Brief report of the hardware commissioning activities

Slides:



Advertisements
Similar presentations
Frédérick BORDRY – LHCMAC 22- 6th December 2007 Review of the experience of LHC powering: short-circuit tests and sector 7-8 and start of powering sector.
Advertisements

New HV test specification for the LHC N. Catalan for the EI section.
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
LHC Magnet Tests: A challenge for an OperationTeam V. Chohan G.H. Hemelsoet CernGeneva Always set the trail, never follow the path.
CRYOGENICS AND POWERING
Powering Group of Circuit Doubts and proposals of the procedure reviewing team (Gianluigi, Rob, Sandrine, Matteo, Boris) Ref document: LHC-MPP-HCP-071.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
LARP Collaboration April 26 th 2006 The Commissioning of the Technical Systems of LHC 1.The final validation that all the collider components/systems.
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Powering of the Superconducting Circuits: Procedures and Strategies for Circuit Validation Antonio Vergara on behalf of the Hardware Commissioning Coordination.
LHC Hardware Commissioning Review May 2005, CERN, 1211 Geneva 23 1 LHC Hardware Commissioning Review Contribution ID: 20 – Quality assurance and.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
1 Copper Stabilizer Continuity Measurement Project Copper Stabilizer Continuity Measurement Status & Plans – May 2011 MPE-TM – 12 May 2011 M. Koratzinos,
HC Review F. Rodriguez-Mateos Powering tests The outcome of the work conducted within HCWG and many discussions among colleagues.
Roberto Saban LEMIC Coordination of Hardware Commissioning  Sector 78 Cooldown Cooldown Powering Tests Powering Tests Test of software for the.
Hardware Commissioning Tools Robin. AB-CO TC 8th February 2007Hardware Commissioning Tools - RJL2 Summary Hardware Commissioning View Slides from Antonio.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
16-17 January 2007 Post-Mortem Workshop Logging data in relation with Post-Mortem and archiving Ronny Billen AB-CO.
Review of Sector th of February Tunnel Access During Powering Tests Hugues Thiesen, AB-PO.
AT-MEL Group Meeting, CERN, 1211 Geneva 23 1 ElQA activities during hardware commissioning N. Catalan Lasheras.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
Roberto Saban TS HC Review bis Outline  Interviews of all the Group Leaders loosely or tightly concerned by hardware commissioning proposing them.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
An invitation to an open discussion We are team reviewing its performance globally We want to help each other to reach the objectives We know the other.
The prototype test String 2 May 13, 20082Roberto Saban – Academic Training Lecture 1 – Why LHC Hardware Commissioning?
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
Considerations from machine protection and the ELQA teams
Electrical insulation of magnet circuits in sector 7-8
Powering LHC magnets version 30/3/2007.
ELQA Electrical Quality Assurance
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Minimum Hardware Commissioning – Disclaimer
The HL-LHC Circuits: Global View and Open Questions
LHC Hardware Commissionning
Giorgio on behalf of ELQA team
12 October 2009 RRB Plenary R.-D. Heuer
The LHC - Status Is COLD Is almost fully commissioned
Coordination of Hardware Commissioning
Consequences of warming-up a sector above 80 K
Powering the LHC Magnets
MPE main activities planned for LS2
Dipole diode lead resistance measurement
Powering from short circuit tests up to nominal
Circuits description and requirements - Closed Session-
TE-MSC activities in SPS during YETS
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
Detailed global view on protection and detection of the circuits
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Rüdiger Schmidt and Karl Hubert Mess
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Machine Protection Xu Hongliang.
+ many slides from various colleagues (KH, Rudiger, Paul, …)
Scrubbing progress - 08/12/2012
Commissioning of the LHC superconducting magnets systems: Why an LHC Hardware Commissioning? Specificity and complexity of this machine Roberto Saban.
Hardware Commissioning
Review of hardware commissioning
Other arguments to train two sectors to 7 TeV
Presentation transcript:

Brief report of the hardware commissioning activities Roberto Saban on behalf of the Hardware Commissioning Teams in the AT,AB & TS Departments Short Circuit Tests Commissioning of machine systems in the Long Straight Sections Commissioning of Sector 78 Preparation for Commissioning for the other sectors Deployement and Resources Notable events Sct : difficult start, now routine, mastered by many LSS : mostly carried-out by equipment groups (RF, injection, etc) but warm magnets Preparation : a lot learnt from 78, being applied to 45, 81 & 34 The sc magnet commissioning would be the most difficult, dense and delicate

official schedule

major events & timeline Stable cryogenic conditions @ 2K Average magnet temperature in Sector 78 Simulated

major events & timeline Simulated Longer filling time, interruptions of utility systems, difficulties with the tuning of the pumping group, swap of the cryoplant & DFB commissioning Stable cryogenic conditions @ 2K Average magnet temperature in Sector 78 First time Huge cryoplant, novel techniques on real load Several large components never even cooled down A lot of experience gained which will profit in the coming sectors

major events & timeline Verification of the Voltage Taps on the HTS CL Longer filling time, interruptions of utility systems, difficulties with the tuning of the pumping group, swap of the cryoplant & DFB commissioning Stable cryogenic conditions @ 2K Average magnet temperature in Sector 78

