Upgrade Strategy for the Experimental Vacuum Systems

Slides:



Advertisements
Similar presentations
Simulation priorities for 2015 R. Bruce for task 5.2.
Advertisements

Management’s preliminary comments to the ERC Report.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
LHeC Experimental Beam Pipe
Machine Detector Interface for the HL (MDI) CERN, April 15, 2011 Austin Ball, Helmut Burkhardt, Marzio Nessi.
FP420 Vacuum Ray Veness. Contents o What is FP420? o How would it be installed in the LHC? o What would it look like? o What are the issues/interest for.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
27-March-10 LCWS10 - Beijing Global Design Effort 1 Barry Barish LCWS10 - Beijing 27-March-10 “Cost Containment” for the TDR.
CERN, Main challenges for the ATLAS upgrade project in the coming year.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
RSSO refresher meeting J. Pedersen M. Tavlet, T. Otto.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
ECRs and ES for the LHC Last presentation on the 26 th of August 2015 (LMC 232) S. Chemli for EN-MEF-DC LMC xxx.
Preparation of Review R. Assmann et al CWG, CWG R. Assmann.
Experimental Sectors Ray Veness / AT-VAC With many thanks to G.Foffano + W.Cameron TS/MME Patrick Lepeule / AT-VAC.
Preliminary View on the LHeC Experimental Vacuum Chambers Jonathan Bosch - University of Manchester And Ray Veness - TE/VSC J.Bosch and R.Veness LHeC -
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Consolidation and Upgrade plans for the LHC Vacuum System
Management’s preliminary comments to the ERC Report FINANCE COMMITTEE June 19, 2002.
CLIC Machine-Detector Interface Working Group (MDI) Emmanuel Tsesmelis CERN TS/LEA CLIC-ACE of 3 September 2008.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
OLAV3 Engineering Integration and installation of experimental beam pipes: the case of LHC 7/8/20111P.Lepeule for VSC group.
Low Emittance Generation and Preservation K. Yokoya, D. Schulte.
Introdcution to Workpackage/Activity Reflection D. Schulte.
Preamble Run 2 and Run 3 will see the continued exploitation of the forward physics potential of the LHC in the long straight sections (LSS) either side.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
8/12/2010Dominik Dannheim, Lucie Linssen1 Conceptual layout drawings of the CLIC vertex detector and First engineering studies of a pixel access/insertion.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
Update on Experimental Beampipe Progress Ray Veness For Beampipe project team in AT/VAC and TS/MME With special thanks to: S.Calatroni, W.Cameron, D.Duarte,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 The next steps – focusing points Define the scope, strategy and cost of the project implementation. Main input: The evolution of the physics findings.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
AT-VAC SPC Nicolaas KOS Beam Screens for Inner Triplet Magnets LHC Upgrade Phase 1 Nicolaas KOS  LHC Upgrade phase 1  Inner triplet BS Requirements.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
ENERGY DEPOSITION AND TAS DIAMETER
29 October 2015 B. Di Girolamo. B. Di Girolamo – Collider-Experiments Day – 5 th HiLumi Annual Meeting 2 Collider-Experiments Interactions There is a.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Mandate Priorities Other tasks Membership Forthcoming reports to CTC
ICE SECTION The coolest place to be! Elias Métral
Jaak Lippmaa HIP, Helsinki University
LBNF CAD models, Drawings and Component list
TC activities.
Some input to the discussion for the design requirements of the GridPixel Tracker and L1thack trigger. Here are some thoughts about possible detector layout.
Impact of running with LHCf and early Totem 90 m optics
Installation of an Instrument on a CERN machine
CERN R&D plans and Infrastructures
Machine-Experiment Interface
Workshop format and scope Expected write-up's Follow-up actions
LAAWG Status Report – 15th May 2007
LHC Experimental Vacuum Systems Status October ‘07
Long Shutdown for the LHC: Vacuum Beam Pipes
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
Progress with Experimental Vacuum Chambers
Accelerator and Experiment Interface Session: LS2, LS3
The HL-LHC project: info day for industry
CLIC Civil Engineering Update
Mauro Morandin & Antoine Daël
UPDATE ON DYNAMIC APERTURE SIMULATIONS
Wednesday Summary of Working Group I
Update on ATLAS insertable B-layer
LHC External Collimation Review
Qingjin XU Institute of High Energy Physics (IHEP),
East Hall under construction
Presentation transcript:

Upgrade Strategy for the Experimental Vacuum Systems Ray Veness / CERN-AT-VAC With thanks to R.Assmann, O.Bruning, R.Ostojic, E.Tsesmelis LHCC 18 XI 08 Beampipe Upgrade Strategy - R.Veness

