LHC Risk Review: Kicker Magnet Reliability

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Etienne CARLIER AB/BT/EC
12/03/2013MPP Workshop Annecy Update on Beam Failure Scenarios Jan Uythoven Thanks to: T.Baer, R.Schmidt, J.Wenninger, D.Wollmann, M.Zerlauth, other MPP.
1 MKBH Erratic Jan Uythoven On behalf of the ABT team (Viliam, Nicolas M., Etienne, Laurent, Francesco etc…..) MPP meeting 8/5/2015.
Beam Dumping System – Failure Scenarios Brennan Goddard, CERN AB/BT How the dump system can fail Catalogue of primary failures Failure classes and protection.
B.Goddard 08/11/04 HHH 2004 Workshop, CERN Beam Dump Brennan GODDARD CERN AB/BT The existing LHC beam dump is described, together with the relevant design.
Technical review on UPS power distribution of the LHC Beam Dumping System (LBDS) Anastasia PATSOULI TE-ABT-EC Proposals for LBDS Powering Improvement 1.
LBDS Kicker Electronic and Slow Control Etienne CARLIER AB/BT/EC.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
LBDS Audit Follow-up Jan Uythoven Thanks to: Etienne Carlier and Brennan Goddard 1.
MKI Erratics: Hardware and Electronics Related Aspects M.J. Barnes Acknowledgements: A.Antoine, R.A. Barlow, P. Burkel, E. Carlier, N. Magnin, V. Mertens.
Etienne CARLIER, LBDS Audit, 28/01/2008 LBDS Environmental Aspects EMC, radiation, UPS… Etienne CARLIER AB/BT/EC.
What will we do for Beam Preparation: Injection and Beam Dump Jan Uythoven Thanks to M.Barnes, E.Carlier, L.Ducimetière, B.Goddard, R.Jones, Y.Kadi, V.Kain,
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
The LBDS trigger and re-trigger schemes Technical Review on UPS power distribution of the LHC Beam Dumping System (LBDS) A. Antoine.
1 Reliability and Availability of the Large Hadron Collider (LHC) MachineProtection System Jan Uythoven CERN, Geneva, Switzerland Thanks to R. Schmidt,
1 Will We Ever Get The Green Light For Beam Operation? J. Uythoven & R. Filippini For the Reliability Working Group Sub Working Group of the MPWG.
1 CC & MP - CC10 - CERN Crab LHC J. Wenninger CERN Beams Department for the LHC Machine Protection Panel.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
Scrubbing Run: TDI, MKI and MKE interlocks Chiara Bracco, Jan Uythoven ABT/BTP Acknowledgments: T. Baer, M. Barnes, E. Carlier.
Overview WP14 Developments Hardware  Interferometry on the spare TDIs, planned to be installed Christmas stop 2015/2016. Final acceptance tests ongoing.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
HL-LHC WP14 2 nd meeting: Intercepting devices and failure cases to be studied Anton Lechner, Jan Uythoven.
Session 8: What we will do for beam preparation in 2009 G. Arduini, R. Giachino 1Session 8 – Summary - GA24/02/2009.
Data providers Volume & Type of Analysis Kickers
The TV Beam Observation system - BTV
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Dependability Requirements of the LBDS and their Design Implications
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Surviving an Asynchronous Beam Dump?
The LHC Beam Dumping System
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Introduction: FCC beam dumping system
SPS extraction, transfer lines, injection
LHC Beam Dumping System Reliability Run Summary
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
Jan Uythoven For discussion
Saturday 21st April 00:33 Interlock during ramp on BLM HV
FCC hh dump kicker - switch topologies and impact on beam
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Overview on LHC Machine Failure Scenarios
Safe Injection into the LHC V.Kain AB/CO
FCC-hh injection group 7
Safe Injection into the LHC V.Kain AB/CO
Initial Experience with the Machine Protection System for LHC
Machine Protection Xu Hongliang.
LHC Injection and Dump Protection
Beam Dumping System and Abort Gap
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 35 – Technical Stop and Restart
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Protection against accidental beam loss at the LHC
Machine Protection System Commissioning plans
Chamonix Workshop XIV CERN - 17th-21st January 2005
Will We Ever Get The Green Light For Beam Operation?
The LHC Beam Interlock System
Interlocking strategy
Jan Uythoven For the LBDS Team
Acknowledgements: Alain Antoine, Nicolas Magnin & Volker Mertens
What systems request a beam dump? And when do we need them?
Close-out.
Presentation transcript:

LHC Risk Review: Kicker Magnet Reliability Jan Uythoven Thanks to Brennan Goddard, Etienne Carlier, Wolfgang Höfle, Verena Kain and Volker Mertens

Scope Different kicker systems Beam Dumping System Extraction Kickers Dilution Kickers Injection Kickers Kickers for Tune and Aperture measurement AC-Dipole Feedback Kickers (Transverse Damper) Discussing Expected failure behavior and likelihood From theory and from experience Measures taken Conclusions Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Studies / Reviews of Kickers and especially the Beam Dumping System LHC review on Machine Protection and Interlocks External, April 2005 PhD thesis on Beam Dumping System Dependability CERN-THESIS-2006-054 Beam Dumping System Review Internal, January 2008 Mainly on controls aspects – not HV aspects Planned review on Beam Dumping System Trigger Synchronisation Unit (TSU) External company: wk 17 – wk 33 Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

LHC Beam Dumping System MKD: 2 x 15 Systems MKBH: 2 x 4 (2) MKBV: 2 x 6 (2) TCDQ Magnet operates in air with coated ceramic chambers Magnet operates under vacuum TCDS Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Beam Dumping System Extraction kickers MKD and dilution kickers MKB Critical because: Important damage could occur as these system have the potential to deflect the full intensity beam up to ‘any angle’ MKD failure: can damage the arc / LHC Most critical for the LHC MKB failure: damage the extraction channel and beam dump block Talk B.Goddard Friday on consequence of dilution failure Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Beam Dumping System System safety is based on: Built in redundancy Continuous surveillance Post Operational Checks (IPOC/XPOC) Redundancy 14 out of 15 MKD, 1 out of 2 MKD generator branches Surveillance Energy tracking, Retriggering 1 out of 4 MKBH, 1 out of 6 MKBV Energy tracking Energy tracking, Fast current change monitoring (MSD) 1 out of 2 trigger generation and distribution Synchronization tracking Reference energy taken from 4 Main Dipole circuits TX/RX error detection Voting of inputs Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

MKD System NOT firing One kicker not firing is covered by System redundancy: can dump correctly with 14/15 MKD systems It is very unlikely that one, or even more unlikely more than one, kicker will not fire because of: Choice of switch type: The GTO Thyristor switch stack consists of 10 discs Adjusted manufacturer failure rate for 1 disc  2.410-6 failures per hour for 1 switch Redundancy within each kicker generator Each generator has two solid state switches in parallel, which can each take the full current Redundancy in triggering system Complete system not firing due to no trigger from Beam Interlock System not treated here Fault external to beam dumping system But studied elsewhere: SIL3 Experience from Reliability Run: No missings occured! Details later Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Functional Architecture of 1 MKD Generator Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

