER (NTDC) PEPCO January 2012.
Pallatana-Bongaigaon Transmission System. 2 Generation Project Summary  Pallatana (726.6 MW): being implemented by OTPC –Unit - 1 : Dec-2011 –Unit -
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Lithuanian interconnection projects Donatas Matelionis LITGRID AB
Arizona ACC Biennial Transmission Assessment Navajo Transmission Project Update May 22, 2008 Presentation by Ben Hoisington Project Administrator, DPA.
Development and Construction of On- Shore Windfarms Andrew Aveyard Green Cat Renewables Jim Wilkinson CA Blackwells.
Paint Your Districts Prepared by: Information Management Unit FAO, Pakistan Contact for more information: 1.To edit the districts with.
SOLAR PARK – ROMANIA Photovoltaic Project Stage : Ready to Build 6,174 MWp November 2013 EXPERT GROUP CONSULTING.
N.A. ZUBERI MANAGING DIRECTOR PRIVATE POWER & INFRASTRUCTURE BOARD October 22, 2011 “CONVERSION OF EXISTING THERMAL POWER PLANTS TO COAL” INTERNATIONAL.
Lahore Waste Management Company City District Government Lahore Progress for Outsourcing of Solid Waste Management Functions in Six Cities of Punjab.
Liberalization of Electricity Market in Taiwan Su, Jin-sheng Energy Commission Ministry of Economic Affairs August 8, 2001.
Should Pakistan leapfrog the developed world in broadband? Rizwan Tiwana Chief Technical Officer Wateen Telecom International Networking and Communications.
September Elements of success behind CASA-1000.
Privatization and Liberalization of the Electric Power Industry in Taiwan Energy Commission Ministry of Economic Affairs October 5, 2001.
Energy for the Future Belene Nuclear Power Plant Project Status.
1 Presentation on Kaladan Multimodal Transit Transport Project (Port & IWT component) 23 rd February 2011.
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED QUARTERLY REPORT ON FUTURE NTDC PROJECTS UPTO For The Quarter Ending March, 2013 PLANNING POWER.
March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers.
MINING AND INFRASTRUCTURE INDABA 2015 ZPC PRESENTATION Presented by: N.F. Gwariro (MD)
VOWTAP Progress Report VOWDA December 2, DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Public Tender for Comprehensive Project to award GTS Project in concession “AGUAYTÍA – PUCALLPA 138 kV ELECTRIC TRANSMISSION LINE (circuit two)” GTS: Guaranteed.
Power Transmission Rehabilitation Project TERMS AND CONDITIONS OF INVESTMENT FUNDS “High Voltage Electric Networks” CJSC (HVEN CJSC) is implementing.
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER DEPARTMENT MONTHLY REPORT ON NTDC DEVELOPMENT PROJECTS PLANNING POWER May, 2012.
NTDC ONGOING DEVELOPMENT PROJECT SR. NO. NAME OF SUBSTATIONS TRANSFORMER CAPACITY (MVA) ASSOCIATED TRANSMISSION LINES EXPECTED COMMISSIONING 1 Ext. at.
Dr. Nyamajeje C. Weggoro Director, Productive and Social Sectors EAC Secretariat THE DAR ES SALAAM-TANGA- MOMBASA NATURAL GAS PIPELINE AND EAST AFRICAN.
PRESENTED BY HENRY RUHNKE WALD, RUHNKE & DOST ARCHITECTS, LLP SIERRA HOUSE & DROP-IN CENTER.
USAID Afghanistan Engineering Support Program (ESP) Pre-Bid Meeting July 14, 2015.
Meeting Nantucket’s demand for electricity, today and tomorrow. Upgrading Nantucket’s Electric Grid.
“AGUAYTÍA – PUCALLPA 138 kV ELECTRIC TRANSMISSION LINE
Planning and Realisation of Wind Farms
YEL WIND POWER PROJECT. YEL WIND POWER PROJECT.
Progress Briefing - Energy Initiative
“Caucasus Power Transmission Network’’ (Armenia-Georgia overhead transmission line/substations) Loan Project.
Energy Sector Pakistan
Loan Project of Construction of Iran-Armenia 400kV third power transmission line (“ Noravan’’ 400/220/20 kV) and related substation.
Memorandum of Understanding with GE Osmonics, Inc
Procurement & Strategic Sourcing (Law School Media Wall)
CASA-1000 TAP Afghanistan’s Energy Connectivity ,Central to South Asia
Power Generation Sector OF Pakistan
BRIEFING ON THE INTERCONNECTION LINES OF THE
Progress on the Renewable Energy IPP Procurement Programme
MULTISPORTS CENTRE PRESENTATION
PORTFOLIO COMMITTEE ON SOCIAL DEVELOPMENT 13 MARCH 2019
HOME AFFAIRS IDENTIFICATION SYSTEM (hanis)
Presentation transcript:

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Monthly Progress Report on NTDCL Development Projects for September, 2013

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER  Ongoing Development Projects  Projects Ready for Implementation  Cross Border Interconnection Projects 1 ACTIVITIES

Ongoing Projects of NTDC

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Overall Progress Expected Commissioning kV GIS Bandala 220 kV substation with two 220/132 kV 160 MVA T/Fs along with allied equipment. 1, ADB Tranche-I Civil & electrical works in progress. 90 %October, 2013 In/Out of 220 kV Gatti- KSK Transmission Line at Bandala (5+5 km) T/L Completed. 100 % Commissioned on kV Rohri 220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment 4, ADB Tranche-II Civil and electrical works in progress. 86 %October, kV Dharki-Rohri New D/C T/L (115 km) T/Ls Completed. 100 % Commissioned in June, kV D/C Rohri New- Shikarpur T/L (50km) 220kV D/C T/L for In/Out of Fauji Mari-Rohri New at Engro Chemical CCPP (5+5km) 3

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Overall Progress Expected Commissioning kV Khuzdar & 220kV Dadu- Khuzdar D/C T/L 220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment 2, JICA Civil and electrical works in progress. 82 %December, kV Dadu-Khuzdar D/C T/L (274 km) Lot-I= 135 KM Lot-II=139 KM Erection and stringing work in progress. Lot-I=97% Lot-II=79% December, kV Kassowal 220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment 2, World Bank Civil and electrical works in progress. 67 %March, 2014 Two 220 kV D/C T/L for In/out of 220 kV Vehari- Yousafwala D/C T/L at Kassowal (45+45km) T/L Completed. 100 % T/L commissioned on kV GIS Shalamar 220 kV gas insulated substation with three 220/132 kV 160 MVA T/Fs and allied equipment 3, JICA Civil and electrical works in progress. 80 %October, 2013 T/L Completed. 100 % T/L commissioned on kV D/C T/L for In/Out of one circuit of 220 kV Ravi-KSK T/L at Shalamar (9 km) and under ground cable (3+3 km) 4

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Overall Progress Expected Commissioning kV Okara 220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment 1, ADB Tranche-II Civil and electrical works in progress. 90 %October, 2013 In/out of 220 kV Yousaf Wala-Sarfraz Nagar D/C T/L at Okara (5+5 km) T/L Completed. 100 % T/L Commissioned on kV T.T. Singh 220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment 1, ADB Tranche-II Installation in progress. 92 % October, 2013 In/Out of 220 kV Faisalabad-Multan D/C T/L at T.T Singh (1+1 km) NTDC own resources Civil works completed. Erection and Stringing in progress 92 % 5

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Overall Progress Expected Commissioning kV Loralai 220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment 5, ADB Tranche-II Civil and electrical works in progress. 84 % December, kV D.G Khan-Loralai D/C T/L (200 km) ADB Tranche-I Erection and stringing in progress. 94 % kV Rahim Yar Khan 500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment 4, JICA Civil and electrical works in progress. 65 % December, kV S/C T/L for In/Out of 500 kV Guddu-Multan 3 rd Circuit at R.Y Khan (30+30 km) Civil and Electrical works in progress % 6

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC FinancingProject Status Overall Progress Expected Commissioning 10- Ext. at 500 kV Ghazi Barotha Addition of one 500/220 kV 600MVA T/F with allied equipment. 1, ADB Tranche-II Civil works in progress. 65 %December, kV Gujrat 220 kV substation with three 220/132 kV 250 MVA T/Fs with allied equipment. 1, JICA Construction of boundary wall is in progress and contractor is preparing design submittals for approval. 5 % July, kV D/C T/L for In/Out of 220kV Mangla-Ghakkar D/C T/L at Gujrat (2+2 km) kV Ghazi Road, Lahore 220 kV substation with three 220/132 kV 160 MVA T/Fs and allied equipment. 2, KfW Bidding documents vetted by M/S Lahmayer and sent to KfW for concurrence. Land acquired. 5 %December, kV D/C T/L for In/Out of 220 kV NKLP-S/Nagar S/C at Ghazi Road (30 km) Korean Exim Bank T/Ls ready for commissioning 100 % Work completed and ready for commissioning 220 kV D/C T/L for In/Out of 220 kV Ravi-KSK S/C at Ghazi Road (50 km) 7