Contents Introduction Organisation for the baseline vacuum system Current work programme for consolidation and upgrades Input required from experiments Proposed strategy for upgrades Conclusions and issues LHCC 18 XI 08 Beampipe Upgrade Strategy - R.Veness

Introduction Background Why do we need this talk? Baseline LHC experimental beampipe project started in 1993 Last system commissioned in Sept. ‘08 Why do we need this talk? Designs ‘frozen’ 2000-2003, but with plans for consolidation Some requests for work from the experiments were not possible due to manpower limitations Some technology was shown to be unreliable without further development, and downgraded for later installation Machine and experimental upgrade plans advancing quickly Need a definition of the central beampipe radius for ATLAS and CMS PIXELS Impact of phase- I triplet upgrade on ATLAS and CMS needs to be analysed Missing some mandates to continue Baseline project is now complete and in ‘operation-shutdown’ mode Financial basis of upgrades needs renewing Technical scope, priorities and responsibility need updating LHCC 18 XI 08 Beampipe Upgrade Strategy - R.Veness

Organisation for the Baseline Systems Structure ‘LHC Experimental Beampipes’ working group, active 1993-2004 reporting to LEMIC and then LHC Technical Committee reviewed from conceptual design to construction Design reviews and TDRs with experiments and machines closed the final designs Scope Layouts and designs of chambers, supports and interfaces inside 4 LHC caverns, plus TOTEM Roman Pots Chamber geometries, machine and experimental physics requirements (aperture, impedance, RF, vacuum, background), follow-up of R&D Resources All installed hardware funded by relevant experiment R&D, design, assembly, test, installation and management funded from a ‘work package’ given to AT-VAC in 2001 Staff assigned to project by AT-VAC and other groups, design office and additional industrial support paid from AT work package LHCC 18 XI 08 Beampipe Upgrade Strategy - R.Veness

Current Work Programme for Beam Vacuum Consolidation and Upgrade ATLAS: Replace stainless VA (&VT) steel chambers and bellows with aluminium for background and ALARA reasons LHCb: Replace defective UX85/3 beryllium chamber, optimise UX85/2 supports, replace stainless steel bellows with aluminium CMS: Re-evaluate forward vacuum chamber supports and gas injection system operation for magnetic fields Upgrades Machine insertion upgrade: New forward chambers in ATLAS and CMS, new TAS and/or TAS chambers, new VAX region (TAS-Q1) ATLAS: New (insertable) B-layer, tracker upgrade (beryllium) beampipe CMS Tracker upgrade (beryllium) beampipe, New materials and manufacturing methods for transparent chambers FP420-type forward physics moving beampipes Phase – II upgrade concepts LHCC 18 XI 08 Beampipe Upgrade Strategy - R.Veness

Apertures for Next Generation Beampipes History ATLAS requested a smaller beampipe diameter in Z ±3.5m for B-layer and PIXEL upgrades Presentation to ATLAS tracker upgrade workshop in 2006 based on aperture requirement at injection (which was the limit for the current beampipe radius) A number of open questions remained to be answered, (eg, future optics and collimation) with final value expected some time after machine start-up Information required from ATLAS and CMS Formal statement needed on range of β* in IR’s 1 and 5 required for physics TOTEM or other high β* optics required after phase – I triplet upgrade? Latest information on structural stability of experimental caverns Next steps Calculate baseline aperture of beampipe in cavern, taking into account new information on triplet and collimation Make detailed simulations based on beam loss, background and machine protection before agreeing final value Need a forum for advancing this in a structured way LHCC 18 XI 08 Beampipe Upgrade Strategy - R.Veness

Proposed Organisation for Upgrades Re-activate ‘LHC Experimental Beampipes’ (LEB) Group Mandate for consolidation and upgrade (phase I and II) of vacuum sectors from Q1 to Q1, plus new forward physics experiments Vacuum chambers, support systems and interfaces with experiments and machine Constraints from experiments and machine, geometry, technology, project management Membership 1 member (TC or nominated) per experiment, representation from concerned machine groups, plus safety Reporting to ? Urgent topics for discussion Definition of upgrade aperture in ATLAS and CMS Follow-up on consolidation projects, and scheduling LHCC 18 XI 08 Beampipe Upgrade Strategy - R.Veness

Conclusions and Issues Baseline vacuum systems The design and follow-up of the currently installed systems was via a VAC-led working group called LEB. This worked well! Current situation There are a large number of requests for consolidation and upgrade activities The financial basis, priorities and resourcing for these activities are not clearly defined Proposed actions The LEB working group should be re-activated with an updated mandate and membership A budget for consolidation and upgrade of experimental vacuum should be agreed between the research and accelerator sectors, along with an associated resource plan LHCC 18 XI 08 Beampipe Upgrade Strategy - R.Veness