CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 1 The CMS ECAL Endcaps Crystal ECAL Endcap Calorimeter (EE) Preshower EE 14648 EE crystals.

Slides:



Advertisements
Similar presentations
1 MICE Target Status Chris Booth 3 rd March 2004.
Advertisements

INFN Milano, Universita` degli Studi Milano Bicocca Siena IPRD May Testbeam results of the CMS electromagnetic calorimeter Alessio Ghezzi.
0 - 0.
PPRP September 2002 UK CMS 1 CMS Endcap Electromagnetic Calorimeter and Global Calorimeter Trigger, Physics & Computing Presented by Peter Hobson, Brunel.
US CMS Collaboration Meeting, May 19, Ren-yuan Zhu, Caltech PWO Crystal ECAL Ren-yuan Zhu California Institute of Technology May 19 th 2001.
2002 LHC Days at Split, Split, October 2002 D J A Cockerill - RAL 1 The ECAL Endcap Calorimeter for CMS D J A Cockerill RAL - UK 2002 LHC Days at Split.
The Lead Tungstate Calorimeter for CMS
Vacuum Phototriodes for the CMS Electromagnetic Calorimeter Endcap
Report from MICE project teams Proposed MICE organogram: revised Revised request for resources for financial year 2003/04 Review of iMICE schedules – status.
CMS ECAL Annual Review - CERN Sept 2001 R M Brown - RAL 1 Test results from 500 preproduction VPTs R M Brown RAL - UK CERN 19 September 2001.
STFC RAL EE at SLHC CERN 15/04/08 R M Brown - RAL 1 EE at SLHC What do we expect at SLHC? EE Layout VPT vulnerability to radiation - Faceplate darkening.
LHCb VELO Production Visit November 9 th 2005 Introduction to staff Status Schedule.
VELO Module PRR preparation meeting28-feb-2006 LiverpoolMassimiliano Ferro-Luzzi 1 Introduction VELO overview Overall planning A bit of (recent) history.
Richmond House, Liverpool (1) 26 th January 2004.
LHC CMS Detector Upgrade Project US CMS Trigger Upgrade Introduction to Cost & Schedule Wesley Smith, U. Wisconsin Fermilab Directors Review 16 July 2013.
ECAL End Cap Schedule issues Justin Greenhalgh This presentation will be at under EE356.
CMS-UK Oversight Committee 18/11/03 D.J.A. Cockerill - RAL 1 The CMS ECAL Endcaps Crystal ECAL Endcap Calorimeter (EE) Preshower EE.
CMS ECAL Meeting Ecole Polytechnique June 2005 A.B.Lodge - RAL 1 ECAL End Cap CMS ECAL End Cap Trigger Meeting. Meeting held 29 th - 30 th June.
D Cockerill, RAL, 8 June 2005 Dee in testbeam ProposalP Bloch, C Seez, Y Sirois Dee calibration in test beam Last period of 2006, November Heavy ions,
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 1 Status of the CMS ECAL Endcaps LHCC Comprehensive Review, June 2006 D Cockerill EE  EE large.
CMS Week March presented by John Coughlan RAL FED Hardware Status Pre-Series Manufacture Final Production Plans.
“Aggressive schedule” seen by MJPB (just for WP1) (incl. VAT) Needed to be aggressive to meet 2005/6 shutdown….
1 Development of Electronic Reporting Tools for IPPC Directive and WI Directive Workshop – Objective and next steps Tuesday 3 rd March 2009 Meeting room.
ECAL FB Meeting, D Cockerill (RAL)1 Large EE Mechanics update.
Weekly Attendance by Class w/e 6 th September 2013.
TPC meeting, GSI, 2-3 June 2003Børge Svane Nielsen, NBI1 Status of laser system TPC meeting, GSI, 2-3 June 2003 Børge Svane Nielsen, Jørn Westergaard Niels.
Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 1 DJAC: PPD CMS ECAL Hardware Tasks (i) The next 2.5 years (ii) The following 2.5 years To March.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
B W Kennedy, CCLRC Rutherford Appleton Laboratory VPTs for the CMS experiment B W Kennedy CCLRC Rutherford Appleton Laboratory St Petersburg, 26 April.