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC FinancingProject Status Overall Progress Expected Commissioning kV Chishtian 220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment 2, JICA Civil work in progress. 49% December, kV Chishtian-Vehari D/C T/L (65 km) Civil and Erection work in progress. 51% 49% Extension at 220 kV Vehari Grid Station kV D.G Khan 500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment 4, ADB Tranche-II Civil and erection works in progress % December, 2013 Erection and stringing in progress % In/Out of 500 kV Guddu- Multan 2 nd Circuit at D.G Khan (20+20 km) 8

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Expected Commissioning 15- Augmentation of existing Grid Stations Name of Grid Stations No. of T/Fs Voltage (kV) Capacity (MVA) 3, ADB Tranche-II i) Contract agreement for 13 T/Fs has been signed with M/S SUNIR and are expected to be delivered in December ii)Bidding document for 5 T/Fs has been sent to ADB for concurrence. December, kV Rewat 1500/ kV Sheikh Muhammadi 4220/ kV Mardan 2220/ kV Burhan 4220/ kV Bund Road 4220/ kV Bahawalpur 2220/ kV Quetta Industrial 2220/

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Overall Progress Expected Commissioning 16-SVC at NKLP Static Var Compensators with T/F of 450 MVA Capacity 2, ADB Tranche-I Basic design has been agreed upon and project will be completed on schedule. 26 %May, kV Dera Murad Jamali 220 kV substation with 220/132 kV 1x160 MVA & 1x100 MVA T/Fs and allied equipment PC-I approved by CDWP on NTDC own resources Contractor mobilized and civil works in progress. 10 % December, kV D/C single conductor T/L for In/Out of 220 kV Uch-Guddu S/C at Dera Murad Jamali (5 km) Re-survey work in progress. 5 % 10

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Overall Progress Expected Commissioning kV Lahore New 500 kV substation with two 500/220 kV 750 MVA T/Fs and allied equipment 12, JICA Work is delayed due to non availability of land. 5 % Two 500 kV S/C T/Ls for In/Out of 500 kV Sahiwal-Lahore S/C at Lahore New (15+15km) T/L route survey is in progress. Two 500 kV S/C T/Ls for In/Out of 500 kV Lahore – Gujranwala S/C at Lahore New (50+50 km) 220 kV D/C T/L for In/Out of 220 kV NKLP- Ghazi Road S/C at Lahore New (50km) 220kV D/C T/L for In/Out of 220 kV NKLP- Wapda Town S/C at Lahore New (45 km) 11

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Overall Progress Expected Commissioning 19- Installation of SVS at 220/132 kV Quetta Industrial SVS (SVC of -50/+300 MVAR & MSC of 300 MVAR) 2, ADB Tranche-II Not yet started. NILDecember, kV Shikarpur 500 kV substation with two 500/220 kV 600 MVA T/Fs and allied equipment 8, JICA Contract agreement signed, L/C opened and contractor mobilized. Land acquired % August, 2014 Two 500 kV S/C T/Ls for In/out of 500 kV Dadu - Guddu Cct # 1 (20+20 km) 1.25%June, 2015 Two 500 kV S/C T/Ls for In/out of 500 kV Dadu – Guddu Cct # 2 (22+22 km) 220 kV D/C T/L for In/out of 220 kV Guddu – Sibbi S/C at Shikarpur (50 km) 12

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC FinancingProject Status Overall Progress Expected Completion 21- Power Dispersal from 747 MW CCPP Guddu 500kV Guddu-Muzaffargarh S/C T/L (256 km) 7, Buyer’s Credit Basis Tender opened on evaluated and sent to BOD for approval. NIL kV T/L for In/Out of 500 kV D.G Khan-Multan S/C T/L at 500 kV Muzaffargarh ( km) Three 500 kV line bays at Muzaffargarh substation 500 kV T/L for In/Out of existing Guddu- Multan (R.Y.Khan) T/L at 500 kV Guddu New substation (2+2 km) Deposit work of GENCO-II Civil works in progress.Dec Power Dispersal from Uch-II 220 kV Uch-II – Sibbi D/C T/L (125km) 2, ADB Tranche-III Bid evaluation report finalized. ADB has been requested for allowing price negotiation with single bidder. Response from ADB is awaited. 5 %Dec Extension at 220kV Sibbi substation Work in progress from NTDC own resources. 50%April, kV D/C T/L for In/Out of 220kV existing Uch-I to Shikarpur New S/C T/L at Uch-II (0.5 km) Reconductoring of 1km T/L and In/Out of 0.5km completed. 100 % Commissioned on Reconductoring of 220kV T/L Uch-I to Uch-II (1 km) 13

