Specifications Updates and Approval

Slides:



Advertisements
Similar presentations
Model Specification Requirements MSRATF Meeting – Mar 11, 2013 Stephanie Lu, MVWG Chair Seattle City Light.
Advertisements

1 MSRATF Update to TSS (Modeling SPS and RAS Ad Hoc Task Force) Scope of Work Approval January 25, 2013 Joe Seabrook Puget Sound Energy.
Underfrequency Load Shedding Report
1 MSRATF Update to TSS (Modeling SPS and RAS Ad Hoc Task Force) May 15, 2013 Joe Seabrook Puget Sound Energy.
Bulk Electric System Definition Task Force Update Reliability Policy Issues Committee March 4, 2010 Brian Theaker BESDTF Chair.
Marv Landauer Report to TSS on RS Activities April 25-27, 2012 Salt Lake City.
Presented to PGDTF February 11, 2015
1 MSRATF Update to TSS (Modeling SPS and RAS Ad Hoc Task Force) Activities August, 2014 Joe Seabrook Puget Sound Energy, Inc.
1 MSRATF Update to TSS (Modeling SPS and RAS Ad Hoc Task Force) Activities May, 2014 Joe Seabrook Puget Sound Energy, Inc.
TRANSMISSION & INTERCONNECTION PLANNING T&D BUSINESS UNIT 1 Distance Relay Specification WECC TSS January 23,2014 Amos Ang.
TRANSMISSION & INTERCONNECTION PLANNING T&D BUSINESS UNIT 1 Current Differential Relay Specification WECC TSS August 20,2014 Amos Ang.
Generator Data Submittals 5/8/ Transmission Customer Forum Bob Jones Transmission Planning Southern Company Transmission 5/8/ Transmission.
Project WECC-0100 Update Reliability Subcommittee February 2014.
December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
Application and Implementation of State Estimator at Idaho Power Company S. Kincic and M. Papic.
1 Planning the CREZ 345 kV System for Multi-contingencies CREZ Technical Conference January 26, 2010 Bernie Pasternack AEP Service Corporation.
Tracy Rolstad TSS Chair TSS Chair Report March 2014 Salt Lake City, UT 1.
Introduction To Protective Relays
WECC-0100 Scope, Content & Status Update Rikin Shah, PAC Orlando Ciniglio, IPC WECC TSS Meeting, Salt Lake City, UT January ,
N-1-1 Contingency Analysis & Relay Protection 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006.
TRANSMISSION & INTERCONNECTION PLANNING T&D BUSINESS UNIT 1 Directional Overcurrent Relay Specification WECC TSS January 23,2013 Amos Ang.
Nodal Planning Go Live Austin, TX February 3, 2011
Project WECC-0100 Standards Briefing WECC-0100 SDT April 7, 2016 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Announcements Design Project has firm due date of Dec 4
NERC Published Lessons Learned Summary
Freeport Area Master Plan Project -
Protection Relay Modeling for Transient Stability Simulation 10/26/2016 CJ Jing, David Franklin, Kevin Moran.
Transmission Planning in ERCOT- Overview
NOGRR-169 OWG discussion Bill Blevins June 28, 2017.
ECE 476 Power System Analysis
UFLS Workshop Discussion #3
WECC Load Modeling and Validation Group Meeting
NERC Published Lessons Learned Summary
Next Steps in Load Modeling
PRC Implementation Plan and Summary of Devices
Long-term Planning and TPL TP Workshop November 2, 2017
Western Electricity Coordinating Council
Phil O’Donnell, Manager Operations and Planning Audits
What is an Operation and Misoperation
Presented by: LADWP November 14, 2017
Kenneth Silver Los Angeles Department of Water & Power
Kenneth Silver Los Angeles Department of Water & Power
NERC TPL Standard Overview
Project WECC-0100 Update Load Modeling Task Force
Reliability Assessment Committee Reliability Workshop Priorities
Protection Philosophy
Protective Relaying Conference
CMPLDWG Composite Model with Distributed Generation Approval
Protection Relay Modeling for Transient Stability Simulation 10/26/2016 CJ Jing, David Franklin, Kevin Moran.
Considerations and Benefits of Using Five Zones for Distance Protection Ricardo Abboud, Jordan Bell, and Brian Smyth Schweitzer Engineering Laboratories,
Accurate Fault Location Using Modeling and Simulation
Andrew Christensen, SDWG Chair
Joe Seabrook Puget Sound Energy, Inc.
Jonathan Young SDWG Chair
What is an Operation and Misoperation
Reliability Assessment Committee Reliability Workshop Priorities
CMPLDWG Composite Model with Distributed Generation Approval
Project WECC-0100 Update Reliability Subcommittee
SRWG Chair Report March 2015 WECC HQ
WECC Load Modeling and Validation Group Meeting
TPL Voltage Guideline Presented to TSS Baj Agrawal Arizona Public Service Co. 8/21/2017.
Kenneth Silver Los Angeles Department of Water & Power
Palo Verde-COI RAS Retirement
Project WECC-0100 Update Load Modeling Task Force
Distance Relay Specification
Andrew Christensen, SRWG Chair
Palo Verde-COI RAS Retirement
System Review Work Group Update to TSS
Joe Seabrook Puget Sound Energy, Inc.
Information Sharing Policy Update March 25-26, 2014
Presentation transcript:

Specifications Updates and Approval Distrelay model Specifications Updates and Approval Megan Cammarano | MVWG Meeting | June 15, 2016

Updates to WECC Model Specifications overview Drivers and Need Updates to WECC Model Specifications The Generic Distance Relay Model was approved January 23, 2014 Model Approval Including examples of proper operation

Drivers and need

2011 Southwest blackout event FERC & NERC report called for improved planning Modeling of automatic actions Reduce assumptions made on timing of actions Expand entities’ external visibility More complete data sharing WECC response agreed to model relays TSS created the Modeling SPS and Relays Ad-Hoc Task Force (MSRATF) to develop and/or implement relay models WECC developed DISTRELAY model specs

Tpl-001-4 Accurate representation of system elements Protection will have significant impact on system performance As stated in TPL-001-4, R4, Part 4.3.1.3 analysis should include: “Tripping of Transmission lines and transformers where transient swings cause Protection System operation based on generic or actual relay models.”

PRC-026 Ensuring load-responsive protective relays do not trip in response to stable power swings during non-Fault conditions Relay models as a part of the system model allow for PRC-026 testing as a part of the annual TPL assessment Requirement R1 criterion 4 references TPL-001-4 and states relay tripping must be assessed within the annual TPL assessment

Updates to wecc model specifications

Add language If the fault persists, both ends should reopen, following the same timeline as their initial opening. If the input parameter RecloseWithFault is set to 0, when the fault persists, the second end to reclose will not reclose.

Include parameter “reclosewithfault” Allows for line “testing” Set parameter to 0 to enable If the first end of the line to reclose recloses on a fault, the second end of the line will not reclose

Motion Change model specifications to those outlined: Include clarification that relays should be able to trigger breakers to reopen after reclosing if the fault persists Add parameter “RecloseWithFault” to allow for line testing

Model approval

Seattle City light system overview Service area population: ~800,000 ~1,900 MVA system load peak 15 major substations 50 transmission lines (656 miles) 92 distance relays

Model examples Using PowerWorld Version 19 Without transfer trip Direct Underreaching Transfer Trip (DUTT) Permissive Overreaching Transfer Trip (POTT)

Example W/O Transfer Trip Contingency: Three-phase fault applied at 1 second on Shoreline to Bothell Ckt 2 at 10% of the line

Example W/O Transfer Trip Bus 1 should open 6 cycles after the fault is applied (Zone 1 Protection) Bus 2 should open 26 cycles after the fault is applied (Zone 2 Protection) Bothell Shoreline

