Detailed global view on protection and detection of the circuits

Slides:



Advertisements
Similar presentations
TE-MPE-CP, RD, 03-Dec Quench Detection and Energy Extraction Systems R. Denz (Quench Detection), K. Dahlerup-Petersen (Energy Extraction Systems),
Advertisements

REVIEW OF THE CRYOGENIC BY-PASS FOR THE LHC DS COLLIMATORS ELECTRICAL CIRCUIT MODIFICATION, INCLUDING OPERATIONAL CONSIDERATIONS PRESENTED BY A. SIEMKO.
How to achieve higher redundancy of the UPS for QPS ? -The lack of redundancy concerns the supply lines from UPS to consumer but equally parts of the UPS.
TE-MPE-EP, RD, 06-Dec QPS Data Transmission after LS1 R. Denz, TE-MPE-EP TIMBER PM WinCC OA Tsunami warning:
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
E. Todesco HL-LHC: OUTLOOK ON PROTECTION FOR IR MAGNETS (WP3) E. Todesco CERN, Geneva Switzerland CERN, 23 rd April 2015 MPE meeting.
CERN Rüdiger Schmidt FCC week 2015 Long Magnet Stringpage 1 Incident September 19 th Architecture of powering and protection systems for high field.
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
AT-MEL-PM, R. Denz, CERN, CH-1211 Geneva 23 1 QPS system and its risks  Principal risks  General remarks  Quench heater circuits  Quench detection.
AT-MEI-PE, RD, LIUWG 31-JUL R. Denz AT-MEI-PE LHC Luminosity Upgrade Protection of the Inner Triplet, D1, Correctors and Superconducting Links/Leads.
F. Savary Question 1 A. Magnet design criteria for the prototype and production magnet to be tested before the installation into the tunnel.
5 th Joint Hi-Lumi LHC-LARP Annual Meeting 2015 SC Link Protection A.Ballarino 28/10/2015.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
Andrzej SIEMKO CERN, Geneva The 2014 Kyoto Workshop on HTS Magnet Technology for High Energy Physics –WAMHTS-2.
TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb R. Denz TE-MPE-CP on behalf of the QPS team QPS Upgrade and Re-commissioning.
16-17 January 2007 Post-Mortem Workshop Logging data in relation with Post-Mortem and archiving Ronny Billen AB-CO.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
QPS Signal Analysis Case studies from MPP and QPS Bob Flora.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
J.C. Perez, S. Izquierdo Bermudez 11T Dipole models instrumentation.
CERN TE-MPE-EP, RD, 09-April Quench Protection Systems (QPS) for the LHC R. Denz, TE-MPE-EP Acknowledgements: K. Dahlerup-Petersen, A. Siemko, J.
TE-MPE-CP, RD, 28-Sep Problems with QPS DAQ Systems During LHC Operation, 1 st Results from 2010 CNRAD Tests R. Denz TE-MPE-CP.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Inner Triplet Protection Strategy LHC & HL-LHC Daniel Wollmann with Inputs from B. Auchmann, G. Ambrosio, R. Denz, P. Fessia, E. Ravaioli, F. Rodrigues.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
Cold powering test results of the 11 T cosθ model magnets at CERN Gerard Willering With thanks to Jerome Feuvrier, Vincent Desbiolles, Hugo Bajas, Marta.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Cold mass design, assembly plans and QA/QC at CERN
HL-LHC IT STRING and Series test of SC link
D1 and D2 powering and protection
R. Denz, A. Gomez Alonso, AT-MEL-PM
MQY-30 Test Result Report
Quench Simulation at GSI
Powering LHC magnets version 30/3/2007.
Minimum Hardware Commissioning – Disclaimer
The HL-LHC Circuits: Global View and Open Questions
State of discussions in preparation for the HL-LHC Circuits Review
Circuits description and requirements
Document Plan & Milestones WP7
Ideas and design concepts, and challenges
12 October 2009 RRB Plenary R.-D. Heuer
R&D of neutrino beam production for future (Multi-)MW proton facility:
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
Powering the LHC Magnets
Felix Rodriguez Mateos for the MCF
International Review of the Conceptual Design of the Cold Powering system for the HL-LHC Superconducting Magnets J.Ph. Tock
Update on circuit protection simulations of the HL-LHC Inner Triplet circuit Matthias Mentink, Circuit specifics + STEAM simulations: Samer Yammine, LEDET.
MBHSP02 test STATUS and first results
Focus Coil Quench Detector
Quench Protection Measurements & Analysis
Powering from short circuit tests up to nominal
Circuits description and requirements - Closed Session-
Knud Dahlerup-Petersen
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
Quench detection electronics for the HL-LHC magnet circuits of the LHC
TEST PLANS for HL LHC IT STRING
+ many slides from various colleagues (KH, Rudiger, Paul, …)
WP3 Meeting – December the 10th 2015 H. Prin
LHC OPERATION AND SUPPORT
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
Hilumi WP3 meeting, 1 October 2014
Machine Protection System Commissioning plans
Nb3Sn QPS strategies How to protect.
Simulations of failure cases 1st STEAM Workshop June 2019
ECR on pole order of the HL-LHC IT circuit and resulting implications
R. Denz, TE-MPE-EP Acknowledgements: J. Steckert
F.Pasdeloup, H.Prin, L. Williams
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