CMS ECAL End Cap EDR Meeting CERN 28 Nov. to 29 Nov 2000 A.B.Lodge - RAL 1 ECAL End Cap CMS ECAL End Cap Engineering Design Review. EDR meeting held 28.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
US CMS Collaboration Meeting, May 19, PWO Crystal ECAL Ren-yuan Zhu California Institute of Technology May 19 th 2001.
CMS Week, CERN, 2002 R M Brown - RAL 1 Performance Characteristics of Production VPTs R M Brown, B W Kennedy, P R Hobson (with crucial input from D J A.
J A Hill – EID RAL 1-2 September EE End Cap Mechanical Design ECAL EE End Cap Engineering CMS-UK Collaboration Meeting Brunel University September.
EE and SE Installation Wolfgang Funk - CERN CMS 11/9/ ) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
EE planning meeting Lucie Linssen 1 CERN EE regional centre and Dee assembly plans Dee assembly TA3, not for EE Supercrystal regional centre.
CMS ECAL Elba May 2006 R M Brown - RAL 1 The Status of the CMS Electromagnetic Calorimeter R M Brown On behalf of the CMS ECAL Group.
CMS ECAL End Cap Meeting CERN 18 Oct to 22 Oct ECAL End Cap High Voltage and Fibre Optic Monitoring Systems Progress. Progress on High Voltage and.
Compressor status AWAKE Technical Board meeting 19 August 2015.
Calibration of the CMS Electromagnetic Calorimeter with first LHC data
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 1 EE Design Status D Cockerill CERN 19 July 2006.
The CMS Electromagnetic Calorimeter at the LHC
B W Kennedy, CCLRC Rutherford Appleton Laboratory Vacuum Phototriodes for the CMS Electromagnetic Calorimeter Endcaps K.W.Bell, R.M.Brown, D.J.A.Cockerill,
1 US CMS DOE/NSF Review: May 8-10, WBS 4.0 The Electromagnetic Calorimeter Roger Rusack The University of Minnesota US-CMS L2 ECAL Manager.
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
CMS ECAL End Cap WACH4, 28 Nov 2002 D Cockerill - RAL (1) - Yield, e/MeV with production crystals and production VPTs - Pre-calibration precision using.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
CMS-UK Oversight Committee 18/11/03 R M Brown - RAL 1 Exploded view of CMS ECAL Tracker HCAL 4T solenoid Muon chambers Total weight: 12,500 t Overall diameter:
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Concept of NA62 IRC based on PWO scintillation crystals A.Fedorov, M. Korjik, A. Lobko Institute for Nuclear Problems, Minsk, Belarus A. Kourilin JINR,
High Voltage Cards & 2000 Electronic/Thermal Model. CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000A.B.Lodge - RAL -1 ECAL End Cap 1 EE End Cap Engineering.
LHCf Detectors Sampling Calorimeter W 44 r.l, 1.6λ I Scintilator x 16 Layers Position Detector Scifi x 4 (Arm#1) Scilicon Tracker x 4(Arm#2) Detector size.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
ECAL Plenary 27/2/07 D.J.A. Cockerill - RAL 1 Status of the CMS ECAL Endcaps ECAL Plenary, 27 Feb 2007 D Cockerill  VPTs  Electronics and Integration.
CMS-UK Oversight Committee 17/11/06 D.J.A. Cockerill - RAL 1 The CMS Electromagnetic Calorimeter UK Responsibilities Procurement and testing of VPTs Design.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
CSP 25th November 2010 Technical agreement number 3: overview
Resolution Studies of the CMS ECAL in the 2003 Test Beam
The Status of the CMS Electromagnetic Calorimeter
CMS Goal of the experiment
Studies of the effect of the LHC cycle on
UK CMS Oversight Committee Mtg
PROGRESS on EE VPTs, Dees D Cockerill
East Hall under construction
Presentation transcript:

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 1 The CMS ECAL Endcaps Crystal ECAL Endcap Calorimeter (EE) Preshower EE EE crystals

