Ion Source and LEBT Beam Diagnostics

Slides:



Advertisements
Similar presentations
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
Advertisements

Requirements Structure and Status for NCFE
PSSC Space Instrument Laboratory Plasma instrument calibration system provides an ion beam of energy range up to 130keV/charge in a clean room To develop.
Bubble Chamber Planning Meeting 04 September
ITS Subsystems Availability MACS Week, June 2011 E. Sargsyan PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 1.
E. Beebe LEBT & Ion Injection EBIS Project Technical Review 1/27/2005 LEBT and External Ion Injection Ed Beebe Preinjector Group Collider-Accelerator Department.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
AWAKE electron source New Electron Source WP at CERN
FETS H - Ion Source Experiments and Installation Scott Lawrie, Dan Faircloth, Alan Letchford, Christoph Gabor, Phil Wise, Mark Whitehead, Trevor Wood,
Uli Raich CERN BE/BI Instrumentation for the new H - Source Test Bench Linac-4 Ion Source Review 2011 Uli Raich CERN BE/BI Linac 4 ion source review, CERN.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Imperial College 1 Plans and Costs Front End Test Stand Aim is to demonstrate a 60 mA, 2 ms, 50 pps chopped beam at 3 MeV RAL/ISIS (ION SOURCE, CHOPPER,
UKNF OsC RAL – 31 st January 2011 UKNF - Status, high lights, plans J. Pozimski.
J. Alessi Implementation Plan EBIS Project Technical Review 1/28/05 Implementation Plan WBS exists Working on a “bottoms up” cost estimate The following.
1 1. Some recent views ( ) 2 Linac tunnel
Results of the argon beam test at Linac3 D. Küchler BE/ABP/HSL Including feedback from R. Scrivens and M. Bodendorfer.
Ion Sources – Hardware and Operation MACS Week Friday 8th October 2010 PP a-LPE, 8 th October 2010, MACS Week 2 Liviu Penescu, „Ion Sources.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Developments of the FETS Ion Source Scott Lawrie.
Low Energy RHIC e - Cooling Meeting Minutes – 12/23/ Cooling Section: –LF Solenoids:  At PPM, G. Woods has assigned buyer, SOW will be revised,
Michał Matusiak Sławomir Wronka
RFQ – Design, Components and Fabrication 1 We aim to design and manufacture a Radio Frequency Quadrupole (RFQ).
FETS-HINS Videoconference 23rd Feb 2007 FETS Mechanical Design Issues by J. Pozimski On behalf of P. Savage.
LINAC3 UPGRADE Source and LEBT modifications for YETS and recommissioning timetable 28/10/2015 Ville Toivanen.
H4F Physics Day 2014 C.Ullmann Proton injector status for FAIR and measurements at BETSI test bench (CEA/Saclay) 2014.
PXIE Ion Source and LEBT Installation Status L. Prost, B. Hanna, R. Andrews Project X Technical Meeting October 29 th, 2013.
PS-ESS and LEBT State of the art Lorenzo Neri Istituto Nazionale di Fisica Nucleare Laboratori Nazionali del Sud.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
The ESS high intensity proton source and the LEBT: status, planning & open points L. Celona on behalf the LNS team Istituto Nazionale di Fisica Nucleare.
PXIE LEBT Status Update Lionel Prost PIP-II “Friday” Meeting January 16 th, 2015.
ESS Vacuum Standardization
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
WU2 - Proton Source & LEBT Schedule 2013 L. Celona Istituto Nazionale di Fisica Nucleare Laboratori Nazionali del Sud.
ESS Front End diagnostic
PXIE Ion Source & LEBT Commissioning Update Lionel Prost on behalf of A. Shemyakin, R. Andrews, B. Brooker, K. Carlson, J. Czajkowski, R. D’Arcy, B. Hanna,
3 MeV Measurements at Lianc4 1 Veliko Dimov (for the source and linac team) (J-B Lallement, J. Lettry, A. Lombardi, D. Fink)
Status of Mechanical Design of LEBT Rich Andrews, Matt Alvarez, Tim Hamerla, Danny Snee.
Report Technical Director Storage-Ring-Installation Completed
NICA injection complex status
Integration of the e+ elements
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Lesson learnt – WP3 S. Gammino.
LINAC 4 source & LEBT measurement results
Proton Source and LEBT Luigi Celona & Lorenzo Neri
LINAC4 LEBT beam size and emittance diagnostics
Tom Shea Front End Meeting Catania
GlueX Electronics Review Jefferson Lab July 23-24, 2003
Bubble Chamber – Beam Requirements
Andreas Jansson, Lali Tchelidze
commissioning and measurements
Beam Commissioning at ESS
Testing and deployment
Ion Source and LEBT control system topology, Interlock strategy
Personnel Safety system 0 for the Ion Source and LEBT (PSS0)
ISRC and LEBT Vacuum System Design
Testing Coordination at ESS
MPS commissioning at ESS
LEBT water cooling system
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
PSS Verification and validation
Tom Shea, Andreas Jansson, Cyrille Thomas
(Beam) Commissioning Plan
Front End Test Stand (F.E.T.S.) Engineering Progress Report
Safety Readiness Review (SRR) Thomas Hansson, ESH
Beam Commissioning Planning
Operation of Target Safety System (TSS)
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
ISrc & LEBT – ICS Installation Readiness Review
Presentation transcript:

Ion Source and LEBT Beam Diagnostics Tom Shea Beam Diagnostics Section Leader Beam Diagnostics (WP7) Work Package Manager SRR 1 – Ion Source & LEBT 2018-07-17--18

Beam Diagnostics Beam Diagnostics Beam Diagnostics Beam Diagnostics Plasma chamber Extraction system Pumping box Solenoid 2 x steerer Gate valve Iris Diagnostics tank Chopper EMU H+V Faraday cup NPM H+V Doppler shift 2 x TMP Repeller ACCT Commissioning tank (RFQ) HV power supply Isolation transformer Collimator Magnetron H2 bottle Ion source LEBT 1 LEBT 2 3 x solenoid Waveguide Primary pump High voltage (HV) platform Low energy beam transport (LEBT) PSS0 controlled area and radiation shielding Front End and Magnets Cooling water Vacuum PSS Beam Diagnostics Control system Voltage divider HV controls Ground potential controls Beam stop Alternative location of beam instruments for commissioning N2 bottle ACCT: AC current transformer EMU: Emittance measurement unit NPM: Non-invasive profile monitor TMP: Turbomolecular pump Beam Diagnostics Beam Diagnostics Beam Diagnostics

Table of Content System Requirements Safety Aspects Operating procedures and training Test & Verification Remaining issues

System Requirements Measurement Requirements allocated to 5 system types Beam Accounting Beam Current Monitors (BCM) Faraday Cup (FC) Doppler (DPL) Beam Centroid Non-invasive profile monitor (NPM) Beam Distribution Emittance measurement unit (EMU) Examples of key requirements 1 mA accuracy on current 1% uncertainty on ion species fraction 100 µm accuracy on position 10% beam size precision 10% emittance accuracy

System Components Non-invasive Profile Monitor Camera system Most electronics rack-mounted, power via Schuko sockets Beam Current Monitor for Ion Source Supply Current Doppler Spectrometer Emittance Measurement Unit Actuator on LEBT Faraday Cup on LEBT

Safety Aspects The Beam Diagnostic systems are not classified as safety systems During IS and LEBT commissioning, they are not yet relied upon to report beam properties that are limited by licensing conditions. They do contribute to a safe operations culture by providing situational awareness. Trustworthy operation is assured by completing calibration prior to beam operations The beam diagnostics section members participate in commissioning activities to verify performance with beam They do present some hazards that are mitigated by by engineering controls. As a primary example, finger-safe enclosures encapsulate: voltage/current mechanical pinch points

Operating procedures and training One user manual per system. Training will be provided prior to first protons. One high-level operator screen per system Key beam data consolidated on overview screens Faraday Cup screen

Test & Verification One Verification Plan/report per system Data in HDF5 linked to each asset (field-replaceable units and systems) System FAT SAT Installation Integration Verification Verification with beam BCM FC EMU Doppler NPM completed in progress

Remaining Issues week 28 29 30 31 32 33 34 35 36 37 38 39 Oct First rack powered Beam ~4 weeks to integrate and verify all systems ICS infrastructure ~3 weeks for issue mitigation and training Verify BCM Verify FC Verify NPM and DPL Verify EMU (single plane) Beam verification, BCM, FC Beam verification, EMU, NPM, DPL Install repaired EMU (second plane)