Detailed global view on protection and detection of the circuits R. Denz Acknowledgements: A. Ballarino, S. Izquierdo Bermudez, G. Kirby, M. Mentink, F. Rodriguez Mateos, H. Prin, A. Siemko, J. Steckert, A. Verweij, D. Wollmann, S. Yammine 7th HL-LHC Collaboration Meeting, Madrid, November 16th 2017

Circuit Table v7.2-1

All voltage taps used for quench detection are redundant Instrumentation All voltage taps used for quench detection are redundant All corrector circuits requiring active quench detection systems are equipped at least with a midpoint voltage tap In specific cases the “midpoint” voltage tap must be located asymmetrically In case dedicated detection systems for the bus-bars are regarded as useful, the respective voltage taps must be provided HTS leads and MgB2 links will be equipped with their respective voltage taps Routing of the link instrumentation wires through the cold part is not required Voltage taps may be specified and added for diagnostic purposes only; the corresponding signals can be processed by the QPS supervision

Newly developed didt sensors will be installed for various purposes: Current sensors Dedicated current sensors for quench detection systems will be used for all the circuits requiring current depending detection settings Nb3Sn magnets, corrector circuits Required resolution is low  resistive part of HTS current lead could serve as sensor Newly developed didt sensors will be installed for various purposes: Improved symmetric quench detection, e.g. for Q4, Q5, Q6 Better compatibility of certain corrector magnet circuits with HL-LHC operational requirements e.g. higher acceleration, fast feed back IT orbit correctors in point 2 and 8, sextupole correctors …

Hardwired interlocks: The HL-LHC interlock architecture is derived from the standard LHC interlock specification Hardwired interlocks: Current loops linking the power converter(s), the powering interlock controller (PIC), the energy extraction system (if applicable) and the quench detection systems. Any rupture of the current loop will stop the power converter. The PIC initiates a beam dump request via the beam interlock controller. CLIQ and quench heater power supplies (DQHDS) are directly triggered by the quench detection systems (active high); these units will be equipped with redundant trigger inputs. In case of a self-triggering CLIQ unit all CLIQ units will fired HL-LHC will use redundant fast interlocks Beams will be dumped prior to CLIQ and DQHDS activation

Detection settings Element Threshold Evaluation time Remark MQXF, MBXF, MBRD, MBH ±100 mV 10 ms Higher thresholds at lower currents may be required e.g. ±200 mV for I < 2 kA Corrector magnets Longer evaluation times may be required in certain cases. High threshold at low current recommended e.g. ±2 V for I < 50 A HTS lead - resistive part 1 sec HTS lead – HTS part ±1 mV - ±5 mV 100 ms MgB2 cables 50 mV – 100 mV Detection settings are still preliminary (besides the ±100 mV, 10 ms of course …) and need to be confirmed.

