Sistan & Balouchestan Electric Power Distribution Company

Slides:



Advertisements
Similar presentations
“Power Factor” In Transmission System
Advertisements

POWER FACTOR IN ELECTRICAL ENERGY MANAGEMENT
Demand Response: The Challenges of Integration in a Total Resource Plan Demand Response: The Challenges of Integration in a Total Resource Plan Howard.
DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Early Lessons Learned from DOE-EPRI Framework Experience Melissa Chan MA DPU.
Power Grid Reinforcement Fall Presentation Team 9b: – Jon Brown – Kyle Reininger – Alan Myers – Karl Homburg – Dan Sinnott.
NETWORK ANALYSIS IN GIS ENVIRONMENT Uday Deshmukh North Delhi Power Limited.
 UK Power Networks. All rights reserved Distribution Network Visibility Low Carbon Networks Fund Tier 1 project UK Power Networks & PPA Energy Omer.
Electrical Engineering Department, Amirkabir University of Technology, Tehran, Iran M. Poursistani N. Hajilu G. B. Gharehpetian M. Shafiei CHP Systems.
Distribution System Analysis for Smart Grid Roger C. Dugan Sr. Technical Executive, EPRI Webcast Feb 8, 2011.
1 Pacific Gas & Electric Company MTS: Evolution of the Electric Distribution System Manho Yeung, Senior Director, System Planning and Reliability PG&E.
Presented by: Hao Liang
EStorage First Annual Workshop Arnhem, NL 30, Oct Olivier Teller.
RiversidePublicUtilities.com Arts & Innovation RiversidePublicUtilities.com Challenges and Solutions for Large-Scale PV Integration on RPU’s Distribution.
Power Engineering Society Chicago Chapter Reactive Power: Sources and Solutions 12 February 2003 David E. Mertz, PE Burns & McDonnell Engineers, Inc.
Bryan Underwood Advisor: Prof. Gutschlag Alternating Current Power Factor Monitoring and Correction.
1 Training Session on Energy Equipment Electricity Presentation from the “Energy Efficiency Guide for Industry in Asia” ©
Plant Utility System (TKK-2210)
Technical Presentation on the new Power Saving Unit (PSU) Introduced By View Power.
F. Ferrandis_SP_ALPHA 2_BLOCK 2_Paper 35_Presentation Barcelona May POWER FACTOR CORRECTION WITHIN INDUSTRIAL SITES EXPERIENCES REGARDING.
SUSTAINABLE ENERGY REGULATION AND POLICY-MAKING FOR AFRICA Module 13 Energy Efficiency Module 13: SUPPLY-SIDE MANAGEMENT.
POWER FACTOR CORRECTION
Group Meeting – Pepco Holdings, Inc. July 17, 2014.
1 SIMPLIFIED VOLTAGE OPTIMIZATION M&V PROTOCOLS Regional Technical Forum August 4, 2009.
Tubas ELECTRICAL NETWORK STUDY Prepared by : Omar Abu-Omar Ahmad Nerat Sameed banifadel PRESENTATION TO: Dr.MAHER KHAMASH.
1.6 Real Single-Phase Transformer.
AFREPREN/FWD Cogen Centre Training Workshop on Cogeneration in Africa
Chapter 7 AC Power Analysis
Power and Power Measurement ENGR 10 – Intro to Engineering College of Engineering San Jose State University (Ping Hsu and Ken Youssefi) 1 Introduction.
Frankfurt (Germany), 6-9 June 2011  Authors: Reinhard BREHMERWIEN ENERGIE Stromnetz GmbH - Austria Thomas SCHUSTERWIEN ENERGIE Stromnetz GmbH – Austria.
1 Presentation to: SWEDE Conference Austin, TX May 2, 2013 Tom Weaver, PE Historical Voltage Range VVO Range “A” Service “A”
1 Distribution Efficiency Conservation Voltage Regulation (CVR) Jillianne Welker 4/21/2009.
Management and Organisation of Electricity Use Electrical System Optimisation Belgrade November 2003.
Brussels Workshop Use case 3 11/09/2015 Mario Sisinni.
Northwest Power and Conservation Council 1 Distribution System Efficiency Potential & Conservation Voltage Reduction Power Committee April 2009.
Distribution Efficiency Initiative: Calculator Review April 29, 2008 Regional Technical Forum.
EECE 887 Distribution System Engineering CHAPTER 1 Power Delivery Systems.
Optimal Power Flow- Basic Requirements For Real Life.
Discussion and Preliminary Findings Concerning Voltage Reduction (VR) for Peak Shaving Mark Carpenter Sr. VP T&D Operations December 6, 2012 Presentation.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Distribution Systems-General
REACTIVE POWER COMPENSATION
A Training Presentation On 132 KV GSS JAIPUR Submitted in partial fulfillment For the award of the degree of BACHELOR OF TECHNOLOGY Submitted To:- Submitted.
1 1 DISTRIBUTION EFFICIENCY INITIATIVE (DEI) Benefits on Both Sides of the Meter RTF MEETING February 5, 2008.
Dated: 17 February 2016 Instructor :Kashif Mehmood.
Lecture 09Electro Mechanical System1 Chapter 11 Special Transformers.
DISTRIBUTED GENERATION ISSUES Technical Issues Non-Technical Issues.
Voltage Reduction Task Force Update September 25, 2014 Presentation to ERCOT TAC.
TRMAC Meeting April 14, 2015 TRM EUI Measure Development Project.
TECHNICAL PAPER ON SIMULTANEOUS AC-DC POWER TRANSMISSION
GRID INTEGRATION COST OF PHOTOVOLTAIC POWER GENERATION G. Strbac, D. Pudjianto, P. Djapic, J. Dragovic Energy Futures Lab.
POWER FACTOR CORRECTION
Power Factor Correction The Definitive power solution
Distribution System Analysis for Smart Grid
Ch 4: Transmission Line Calculations
Introduction to Electric Power System and A. C. Supply
Power Factor Correction The Definitive power solution
“Caucasus Power Transmission Network’’ (Armenia-Georgia overhead transmission line/substations) Loan Project.
Management Of Tulkarm Electrical Network
D. Menniti, N. Sorrentino, A. Pinnarelli, M. Motta, A. Burgio and P
Economic Operation of Power Systems
EE6501 POWER SYSTEM ANALYSIS
Distribution Feeder Voltage Regulation and Control
Introduction To Reactive Power
POWER SYSTEM ANALYSIS INTRODUCTION.
Design of Electric Power Systems and Utilities
Irvine Smart Grid Demonstration Distribution Volt / Var Control
Why does power factor matter Make-up of distribution capacitor banks
ELL100: INTRODUCTION TO ELECTRICAL ENGG.
Jakov Chavez Vega Kalle Valtavirta
Chapter 33 Transformer: Three Phase. Chapter 33 Transformer: Three Phase.
Presentation transcript:

Sistan & Balouchestan Electric Power Distribution Company

شرکت توزیع نیروی برق سیستان و بلوچستان Sistan & Balouchestan Electric Power Distribution Company شرکت توزیع نیروی برق سیستان و بلوچستان

Sistan & Balouchestan Electric Power Distribution Company

Sistan & Balouchestan Electric Power Distribution Company

Sistan & Balouchestan Electric Power Distribution Company

Sistan & Balouchestan Electric Power Distribution Company Efficiency ranges 28-35 % with respect to size of thermal plant, age of plant and capacity utilization Step-up to 400 / 800 Kv to enable EHV transmission. Envisaged max. losses 0.5 % or efficiency of 99.5 % EHV transmission and substations at 400 kV / 800 kV. Envisaged maximum losses 1.0 % or efficiency of 99 % HV transmission & Substations for 220 / 400 kV. Envisaged maximum losses 2.5 % or efficiency of 97.5 % Sub-transmission at 66 / 132 kV Envisaged maximum losses 4 % or efficiency of 96 % Step-down to a level of 11 / 33 kV. Envisaged losses 0.5 % or efficiency of 99.5 % Distribution is final link to end user at 11 / 33 kV. Envisaged losses maximum 5 % of efficiency of 95 % Cascade efficiency from Generation to end user= n x n x n x n x n x n x n The cascade efficiency in the T&D system from output of the power plant to the end user is 87% (i.e. 0.995 x 0.99 x 0.975 x 0.96 x 0.995 x 0.95 = 87%) Sistan & Balouchestan Electric Power Distribution Company