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Sr. No. Name of the Projects Scope of work Approved Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Overall Progress Expected Completion 23- Power Dispersal from Neelum Jhelum HPP Package-I 500 kV D/C T/L from Neelum Jhelum to Gujranwala (270km) 22, Approved by ECNEC on Buyer’s Credit Basis LOA issued on NIL kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Azad Pattan (5km) 500 kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Karot (5 km) Package- II Extension at 500 kV Gujranwala Bidding not yet initiated 24- Power Dispersal Arrangements from Duber Khwar Power House 220 kV D/C T/Line from Duber Khwar to Khan Khwar Power House (33km) (For Lot-I & II) Approved under PC-I of Hydel Power Project Deposit work of G.M (Hydel) Erection and stringing work in progress. 90 % Oct (Subject to clearance of ROW problems from Tower No. 2 to 10 during Jirga Meeting on ) 14

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER 15 Sr. No. Name of the Projects Scope of work Approved Cost (MRS/MUS$) Date of Approval by ECNEC Financing Project Status Overall Progress Expected Completion 25- Dispersal of power from 2x50MW Wind Power Plants at Mirpur Sakro 132kV D/C T/L on Greeley conductor from WPP#1 to 132kV Thatta G/S (64km) NTDC own resources Tender opened, evaluated and case is being prepared for getting approval of competent authority for award of work NILJune 2014 Construction of two 132kV line bays each at Thatta G/S 26- Interconnection arrangement for dispersal of power from TGF & WPP#4 at Jhimpir 132kV D/C T/L for looping I/O of Jhimpir-Nooriabad 2 nd 132kV at TGF & WPP#4 at Jhimpir (7 km) 207 2_ NTDC own resources Procurement of material initiated. NIL Conversion of 2 Nos. 132kV iso bays to line bays at Nooriabad substation for Kalu Kahar and Jamshoro old S/C T/Ls. 132kV T/L approx 4km from Nooriabad to the nearby Jamshoro- KDA T/L Total 108,526 1,479

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Summary of Ongoing 500kV Projects Sr. No. DescriptionAddition in T/L & T/F Capacity kV S/C Transmission Lines Length1150 km /220 kV Transformation Capacity (New Projects) 5100 MVA /220 kV Transformation Capacity (Extension) 600 MVA /220 kV Transformation Capacity (Augmentation) 300 MVA 500/220 kV Transformation Capacity (Grand Total) 6000 MVA 16

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Summary of Ongoing 220kV Projects Sr. No. DescriptionAddition in T/L & T/F Capacity kV D/C Transmission Line km /132 kV Transformation Capacity (New Projects) 6930 MVA /132 kV Transformation Capacity (Extension) /132 kV Transformation Capacity (Augmentation) 1620 MVA 220/132 kV Transformation Capacity (Grand Total) 8550 MVA 18

Projects Ready for Implementation

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER NTDC Development Projects Ready for Implementation Sr. No. Name of the Projects Scope of work Est. Cost (MRs/ MUS$) Date of Approval by ECNEC FinancingProject Status Expected Completion 1- 3 rd Circuit from Jamshoro to Rahim Yar Khan (For power evacuation from 2x660 MW Coal Power Plant at Jamshoro & WPPs) 500 kV Jamshoro-Moro-R.Y.K S/C T/L (535 km) 24, Approved by ECNEC on ADB Tranche-III Rebidding in process kV Moro-Dadu S/C T/L (55 km) 500 kV Switching Station at Moro Extension at 500 kV Jamshoro, Dadu & R.Y.K Grid Stations. 2- Power Dispersal from Chashma Nuclear (C3 & C4) 220 kV Chashma Nuclear – Bannu D/C T/L (125 km) 3, Approved by ECNEC on Proposed under ADB Tranche-IV Route under checking kV D/C T/L for In/Out of existing C1 &C2 at C3 & C4 (2 km) Extension at 220kV Bannu 20

