MD707 Operations Management Professor Joy Field

Slides:



Advertisements
Similar presentations
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Process.
Advertisements

Capacity After deciding what products/services should be offered and how they should be made, management must plan the capacity of its processes. Capacity.
Capacity Planning.
Capacity Planning. How much long-range capacity is needed When more capacity is needed Where facilities should be located (location) How facilities should.
Constraint Management
6 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Capacity Planning (Long-Term Capacity Planning) 6.
PRODUCTION AND OPERATIONS MANAGEMENT
Capacity Planning For Products and Services
Capacity Planning For Products and Services
Unit 2 Manufacturing Operations Sections: 1.Manufacturing Industries and Products 2.Manufacturing Operations 3.Production Facilities 4.Product/Production.
6 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Capacity Planning 6 For Operations Management, 9e by Krajewski/Ritzman/Malhotra.
6 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Capacity Planning Chapter 6.
© 2007 Pearson Education Constraint Management Chapter 7.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 5 Capacity Planning For Products and Services.
Capacity planning.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Chapter 8.
Facilities and Aggregate Planning. A digression I am not an advocate of gambling, but use an example here that you might draw on later. Say I have a coin.
Strategic Capacity Planning for Products and Services McGraw-Hill/Irwin Copyright © 2012 by The McGraw-Hill Companies, Inc. All rights reserved.
CAPACITY LOAD OUTPUT.
Operations Management Capacity Planning Supplement 7
For Products and Services
PRODUCTION PLANNING ELİF ERSOY Production Planning2 WHAT IS PRODUCTION PLANNING?  Production planning is a process used by manufacturing.
Facilities and Aggregate Planning. Overview As you know there are 24 hours a day, 7 days a week. What can you get done in a week period? Firms need to.
Operations Management
IE 3265 Production & Operations Management Slide Series 2.
Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Chapter 4 How Businesses Work.
Operations Planning Horizons
Long-Range Capacity Planning
Topic on Production and Cost Functions and Their Estimation.
Chapter 4 How Businesses Work McGraw-Hill/Irwin Copyright © 2012 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Selection and Capacity Planning
To Accompany Ritzman & Krajewski, Foundations of Operations Management © 2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Capacity.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Process.
OPERATIONS MANAGEMENT for MBAs Fourth Edition
Aggregate Planning and Resource Planning Chapters 13 and 14.
©2006 Pearson Prentice Hall — Introduction to Operations and Supply Chain Management — Bozarth & Handfield Chapter 8, Slide 1 Capacity Decisions Defining.
PowerPoint presentation to accompany Heizer/Render - Principles of Operations Management, 5e, and Operations Management, 7e © 2004 by Prentice Hall, Inc.,
The Economics of Production Make or Buy Decisions Capacity Expansion Learning-Curves Break-even Analysis Production Functions.
C A P A C I T Y Dr. Dewi Nusraningrum, M.Si. CAPACITY PLANNING - Capacity is the maximum rate of output for a facility. - Capacity planning is central.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 5 Capacity Planning For Products and Services.
Module 4: Capacity Capacity
Capacity Planning. Capacity Capacity (I): is the upper limit on the load that an operating unit can handle. Capacity (I): is the upper limit on the load.
© 2007 Pearson Education Constraint Management Chapter 7.
CHAPTER 8 CAPACITY. THE CONCEPT Maximum rate of output for a process Inadequate capacity can lose customers and limit growth while excess capacity can.
Aggregate Planning and Resource Planning Chapters 13 and 14.
© 2006 Prentice Hall, Inc.S7 – 1 Capacity Planning © 2006 Prentice Hall, Inc.
Lecture 11 Capacity Management and Planning Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming College,
Constraint Management
Capacity Planning Pertemuan 04
1 Chapter 16 Relevant Costs and Benefits for Decision Making.
S7 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry.
 Capacity is the ability of a process or system to hold, receive, store or accommodate.  In business terms, it is the amount of output that a system.
Chapter 5 Lecture 8 Capacity Planning FOR Products and Services.
© 2006 Prentice Hall, Inc.S7 – 1 Operations Management Supplement 7 – Capacity Planning © 2006 Prentice Hall, Inc. PowerPoint presentation to accompany.
5-1Capacity Planning William J. Stevenson Operations Management 8 th edition.
Capacity Planning.
Strategic Capacity Management
Operations Management
Constraint Management
What is Capacity? Design capacity Effective capacity Actual output.
Capacity Planning For Products and Services
Capacity Planning.
Capacity Planning For Products and Services
Operations Management Capacity Design
Stevenson 5 Capacity Planning.
Planning Capacity Chapter 4.
Capacity Planning For Products and Services
Production and Operations Management
Capacity Planning For Products and Services
Presentation transcript:

MD707 Operations Management Professor Joy Field Capacity Planning MD707 Operations Management Professor Joy Field

Capacity Planning Capacity is the maximum rate of output for a facility. Capacity planning considers questions such as: What should be the balance between long-term and short-term capacity? Should we expand capacity before the demand is there or wait until demand is more certain?  What facility size is optimal? Capacity decisions follow from a firm’s operations strategy and forecasted demand pattern.