Sistan & Balouchestan Electric Power Distribution Company Efficiency ranges 28-35 % with respect to size of thermal plant, age of plant and capacity utilization Step-up to 400 / 800 Kv to enable EHV transmission. Envisaged max. losses 0.5 % or efficiency of 99.5 % EHV transmission and substations at 400 kV / 800 kV. Envisaged maximum losses 1.0 % or efficiency of 99 % HV transmission & Substations for 220 / 400 kV. Envisaged maximum losses 13.043 % or efficiency of 86.96 % Sub-transmission at 66 / 132 kV Envisaged maximum losses 14.286 % or efficiency of 85.714 % Step-down to a level of 11 / 33 kV. Envisaged losses 0.5 % or efficiency of 99.5 % Distribution is final link to end user at 11 / 33 kV. Envisaged losses maximum 25 % of efficiency of 75 % Cascade efficiency from Generation to end user= n x n x n x n x n x n x n The cascade efficiency in the T&D system from output of the power plant to the end user is 87% (i.e. 0.995 x 0.99 x 0.8696 x 0.857 x 0.995 x 0.75 = 54.8%) Sistan & Balouchestan Electric Power Distribution Company

Sistan & Balouchestan Electric Power Distribution Company Efficiency ranges 28-35 % with respect to size of thermal plant, age of plant and capacity utilization Step-up to 400 / 800 Kv to enable EHV transmission. Envisaged max. losses 0.5 % or efficiency of 99.5 % EHV transmission and substations at 400 kV / 800 kV. Envisaged maximum losses 1.0 % or efficiency of 99 % HV transmission & Substations for 220 / 400 kV. Envisaged maximum losses 10 % or efficiency of 90 % Sub-transmission at 66 / 132 kV Envisaged maximum losses 7.94 % or efficiency of 92.06 % Step-down to a level of 11 / 33 kV. Envisaged losses 0.5 % or efficiency of 99.5 % Distribution is final link to end user at 11 / 33 kV. Envisaged losses maximum 15 % of efficiency of 85 % Cascade efficiency from Generation to end user= n x n x n x n x n x n x n The cascade efficiency in the T&D system from output of the power plant to the end user is 87% (i.e. 0.995 x 0.99 x 0.90 x 0.9206 x 0.995 x 0.85 = 69%) Sistan & Balouchestan Electric Power Distribution Company

Sistan & Balouchestan Electric Power Distribution Company Efficiency ranges 28-35 % with respect to size of thermal plant, age of plant and capacity utilization Step-up to 400 / 800 Kv to enable EHV transmission. Envisaged max. losses 0.5 % or efficiency of 99.5 % EHV transmission and substations at 400 kV / 800 kV. Envisaged maximum losses 1.0 % or efficiency of 99 % HV transmission & Substations for 220 / 400 kV. Envisaged maximum losses 10 % or efficiency of 90 % Sub-transmission at 66 / 132 kV Envisaged maximum losses 7.94 % or efficiency of 92.06 % Step-down to a level of 11 / 33 kV. Envisaged losses 0.5 % or efficiency of 99.5 % Distribution is final link to end user at 11 / 33 kV. Envisaged losses maximum 5 % of efficiency of 95 % Cascade efficiency from Generation to end user= n x n x n x n x n x n x n The cascade efficiency in the T&D system from output of the power plant to the end user is 87% (i.e. 0.995 x 0.99 x 0.90 x 0.9206 x 0.995 x 0.95 = 77.15%) Sistan & Balouchestan Electric Power Distribution Company

Leveling of distribution system loads by network re-configuration Sistan & Balouchestan Electric Power Distribution Company Leveling of distribution system loads by network re-configuration Voltage optimization Power factor correction Install new feeders/transformers/substations Increasing primary conductor size Adding a (parallel) feeder Upsizing conductors or reconfiguring secondary network Changing out a distribution transformer Using amorphous core transformers Voltage conversion Updating substation auxiliary equipment Adding substation transformers Upgrading metering technology updating street lighting technology

Some loads in the heavy loaded feeder shifted to Sistan & Balouchestan Electric Power Distribution Company Some loads in the heavy loaded feeder shifted to another lightly loaded feeder . First step for loss reduction with less investment

Voltage Optimization (VO) is the concept of tuning the circuit to Sistan & Balouchestan Electric Power Distribution Company Voltage Optimization (VO) is the concept of tuning the circuit to achieve a flattened voltage profile before implementing CVR in order to produce greater savings than CVR alone.