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER NTDC Development Projects Ready for Implementation Sr. No. Name of the Projects Scope of work Est. Cost (MRs/ MUS$) Date of Approval by ECNEC Financing Project Status Expected Completion 3- Power Dispersal from 1200 MW Thar Coal Based Power Plant 500 kV Thar – Matiari D/C T/L (250 km) 22, JICA has shown interest to fund the project. T/L Plan and Profile Drawings completed. Execution is linked with installation of Coal Fired Power Plants at Thar kV Switching Station at Matiari kV Nowshera 220kV sub station with 220/132kV 3x250 MVA T/Fs along with allied equipment 1, Proposed in ADB Tranche-IV Site for Grid Station selected. Acquisition of land in progress In/Out of 220 kV Ghazi Barotha – Shahi Bagh D/C T/L at Nowshera (5+5 km) 21

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER NTDC Development Projects Ready for Implementation Sr. No. Name of the Projects Scope of work Est. Cost (MRs/ MUS$) Date of Approval by ECNEC FinancingProject Status Expected Completion kV Lalian New 220kV sub station with 220/132kV 3x250 MVA T/Fs along with allied equipment 1, Proposed in ADB Tranche-IV Hiring of project preparatory consultants in process. Land not yet acquired In/Out of 220 kV Gatti – Ludewala D/C T/L at Lalian New (4+4 km) kV Mansehra 220kV sub station with 220/132kV 2x250 MVA T/Fs along with allied equipment ADB Tranche-III Bids opened on evaluated & sent to competent authority for approval. Land acquired Two 220 kV D/C T/L for In/Out of 220 kV Alai Khawar – Islamabad Peshawar Road D/C at Mansehra ( km) 22

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER NTDC Development Projects Ready for Implementation Sr. No. Name of the Projects Scope of work Est. Cost (MRs/ MUS$) Date of approval by ECNEC FinancingProject Status Expected Completion /132 kV D.I.Khan 220kV sub station with 220/132kV 2x250 MVA T/Fs along with allied equipment 3, Proposed in ADB Tranche-IV Land for G/S acquired. Boundary wall completed kV D/C T/L for In/Out of 220 kV Chashma Nuclear- Ludewala S/C T/L at D.I Khan (100km) Total 57,

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Summary of Projects Ready for Implementation Sr. No.DescriptionAddition in T/L & T/F Capacity 1-500kV S/C Transmission Lines Length1090 km 2-220kV Transmission Line246 km 3-220/132 kV Transformation Capacity2500 MVA 24

Cross Border Interconnection Projects

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED Cross Border Interconnection Projects Sr. No. Name of the Projects Scope of work Est. Cost (MUS$) Project StatusFinancing Expected Completion 1- Import of 100MW Power from Iran. 220 kV Pak Iran Border-Gwadar D/C T/L (100km) 44 Work of profile & plan tabling is in progress. 70% by Export Development Bank of Iran and 30% by NTDC. August, 2014 Work awarded to contractor and contractor mobilized. 220 kV GIS at Gwadar with 2x160MVA T/Fs 2- Import of 1000MW Power from Iran. 500 kV HVDC Bipolar Transmission Line from Pak - Iran Border to Quetta (585km). 508 MoU signed between Pakistan & Iran on to implement the project. Not yet committed kV Convertor Station at Quetta. 220 kV Quetta-Quetta Ind.D/C T/L (5 km) 220 kV Quetta-Loralai D/C T/L (170km) 220 kV Quetta-Mastung D/C T/L (50km) 26

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED Cross Border Interconnection Projects Sr. No. Name of the Projects Scope of work Est. Cost (MUS$) Project StatusFinancing Expected Completion 3- Import of 1000MW Power from Tajikistan (CASA-1000) 500 kV HVDC Bipolar Transmission line from Pak-Afghan Border to Peshawar (71km). 200 Feasibility Study completed. Positive response from World Bank and IDB kV Converter Station at Peshawar 220 kV D/C T/L for interconnection of 220 kV Peshawar- ShahiBagh (10 km) 500 kV D/C T/L for interconnection of 500 kV Peshawar- Tarbela (5 km) 4- Import of MW Power from India. Different options for Interconnection are under study. - World Bank has offered to sponsor pre-feasibility study for the project Positive response from World Bank - Total752 27

NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED PLANNING POWER Report Prepared by:DesignationContact No. Maqsood Ahmad Qureshi Manager Projects Planning Fahmeeda Shafi Dy. Manager Projects Planning