Powering from short circuit tests up to nominal

Slides:



Advertisements
Similar presentations
LHC Machine Protection
Advertisements

Frédérick BORDRY – LHCMAC 22- 6th December 2007 Review of the experience of LHC powering: short-circuit tests and sector 7-8 and start of powering sector.
1 Powering Tests and Safety Electrical Safety Hugues Thiesen Power Converter Group.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
New HV test specification for the LHC N. Catalan for the EI section.
CRYOGENICS AND POWERING
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
Powering Group of Circuit Doubts and proposals of the procedure reviewing team (Gianluigi, Rob, Sandrine, Matteo, Boris) Ref document: LHC-MPP-HCP-071.
LARP Collaboration April 26 th 2006 The Commissioning of the Technical Systems of LHC 1.The final validation that all the collider components/systems.
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Powering of the Superconducting Circuits: Procedures and Strategies for Circuit Validation Antonio Vergara on behalf of the Hardware Commissioning Coordination.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
CERN Rüdiger Schmidt FCC week 2015 Long Magnet Stringpage 1 Incident September 19 th Architecture of powering and protection systems for high field.
1 Copper Stabilizer Continuity Measurement Project Copper Stabilizer Continuity Measurement Status & Plans – May 2011 MPE-TM – 12 May 2011 M. Koratzinos,
R.Schmidt, HC 28/5/ Access to underground areas during powering Risk: accidental massive helium release (as on 19 September) when superconducting.
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
AT-MEL-PM, R. Denz, CERN, CH-1211 Geneva 23 1 QPS system and its risks  Principal risks  General remarks  Quench heater circuits  Quench detection.
HC Review F. Rodriguez-Mateos Powering tests The outcome of the work conducted within HCWG and many discussions among colleagues.
Hardware Commissioning Tools Robin. AB-CO TC 8th February 2007Hardware Commissioning Tools - RJL2 Summary Hardware Commissioning View Slides from Antonio.
M. POJER, ON BEHALF OF THE USUAL BUNCH OF SUSPECTS… S UPERCONDUCTING CIRCUITS RE - COMMISSIONING AFTER THE 2011 C HRISTMAS BREAK.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
Review of Sector th of February Tunnel Access During Powering Tests Hugues Thiesen, AB-PO.
AT-MEL Group Meeting, CERN, 1211 Geneva 23 1 ElQA activities during hardware commissioning N. Catalan Lasheras.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
MPP Workshop Status of Powering Interlocks I. Romera on behalf of MPE-MS MPP Workshop, 12 June 2015, I. Romera (TE-MPE)1.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
An invitation to an open discussion We are team reviewing its performance globally We want to help each other to reach the objectives We know the other.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Training LHC Powering Robin Lauckner Software Tools for Commissioning Robin Lauckner 28 th March, 2007.
The prototype test String 2 May 13, 20082Roberto Saban – Academic Training Lecture 1 – Why LHC Hardware Commissioning?
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
SC Undulators protection and commissioning W. Venturini Delsolaro Acknowledgements: R. Denz, R. Maccaferri.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
MPP Main Ring Magnet Performance Panel Meeting Wednesday 16 January 2008 Agenda: 1)General information & pending actions 2)ElQA Issues by Stephan RUSSENSCHUCK.
LHC Post Mortem Workshop - 1, CERN, January 2007 (slide 1/52) AB-CO Measurement & Analysis Present status of the individual.
HL-LHC IT STRING and Series test of SC link
R. Denz, A. Gomez Alonso, AT-MEL-PM
Powering LHC magnets version 30/3/2007.
Minimum Hardware Commissioning – Disclaimer
The HL-LHC Circuits: Global View and Open Questions
Superconducting Circuits, a generic view
12 October 2009 RRB Plenary R.-D. Heuer
The LHC - Status Is COLD Is almost fully commissioned
Powering the LHC Magnets
Circuits description and requirements - Closed Session-
LS1 TE/MPE/EE CABLE ACTIVITIES
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
3 issues identified in review
Rüdiger Schmidt and Karl Hubert Mess
TEST PLANS for HL LHC IT STRING
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Machine Protection Xu Hongliang.
+ many slides from various colleagues (KH, Rudiger, Paul, …)
Brief report of the hardware commissioning activities
Commissioning of the LHC superconducting magnets systems: Why an LHC Hardware Commissioning? Specificity and complexity of this machine Roberto Saban.
Hardware Commissioning
Review of hardware commissioning
Presentation transcript:

Powering from short circuit tests up to nominal Antonio Vergara for the HCC Team 28th March, 2007

General Overview What we want to do? When are we going to do it? Power ALL the superconducting circuits of the LHC up to their nominal operation current (7 TeV) without beam. When are we going to do it? FROM MONDAY. See Blanca’s slides Where are we going to do it? In the tunnel (Field Control Room) and on the surface (CCC) Who is going to do it? The Commissioning Crew. See Roberto’s slides How are we going to do it? Well, safely and fast. See Robin’s, Paul’s and Antonio’s slides

General Overview So far we have learnt about Superconducting electrical circuits Power converters Superconducting magnets, busbars and current leads Powering interlock system Quench protection system Cooling and ventilation, AC distribution, cabling Cryogenics The Powering Tests will make these systems work together for the first time. But before that…

The Way to the Powering Tests Individual System Tests (IST) The Short-Circuit Tests