Measuring Capacity Type Utilization Output measures Input measures Average output rate/maximum capacity Maximum capacity = effective or design capacity?

Capacity Bottlenecks and Flow Three-Stage Process 1 200/hr 2 50/hr 3 Inputs Outputs

Capacity Cushion Pressures for a large capacity cushion Uneven demand Uncertain demand Uncertain supply Changing product mix Capacity comes in large increments (economies of scale) Pressures for a small capacity cushion Capital costs

Links with Other Operational Characteristics and Priorities Operational Characteristic/Priority Capacity Cushion Faster delivery times Larger High quality levels Smaller Higher capital intensity Less worker flexibility More stable schedules

Timing of Capacity Increments Two Capacity Strategies Planned unused capacity Forecast of capacity required Planned use of short-term options

Optimal Operating Level

Steps in the Capacity Planning Process Estimate capacity requirements Identify gaps Develop alternatives Evaluate the alternatives  Select an alternative and implement

Make or Buy Decision Problem Hahn Manufacturing has been purchasing a key component of one of its products from a local supplier. The current purchase price is $1,500 per unit. Efforts to standardize parts have succeeded to the point that this same component can now be used in five different products. Annual component usage should increase from 150 to 750 units. Management wonders whether it is time to make the component in-house, rather than to continue buying it from the supplier. Fixed costs would increase by about $40,000 per year for the new equipment and tooling needed. The cost of raw materials and variable overhead would be about $1,100 per unit, and labor costs would go up by another $300 per unit produced. Should Hahn make rather than buy? What is the break-even quantity? What other considerations might be important?

Determining Resource Requirements The amount of resources (e.g., machines, people, service counters, etc.) needed at a bottleneck operation is based on the total processing and setup time required to meet demand. where M = number of bottleneck resources needed to meet production requirements D = yearly demand (in number of units/year) p = processing time per unit (in hours) Q = lot size s = setup time/lot (in hours) N = number of hours available/machine/year c = capacity cushion (in percentage)

Resource Capacity Problem You have been asked to put together a capacity plan for a critical bottleneck operation at the Surefoot Sandal Company. Your capacity measure is number of machines. Three products (men’s women’s, and kid’s sandals) are manufactured. The time standards (processing and setup), lot sizes, and demand forecasts are given in the following table. The firm operates two 8-hour shifts, 5 days per week, 50 weeks per year. Experience shows that a capacity cushion of 5 percent is sufficient. Assume a new setup for each lot produced. Product Processing (hr/pair) Setup (hr/lot) Size (pairs/lot) Demand Forecast (pairs/yr) Men’s sandals 0.05 0.5 240 80,000 Women’s sandals 0.10 2.2 180 60,000 Kid’s sandals 0.02 3.8 360 120,000 How many machines are needed at the bottleneck? If the operation currently has two machines, what is the capacity gap? If the operation can not buy any more machines, which products can be made? If the operation currently has five machines, what is the utilization?

Resource Capacity Problem Solutions Total time available per machine per year (2 shifts/day)(8 hours/shift)(5 days/week)(50 weeks/year) = 4000 hours/machine/year With a 5% capacity cushion, the hours/machine/year that are available = 4000(1-0.05) = 3800 hours/machine/year Total time to produce the yearly demand of each product (this is equal to the processing time plus the setup time) Men’s =(0.05)(80,000)+(80,000/240)(0.5)= 4167 hrs Women’s =(0.10)(60,000)+(60,000/180)(2.2)= 6733 hrs Kid’s =(0.02)(120,000)+(120,000/360)(3.8)= 3667 hrs Total time for all products =4167+6733+3667= 14567 hrs

Resource Capacity Problem Solutions (cont.) Machines needed = (14,567/3800) = 3.83 = 4 machines Capacity gap is 4 - 2 = 2 machines With two machines, we have (3800)(2) = 7600 hours of machine capacity. We can make all of the women’s sandals (6733 hours) and some of the men’s sandals, for example. With five machines, (5)(4000) = 20,000 machine-hours/year are available. The total number of machine-hours/year needed for production are 14,567. Utilization = (14,567/20,000)(100%) = 73%. Thus, the capacity cushion is (100% - 73%) = 27%.