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 2 CMS ECAL Endcap, EE The UK is responsible for - procurement of the mechanical structures for the detector - completing the detailed design and systems integration - procurement and testing of VPTs - design and procurement of the VPT HV system - assembly of 50% of the SCs

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 3 Potential mass production suppliers: Shanghai Institute of Ceramics (SIC) North Crystals (NC), Apatity, Murmansk Pre-production full sized ECAL Endcap samples SIC: 50 received Feb EB on order NC: 7 received May more due soon ECAL Crystals Urgent need to secure additional crystal producers to meet the CMS schedule for ECAL Barrel and Endcap installation. Must ensure crystals meet CMS ECAL technical specifications, especially for radiation tolerance, before launching contracts UK leading the crystal appraisal work at the CERN H4 ECAL test beam Programme of intense test beam irradiation and monitoring with purpose built supercrystals mounted on E0’

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 4 SIC Co 60 irradiation results Induced absorption data for the SIC crystals - consistent with results from BCTP crystals Specification limit 1.5 m Gy in 1.1h

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 5 Crystal test beam appraisal with E0’ Supercrystal in assembly jig with 15 SIC Endcap crystals for test beam appraisal 10 remaining pockets for BCTP crystals as control/comparison

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 6 Vacuum Photo-triodes (VPTs) 25.4 mm VPT Production – good progress 7900 (51%) delivered Concerns: - anomalous devices, 6% of production Observations: - production about 4 months behind contracted delivery agreement. Not on critical path.

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 7 EE large mechanics Excellent progress. Large mechanics for first Endcap finished at TM, on schedule. BP flat to 0.4mm across 3.4m BP precision holes to within 50  m to neighbour

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 8 EE large mechanics Ring flanges 2 cast, machined and completed Load tested to 12.75t (versus 8t in CMS) Deflection: 0.4mm at 12.75t in agreement with FEA Holes to within  m, within request Cooling and positional spacers

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 9 Front-End Electronics Engineering run for DSM ASICS successful (enough for 3 SMs) Launch full production of electronics in mid-summer. Plan is to have a full SuperModule in beam by the end of September Conversion to 0.25  m electronics has been very successful! 25 channels ECAL Trigger Tower Test Beam October 2003  E/E 1% 0.5%

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 10 EE electronics integration Remaining major UK design/procurement task Detailed design for the integration of electronics and services on the back of EE Progress: Mass production of 500 cooling bar castings commencing Mon May 17 Completion of castings End June 2004

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 11 Surface SX5 installation of EB+ (and as many EB- as possible) Dec 2005 until January 15 th 2006 Underground UX5 installation 1 (before Tracker)May 2006 UX5 installation 2 (after Tracker) November 2006 CMS closed April –June 2007 Pilot run End late Summer 2007 ECAL Endcap EE/SE+ installation October 15 th –November 15 th 2007 EE/SE- Installation March 2008 Physics run CMS planning, main dates of CMS V34 P Bloch

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 12 Crystal Planning P Bloch Possible delivery profiles with 2 crystal suppliers, P Bloch Barrel crystal schedule → End Cap crystal schedule → Total

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 13 EE planning P Bloch Need highly parallel production, good planning and preparation for 2006/7

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 14 CMS EE Conclusions Late EE crystal delivery THE major concern - SC mass production on hold UK successfully undertaking its deliverables to CMS - VPT procurement, test and appraisal - large mechanics design and procurement - HV system design - Electronics integration

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 15 Additional info follows, next slide

CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 16 Impact on UK programme, late crystal delivery Good planning, preparation and parallel production will be needed for the assembly of 4 Dees in 2006/7 Use all the resources that will become available : UK SC assembly laboratory CERN ECAL barrel assembly team and infrastructure Possible technicians at CERN from Rome The separate CERN TA1 group and CERN SC/Dee assembly laboratory Gain assembly experience beforehand SC construction - will have ~ 250 EE crystals from this summer = 10 SCs - ‘SC challenge’ to show we can assemble 10 SCs per week Test beam experience – integration of electronics, laser monitoring system Dee pre-assembly experience of mechanical and cooling items, with CERN TA1 group Dee electrical looming prepared ahead of time