Loss Reduction Techniques Install new feeders Sistan & Balouchestan Electric Power Distribution Company Heavy loaded area to be supplied by new feeder so that existing feeder supplies less loads (for new feeder install , sometimes new HV/MV transformer needed) New substation to be built in the center of high load density area so that existing feeder supplies less loads Building new facilities ( feeders , transformers , substations ) requires a certain level of investment. Impact of loss reduction and investment must be carefully considered.

Sistan & Balouchestan Electric Power Distribution Company Certain customer inductive loads , distribution lines , and transformers require reactive power to be supplied by the electric grid. Addition of reactive power(VAR) increases the total line current, which contributes to additional losses in the system .

Sistan & Balouchestan Electric Power Distribution Company Improvement of power factor reduces power flow in a feeder . Thus, system loss reduction achieved Power factor improved by compensating the reactive power

Loss Reduction Techniques Load Balancing and Multi-Phasing Sistan & Balouchestan Electric Power Distribution Company Phase balancing is balancing phase currents along three- phase circuits. Balancing phase loads at the substation does not guarantee phase balance along the feeder path.

Sistan & Balouchestan Electric Power Distribution Company Doubling the voltage would reduce the current by half and reduce the line loss to 25% of original. Upgrading the primary voltage of the distribution feeder involves upgrading the distribution equipment, which can be cost intensive

Requires comprehensive cost/benefit studies Sistan & Balouchestan Electric Power Distribution Company Balances load between the transformers at existing substations or at a new substation location . Requires comprehensive cost/benefit studies

Increasing primary conductor size Adding a (parallel) feeder Sistan & Balouchestan Electric Power Distribution Company Increasing primary conductor size Adding a (parallel) feeder Upsizing conductors or reconfiguring secondary network Changing out a distribution transformer Using amorphous core transformers Upgrading metering technology Updating street lighting technology

Distributed Generation Sistan & Balouchestan Electric Power Distribution Company Advanced Metering Infrastructure (Data improves loss analysis and CVR effectiveness ) Volt/VAR Control via Distribution Management System (Optimizes set points for local Volt/VAR controllers (LTC, regulator, cap banks) ) Distribution Automation ( Provides monitoring and control to optimize system Configuration ) Distributed Generation Energy Storage Systems (Reduces peak load and energy and associated losses ) Demand Management

Evaluation of Loss Reduction Measures Sistan & Balouchestan Electric Power Distribution Company When “Cost of Loss Reduction” > “Economic Value of Reduced Energy Loss”, the loss is feasible Determine the most effective measures and their respective input

Best Practices in Technical Loss Reduction Sistan & Balouchestan Electric Power Distribution Company Network Re-Configuration Network Reconducturing Optimal Location of DTRs Integrated Optimal Strategy

Rule Based Optimal Integrated Strategy Sistan & Balouchestan Electric Power Distribution Company Rule1: Reconfigure the network for minimal losses Rule2: Determine the optimal number, location and capacity of the shunt capacitor banks to be placed on the network Rule3: If voltage drop violation is severe and losses are violated marginally, then install AVB on the feeders to improve voltage profile and maximise reduction of losses . If loss violation is severe and violation of voltage drop is marginal or severe, proceed for implementation of optimal reconductoring of the network.

Table -1 Voltage Drop and losses of existing Network Sistan & Balouchestan Electric Power Distribution Company S. No. Feeder Length Km Active Load Kw Reactive KVAR Power Loss KW Regulation (%) Energy Loss (%) 1 F1 52.70 2401.00 1951.00 770. 32.27 11.55 2 F2 31.70 1126.00 1087.00 95.0 7.11 3.05 3 F3 29.80 933.00 894.00 88.0 8.36 3.41

Feeders F2 & F3 are approximately equally loaded. Discussion Sistan & Balouchestan Electric Power Distribution Company On a review of Table – I : It is observed that feeder F1 is heavily loaded and losses and voltage drop are high. Feeders F2 & F3 are approximately equally loaded. The network has a heavy unequal loading, calling for reconfiguration of network.