major events & timeline ElQA @ 80K Verification of the Voltage Taps on the HTS CL Filling of the arc magnet coldmasses Swap of cryoplant and tuning First superfluid helium in the arc Stable cryogenic conditions @ 2K DFBs cleared for operation with current 4.5K Magnet & associated DFBs full with liquid Average magnet temperature in Sector 78

major events & timeline Swap of cryoplant and tuning First superfluid helium in the arc Stable cryogenic conditions @ 2K DFBs cleared for operation with current Average magnet temperature in Sector 78

non conformities Voltage tap of QF Intermittent fault on QD Presence of a few SSS with known bus-bar non-conformity Presence of a « Bad » dipole Doubts about the quality of some interconnects

Circuits powered from the powering areas via DFBs Circuit Type Sector LHC 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-1 13 kA 3 24 Indipendently Powered Dipoles 2 1 16 Indipendently Powered Quadrupoles 14 7 6 13 12 5 78 600A with Energy Extraction 23 27 28 202 600A Energy Extraction in Converter 20 136 600A no Energy Extraction 9 72 80-120A Correctors 50 37 22 33 284 TOTAL 123 105 83 99 95 79 812 Limited Current: RB (2 kA), RQF (6.5 kA), RQD (350 A) 3 Only RD2, Inner triplet dipole not available 1 Only RQ4 and RQ5 2 14 Line-N Circuits, 3 spool piece correctors & 2 MQTLH 19 Three Line-N Circuits RCO and inner triplet correctors not available Q4 and Q5 available correctors 7 Minimum Total Required 35 Voltage tap of QF Intermittent fault on QD Presence of a few SSS with known bus-bar non-conformity Presence of a« Bad » dipole Doubts about the quality of some interconnects Circuits powered from the arc Circuit Type Sector LHC 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-1 60A Closed Orbit Correctors 94 752 4 5/7/2019 Roberto Saban

commissioning of circuits First superfluid helium in the arc Stable cryogenic conditions @ 2K DFBs cleared for operation with current 4.5K Magnet & associated DFBs full with liquid Average magnet temperature in Sector 78 ElQA & Powering of four 60A circuits

commissioning of circuits First superfluid helium in the arc Stable cryogenic conditions @ 2K DFBs cleared for operation with current 4.5K Magnet & associated DFBs full with liquid Average magnet temperature in Sector 78 DFB commissioning ElQA & Powering of all the circuits in the matching section left of Point 8 All powered to nominal current

commissioning of circuits First superfluid helium in the arc Stable cryogenic conditions @ 2K DFBs cleared for operation with current 4.5K Magnet & associated DFBs full with liquid Average magnet temperature in Sector 78 ElQA of the arc magnets

Electrical Quality Must further investigate the design of the electronics for the cryogenic instrumentation

progress DFBs cleared for operation with current Stable cryogenic conditions @ 2K

notable events: coupling between Q4 and D2 After the separate commissioning of all the matchings section magnets at operating at 4.5K, the magnets were powered in unison varying the current in one of the magnets (Q4) while the other (D2) was sitting at nominal current. A coupling between the two circuits was observed, since D2 quenched. The experiment was repeated and gave consistently the same result. The probable cause is a cold cabling non-conformity:

notable events: coupling between Q4 and D2

notable events: insulation fault in the dipole circuit QPS DFBAN DFBAO MBB MBA Time of flight measurement along the transmission line

sector 78 is closed Access control point Locked door allowing escape

Hardware Commissioning organization 16.30 7.00 15.00 22.00 morning shift 8.30 afternoon shift HCC EIC PIC POC MELC MPP CPP ACR VAC CV EL Soft Hardware Commissioning Coordination Meeting

on call outside normal working hours the CCC & the field HCC EIC OP FCR Point8 or CCC 2 shifts POT POI QPS EE QPS EE PIC Cryo the field Equipment owners on call outside normal working hours on-call during normal working hours good will outside normal working hours HCC MPP Mr Circuit CPP EL CV MEL-CF POE QPS/EE CO PIC MEL-CF VAC ACR

the actors Cryogenics DFBs Electrical Quality Assurance Quench Protection Power Converters Magnet constructors Interlocks Energy Extraction Controls Glued together by Hardware Commissioning Coordination and the Operation Group

the tools targeted diagnostic instrumentation automated test program sequencing performant diagnostic tools logging system monitoring web pages post mortem & analysis tool collaborative tools logbook twiki mtf

What can slow us down? Non-conformities observed during ELQA The commissioning the cryogenic system and DFBs The commissioning the DFBs with current Time for fixing issues, such as condensation on the DFBs, on current leads, … Time for quenching magnets Time for cool down after a quench The availability of the cryogenic system The availability of utilities (water, electricity, computer network) Unexpected/training quenches Data analysis of unexpected events 5/7/2019 Roberto Saban

… in summary sector 78 is far from being commissioned what is commissioned however is: operating mode automate sequencing of tests diagnostic tools test data recording tools quality assurance and progress follow up above all, the team is built and is performing well