The Short-Circuit Tests

The Way to the Powering Tests Individual System Tests (IST) The Short-Circuit Tests START OF COOL-DOWN CRYOGENIC CONDITIONS 3. Powering Procedure Tests 4. PIC1 - Correctors 5. Electrical Quality Assurance @ Cold 6. Quench Heater Discharge 7. PIC1 – Main Magnets 8. Connection of the converters to the CL

During Cool-Down…

THE POWERING TESTS And at last… 3. PIC2 CONVERTERS CONNECTED TO THE MAGNETS 3. PIC2 4. Powering to Nominal of every circuit (P2N) 5. 24-hour run with all the circuits at nominal

Powering Interlock Tests – PIC1 & PIC2 - FAQ What do PIC1 and PIC2 validate? The correct functioning of the powering interlock system and associated systems and The interfaces between the Powering Interlock Controllers and the QPS, Energy Extraction and Power Converters Which is the difference between PIC1 and PIC2? For PIC1 the converters are NOT CONNECTED to the superconducting magnets while for PIC2 the converters are CONNECTED to the superconducting magnets. PIC2 is therefore the first test with current in the magnets Why is PIC1 for the correctors done without the Stable Cryogenics Conditions? PIC1 for the correctors has no interference in the superconducting part of the circuit, on the other hand PIC1 for the main circuits implies discharge of the quench heaters which can only be done under stable cryogenic conditions. Do we need to complete PIC1 in the whole powering subsector for starting PIC2? YES Do we need to complete PIC2 in the whole powering subsector for starting P2N? NO, but preferable

Types of electrical circuits with sc magnets 13 kA Main: Main dipoles and main quadrupoles (24 circuits) IT: Inner triplet quadrupoles (8 circuits) IPQD: Individual powered insertion main magnets (94 circuits) Extraction of the energy stored in the magnets is performed by the QPS system 600 A EE: most 600 A corrector magnets powered in series (202 circuits) Extraction of the energy stored in the magnets is performed with an energy extraction unit back to back to the power converter rack 600 A no EE crowbar: most individual 600 A trim quadrupoles (136 circuits) Extraction of the energy stored in the magnets is performed with the power converter 600 A no EE: inner triplet correctors (56 circuits) No energy extraction unit required 80-120A: 80 A and 120 A (300 circuits) No energy extraction unit required, connected to the Powering Interlock Controller 60A: 60 A (752 circuits) No energy extraction unit required, not connected to the Powering Interlock Controller R.Schmidt

The Main Dipole Circuit Powering PM Analysis Results RB Circuit PM data 12 kA EE Quench 8.5 kA Loss PP 6 kA Quench 2 kA SPA FPA EE PIC2 Injection 760A 350A

Sequence of Powering Tests Injection Intermediate 1 Intermediate 2 Intermediate 3 Nominal

Circuit Inventory Sector 7-8 ARC 7-8 60A XL8 ML8 120A RB RQ Q6-Q10 600A Q4Q5D2 5 94 22 47 1 2 3 12 14 DESIGN 200 22 47 1 2 5 94 3 12 186 TRIPLET 22 47 1 2 5 94 3 12 MB1055 186 Max 2kA MB1055 20 23 1 2 5 94 3 12 160 160 Circuits fully Commissioned Status after the Powering Tests 3 Main Circuits (RB, RQF, RQD) to be re-commissioned 1 Inner Triplet and 26 arc correctors never powered

The Two Fronts FRONT 1 FRONT 2 E.Barbero / Mr Circuit

Parallelism or what can be done at the same time? The 3 types of parallelisms: Parallelisms between sectors Parallelisms between fronts Parallelisms between circuits – Battery General Constraints: One Front can commission only one circuit or one battery at a time Tests carried out by one Front should be transparent to the other ones

Constraints on Parallel Commissioning Two sectors cannot test simultaneously Two or more 13kA circuits Two fronts cannot test simultaneously Circuits in the same powering subsector when one main circuit is involved.

The Two Fronts – Arc 7-8 Afternoon Shift Morning Shift Morning & Afternoon

Constraints on Parallel Commissioning Two sectors cannot test simultaneously Two or more 13kA circuits Two fronts cannot test simultaneously Circuits in the same powering subsector when one essential circuit is involved. A battery cannot Include circuits above 600A Imply more than one DFB Imply more than two DFB chimneys Include circuits sharing the same QPS controller Include circuits from different circuit type Include circuits from different powering subsectors

Schedule Preparation Preparation PIC2 P2N P2N PIC2 FRONT 1 2 Shifts ARC 7-8 60A ML8 CRYO-OK 4.5K Today WEEK 13 WEEK 15 WEEK 14 WEEK 16 Preparation CRYO-OK 1.9K Preparation PIC2 P2N P2N PIC2 FRONT 1 2 Shifts FRONT 2 2 Shifts

Sector 7-8 – Total TOTAL TIME SECTOR 7-8: 10 WEEKS (from CRYO_START)

Glossary Powering Tests Short-Circuit Tests Field Control Room Individual System Tests (IST) Powering Procedure Tests PIC1 PIC2 Circuit type Sequence Fronts Parallelism Battery of circuits Sector Powering Subsector QPS Controller DFB Chimeny Morning and afternoon shifts Post-Mortem (PM) Analysis Injection Current Intermediate Current I_MIN_OP Current Nominal current