Simulation results correct! Example w/o transfer trip Transient Stability Started at 5/18/2017 3:06:00 PM Time: 1.000 Event: Apply Solid Fault (3PB) Line BOTHELL TO SHORELIN CKT 2 Time: 1.000 Event: Relay A Zone 1 tripped Line BOTHELL TO SHORELIN CKT 2 Time: 1.100 Event: Line Relay DISTRELAYRF,Direct Trip action: Open From End Line BOTHELL TO SHORELIN CKT 2 Time: 1.333 Event: Relay A Zone 2 tripped Line BOTHELL TO SHORELIN CKT 2 Time: 1.433 Event: Line Relay DISTRELAYRF,Direct Trip action: Open To End (Both ends now Open) Line BOTHELL TO SHORELIN CKT 2 Transient Stability Solution Finished at 5/18/2017 3:11:01 PM

Simulation results Example W/O Transfer Trip

Simulation Results Example W/O Transfer Trip

Simulation Results Example W/O Transfer Trip

Example W/ Transfer Trip (DUTT) Contingency: Three-phase fault applied at 1 second on Bothell to Diablo Ckt 1 at 10% of the line

Example W/ Transfer Trip (DUTT) Bothell should open 6 cycles after the fault is applied (Zone 1 Protection) Diablo should open 1 cycle after that (TT communication time) Bothell Diablo

Simulation results correct! Example w/ transfer trip (DUTT) Transient Stability Started at 5/15/2017 1:19:29 PM Time: 1.000 Event: Apply Solid Fault (3PB) Line BOTHELL TO DIABLO CKT 1 Time: 1.000 Event: Relay A Zone 1 Entered (pickup) Line BOTHELL TO DIABLO CKT 1 Time: 1.100 Event: Line Relay DISTRELAYRF,Direct Trip action: Open From End Line BOTHELL TO DIABLO CKT 1 Time: 1.117 Event: Line Relay DISTRELAYRF,Transfer Trip action: Open To End (Both ends now Open) Line BOTHELL TO DIABLO CKT 1 Transient Stability Solution Finished at 5/15/2017 1:24:25 PM

Simulation results Example W/ Transfer Trip (DUTT)

Simulation results Example W/ Transfer Trip (DUTT)

Simulation results Example W/ Transfer Trip (DUTT)

Example W/ Transfer Trip (pott) Contingency: Three-phase fault applied at 1 second on Delridge to Duwamish Ckt 1 at 10% of the line

Example W/ Transfer Trip (pott) Delridge should open 6 cycles after the fault is applied (Zone 1 Protection) Duwamish should open 1 cycle after that (TT communication time) Delridge Duwamish

Simulation results correct! Example w/ transfer trip (POTT) Transient Stability Started at 5/15/2017 2:06:46 PM Time: 1.000 Event: Apply Solid Fault (3PB) Line DELRIDGE TO DUWAMISH CKT 1 Time: 1.000 Event: Relay A Zone 1 Entered (pickup) Line DELRIDGE TO DUWAMISH CKT 1 Time: 1.100 Event: Line Relay DISTRELAYRF,Direct Trip action: Open From End Line DELRIDGE TO DUWAMISH CKT 1 Time: 1.117 Event: Line Relay DISTRELAYRF,Transfer Trip action: Open To End (Both ends now Open) Line DELRIDGE TO DUWAMISH CKT 1 Transient Stability Solution Finished at 5/15/2017 2:11:56 PM

Simulation results Example W/ Transfer Trip (POTT)

Simulation results Example W/ Transfer Trip (POTT)

Simulation results Example W/ Transfer Trip (POTT)

DISTRELAY is functioning properly for multiple contingencies Conclusion DISTRELAY is functioning properly for multiple contingencies No significant increase in computation time With 92 DISTRELAY models

motion Approve DISTRELAYRF model and add to WECC Approved Dynamic Model Library Note: Please do not use on series compensated lines until further testing is completed