The benefits are evaluated by pricing the peak power loss reduction at Sistan & Balouchestan Electric Power Distribution Company The benefits are evaluated by pricing the peak power loss reduction at marginal capacity cost and energy savings at marginal energy cost.

Table -II Power Loss and Voltage drop of Network for each short term measure Sistan & Balouchestan Electric Power Distribution Company Details of Short Name Voltage Energy Power Loss Benefit Works to Term Measure of Feeder Drop % Loss % Reduction % Improve- ment % Cost Ratio be Executed 1. Reconfiguration F1 9.93 4.11 83.63 22.34 10.15 13.3 KM   F2 13.08 4.81 -140.00 -5.97 of Line F3 12.12 4.77 -82.95 -3.76 2. Shunt Capacitor 19.36 5.81 59.22 12.91 10.38 4 SSCB 5.42 1.81 43.20 1.69 1 SSCB 1 SSCB 6.40 2.08 42.00 1.96 3. Reconductoring 11.39 1.93 88.05 20.88 2.911 6.1 KM 4.33 1.42 56.00 2.78 7.2 KM 6.8 KM 5.04 1.45 60.30 3.32

Table -II Power Loss and Voltage drop of Network for each short term measure Sistan & Balouchestan Electric Power Distribution Company Details of Short Term Measure Nameof Feeder Voltage Drop % Energy Loss % Power Loss Reduction % Voltage Improve- ment % Benefit Cost Ratio Works tobe Executed 4. AVB F1 4.24 8.04 36.49 28.03 4.41 3 AVB   F2 0.00 2.65 3.16 7.11 1 AVB F3 2.94 3.08 10.22 5.42 1AVB 5. Series Capacitor 14.41 8.57 33.76 17.86 2.52 488 KVAR 2.62 14.73 166 KVAR 1.40 3.00 12.50 6.96 114 KVAR

On a review of Table – II: Discussion Sistan & Balouchestan Electric Power Distribution Company On a review of Table – II: It is noticed that none of the short term measures when considered alone can bring the network to set target norms of losses and voltage drop. Further, it is observed that i)Reconfiguration equalises loading on Feeders and also reduces losses of total network by 45% but neither losses nor voltage drop are within the desired limits. ii)With shunt compensation, Feeder F 1 still has high losses and voltage drop, even after it has reduced losses by 60% and improves voltage by 12%

Discussion Sistan & Balouchestan Electric Power Distribution Company iii) Reconductoring alone will bring losses of all feeders within the set target norms but the voltage drop of Feeder F1 is violated iv)Installation of AVB has brought voltage profile within the desired limits but losses of all Feeders continue to be high. v) Series capacitor will not reduce the losses and voltage drop of Feeder F 1 to set norms and the rate of return is low. 

Table -III Combinations of Short Term measures Sistan & Balouchestan Electric Power Distribution Company Type of Improvement Feeder Voltage Energy Power Loss Benefit Works to be   No Drop % Loss % Reduction % Improve- Cost Executed ment % Ratio 1. Shunt Capacitor + Reconductoring F1 2.52 1.53 90.50 29.75 4.15 4 SSCB + 16.1 KM 2 SSCB 1 SSCB F2 5.42 1.81 42.10 1.69 F3 6.40 2.08 40.91 1.96 2. Shunt Capacitor + Reconfiguration 6.59 3.63 84.28 25.68 6.96 4 SSCB + 12.1 KM 2 SSCB 1 SSCB 10.3 2.66 -25.26 -2.50 8.30 2.50 21.59 0.06 3. Reconductoring + Reconfiguration 7.32 1.19 94.15 24.95 2.58 16.1 KM + 12.1 KM 7.2 KM 6.8 KM 5.81 1.72 32.63 1.30 6.48 1.80 44.32 1.88