Quench Detection Systems (QDS): Inner triplets Quench Detection Systems (QDS): Magnets, bus-bars, MgB2 links, HTS leads Dedicated QDS for the different elements; detection settings can be specified accordingly Protection systems: Quench heaters (inner & outer layer), CLIQ 24 + 48 DQHDS, 6 CLIQ units Protection strategy: Any detection trigger will activate all CLIQ and Quench Heater Discharge Power Supplies (DQHDS)

Inner triplet – instrumentation scheme Q1a & Q1b Q1a and Q1b each have unique individual currents, so that a finer subdivision of balanced sections is needed Two layers of quench detection, and two-fold QDS redundancy 1st layer: balanced individual poles (e.g. pole 1 vs pole 4)  2 x QDS channels 2nd layer: balanced groups of two poles (e.g. poles 1+4 vs 2+3)  2 x QDS channels Total: 12 x QDS channels for Q1

Inner triplet – instrumentation scheme Q2 & Q3 Same current for: Q2a and Q2b, and Q3a and Q3b  less QDS detectors are needed Groups of two poles are balanced against each other (e.g. poles 1 & 4 versus 2 & 3)  2 x QDS channels Magnets are balanced against each other (Magnet a vs b)  2 x QDS channels Total: 6 x QDS channels for Q2, and 6 x QDS channels for Q3

Inner triplet – bus-bar quench detection scheme Bus-bar protection underneath current leads A and E: 2 x 2 QDS channels monitoring bus-bars Bus-bar protection for T-sections between Q1a-Q2a, and Q2b-Q3a: 2 x 3 QDS channels monitoring bus-bars Bus-bar between Q2a and Q2b is monitored by the magnet QDSs

Inner triplet – instrumentation summary Qty Voltage taps QDS channels Magnets 6 6 x 2 x 7 or 6 x 2 x 5 12 (Q1) + 6 (Q2) + 6 (Q3) HTS leads 5 5 x 2 x 4 10 SC link 5 x 2 x 2 Total 164 or 120 54 Final voltage tap configuration still to be confirmed. Routing of voltage taps and required twisting to be confirmed.

Inner triplet – correctors Orbit correctors (MCBXF): QDS: magnets, bus-bars, MgB2 links, HTS leads Protection systems: energy extraction by PC crowbar; optional energy extraction systems Superferric order 2 (MQSXF): Superferric order 3, 4, 5, 6: QDS: MgB2 links, HTS leads Protection systems: energy extraction by PC crowbar

D1, D2 and D2 corrector D1 and D2 dipoles: D2 corrector QDS: magnets, bus-bars, MgB2 links, HTS leads Dedicated QDS for the different elements; detection settings can be specified accordingly Protection systems: quench heaters 4 (D1) x DQHDS, 8 (D2) x DQHDS D2 corrector Protection: energy extraction by PC crowbar; optional energy extraction system As the CCT magnet could experience symmetric quenches, each of the two apertures will be equipped with a non-central tap

Protection systems: quench heaters Q4, Q5 and Q6 correctors QDS: magnets, bus-bars, HTS leads  refurbished existing LHC systems adding additional features Dedicated QDS for the different elements; detection settings can be specified accordingly Enhanced quench heater circuit supervision Improved symmetric quench detection with the help of didt sensors Protection systems: quench heaters Q4, Q5 and Q6 correctors Protection by PC crowbar detection by PC as presently implemented in LHC for 60 A and 120 A corrector circuits

11 T dipoles QDS: Protection systems: Magnet and bus-bars inside 11 T assembly nQPS layer of RB circuits needs to be re-configured after installation of 11 T dipoles Protection systems: Quench heaters, energy extraction systems of main circuits 2 x 8 DQHDS

11 T – instrumentation scheme

11 T – instrumentation summary In total 16 magnet voltages, four bus-bar voltages, two total magnet voltages and  two circuit currents are treated by the redundant QDS systems Detection of aperture symmetric quenches will be assured by comparing MBHA with MBHB The choice of taps will always include bus-bars and splices around the concerned magnet pole so that all internal bus-bars are covered by QDS nQPS for RB.A67 and RB.A78 needs to be re-configured as 11 T dipole cannot be used as reference magnet See as well LHC-MBH-ES-0001 EDMS 1764166 (under approval)

Summary Definition of protection of the various HL-LHC superconducting circuits advancing well and almost concluded Still some open questions like optional energy extraction systems Detailed implementation of instrumentation schemes started Completed for 11 T dipoles Some details to be clarified for inner triplets Still to be done for D1, D2, correctors etc. Quench detection algorithms and settings established Based on present knowledge about the magnets and other superconducting elements Final validation after tests with prototypes