Voltage Improve- ment % Table -III Combinations of Short Term measures Sistan & Balouchestan Electric Power Distribution Company Type of Improvement Feeder No Voltage Drop % Energy Loss % Power Loss Reduction % Voltage Improve- ment % Benefit Cost Ratio Works tobe Executed 4. Reconductoring F1 4.78 1.01 93.90 27.49 2.72 16.1 KM + 3 SSCB 7.2 KM + + Shunt Capacitor F2 3.21 1.05 67.37 3.90   F3 3.32 0.96 73.86 5.04 2 SSCB 6.8 KM + 1 SSCB 5. Reconductoring 3.47 1.65 89.87 28.88 2.82 16.1 KM + 1 AVB 7.2 KM + AVB 4.33 1.42 55.79 2.78 1.45 60.22 8.8 KM 6. Reconfiguration 6.91 2.18 91.87 25.36 7.19 13.3 KM +SSCB 2SSCB 9.34 2.89 -35.79 -2.23 8.54 2.52 10.23 -0.18 2 SSCB

Table -III Combinations of Short Term measures Sistan & Balouchestan Electric Power Distribution Company Type of Feeder Voltage Energy Power Loss Benefit Works to Improvement No Drop % Loss % Reduction % Improve- ment % Cost Ratio be Executed 7. Reconfiguration F1 5.41 1.50 94.55 26.86 2.91 13.3 KM + 31.8 KM + Reconductoring F2 7.03 1.44 35.80 0.08   F3 6.38 1.60 44.32 2.03 8. Reconfiguration 0.00 3.42 12.48 32.27 6.36 13.3 KM + 1 AVB 1 AVB + AVB 2.84 4.07 94.73 4.27 4.01 4.11 54.54 4.35 1 AVB 9. Shunt Capacitor 0.25 5.50 61.82 30.00 6.11 4SSCB + 5.42 1.81 42.11 1.69 2 AVB 2 SSCB 1.09 1.86 47.73 7.27 1SSCB + 1 AVB

Table -III Combinations of Short Term measures Sistan & Balouchestan Electric Power Distribution Company Type of Improvement Feeder Voltage Energy Power Loss Benefit Works to   No Drop % Loss % Reduction % Improve- ment % Cost Ratio be Executed 10. Reconfiguration F1 0.00 2.00 92.59 32.25 5.25 13.3 KM + 2 SSCB + 2 AVB + Shunt Capacitor + AVB F2 1.40 2.59 21.05 5.71 F3 1.83 2.32 17.05 6.53 3 SSCB +1 AVB 2 SSCB + 1 AVB 11. Shunt Capacitor 2.52 1.53 90.50 29.75 3.89 + Reconductoring + AVB 5.42 1.81 42.10 1.69 1.09 1.86 47.77 7.27

A review of Table III indicates that: Sistan & Balouchestan Electric Power Distribution Company A review of Table III indicates that: i)The BCR of combination where Reconfiguration is done first and then other short term measure is undertaken later is better than corresponding combination where Reconfiguration is done later and the other measure is done first. ii) The results of Reconfiguration show that there is a transfer of a load from feeders F2 & F3 to feeder F1 only and the transfer between the feeders F2 & F3 is negligible . It indicates that network Reconfiguration is effective only between feeders of unequal loading .  .

Sistan & Balouchestan Electric Power Distribution Company iii)The combination of Reconfiguration+ Shunt Capacitor gives the highest BCR but it violates the voltage limits iv)The combination of Reconductoring + AVB alone satisfies both the limits of losses and voltage but BCR is very low and is not recommended.  v) The combination of Shunt Capacitor + Reconductoring has higher BCR than Reconductoring + Shunt Capacitor, as the later involves reconductoring of longer length of line. It validates Rule 3 that Reconductoring should be undertaken only after installation of capacitors required.  .

losses and obtain better BCR. Sistan & Balouchestan Electric Power Distribution Company vi)The combination Reconfiguration + Shunt Capacitor + AVB meets the targets set for losses and voltage drop and has highest BCR of 5.25 vii)The next best combination which meets the targets set is Shunt Capacitor + Reconductoring + AVB but has a lower BCR of 3.85 viii)The fact that combination of Shunt Capacitor + Reconductoring + AVB has a higher BCR compared to combination of Reconductoring + AVB indicates that installation of capacitors is necessary to reduce losses and obtain better BCR.

Sistan & Balouchestan Electric Power Distribution Company THANK ‘U’