MKD system Kicking with Wrong Strength Probably one of the worst scenario’s Covered by comprehensive Energy Tracking System (BETS) Energy is calculated from the main dipole currents in the four ‘adjacent’ octants Large redundancy in generation of energy reference and in verification of kicker strength while being ready for the next dump Kicker settings and Energy Interlock values both hardcoded in the Front Ends, using separate tables No remote access to these tables Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Erratic firing of MKD kicker Re-triggering system which detects any ‘spontaneous’ firing of an MKD or MKB kicker magnet Within 700 ns all switches will be fired asynchronously During this delay and the 3 µs rise time of the MKD kickers, the bunches swept over the aperture will be intercepted by the TCDQ and TCDS absorbers. Again redundant signal paths Experience from Reliability Run: No erratics occurred! Details later Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Power Cut In this case the beam will clearly need to be dumped because most other equipment will stop working Beam dumping system kickers are on 2 parallel, redundant Uninterruptable Power Supplies (UPS) UPS required: Trigger Synchronisation Unit needs power from UPS to start the trigger of the beam dump All other power is stored in capacitors, ready to be ‘released’ at the moment of trigger Already tested in 2008 – generates dump – more extensive diagnostics on sychronisation for further tests planned in 2009 Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

All these systems are obligatory ! Safety Study Ph.D. thesis Roberto Filippini (CERN-THESIS-2006-054) FMECA analysis More than 2100 failure modes at component levels Components failure rates from standard literature (Military Handbook) Arranged into 21 System Failure modes Operational Scenarios with State Transition Diagram for each Mission = 1 LHC fill State Transition Diagram for Sequence of Missions and checks Likelihood for any unacceptable failure All these systems are obligatory ! Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Source of failures (from study) Apportionment of unsafety (=unacceptable failure) to the different components: MKD is the most complicated system and contributes most to the unsafety. The MKB dilution failures contribute 6 % to the unacceptable failures (presentation B.Goddard Friday) Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Operational Experience Reliability Run of the Beam Dumping System Operation only below 5.5 TeV, due to MKB break down Operation ‘with beam’ at injection energy Beam 2 System pulses = 19 magnets Beam 1 Beam 2 # Pulses 23’534 15’469 Time considered 10.5 months 9.1 months Continuous running (p <13 h) 2.7 months 1.7 months Beam 2 Data from 8/11/07 to 19/09/08 Jan Uythoven, AB /BT Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009 14

Reliability Run: Internal and External Post Operational Checks (IPOC / XPOC) MKD pulse 741’057 Magnet Pulses Analysed with IPOC and XPOC Systems > 10 years of operation Some hardware problems discovered  No critical failures on the MKD system which would have resulted in a non-acceptable beam dump even if redundancy would not be there No ‘asynchronous’ beam dumps were recorded (erratics). No missings. However, unexpected MKB breakdown   Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

MKD Issues Discovered Four switch failures due to short circuit on one of the GTO discs Within limits of reliability calculation assumptions Would not have given an unacceptable beam dump but internal dump request resulting in synchronous dump Problem with voltage distribution of GTO stacks: internal dump request All checked and redistributed for 2009 Only affected availability, not safety Re-soldering of trigger contacts on GTO stack All failures were detected by diagnostics, IPOC/XPOC ! Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

MKB failures Unexpected common mode failure on the MKB system. Flashovers in 3 out of 4 magnets simultaneously after operation under bad vacuum: stopped operation above 5 TeV. Measures taken: Additional vacuum interlock HV insulators, identified as weak point, being changed for 2009 Reduced conductance between adjacent MKB tanks by smaller aperture interconnects 50 s Moment of break down I [kA] MKB generator design similar to MKD, but with less redundancy within generator Measured MKB wave form Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Injection System Kickers MKI Travelling Wave Structure, with PFNs and ‘classical’ thyratron switches Per system experienced / expect about 1 missing kick per year Expect / experienced a few erratics per year Limited charging time of 2 – 3 ms before triggering System switched off after injection Operation is stopped after any missing or erratic No redundancy in number of kickers Machine aperture protected by two sided injection absorber TDI Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Injection Absorber TDI LEFT OF IP2 (H plane) Kicker MKI TCDD TCDI Septum MSI TDI MKI +90˚ TDI: ~ 4m long, ~ 10 m upstream of D1, additional mask in front of D1 (TCDD) Protects machine against MKI failures Required setting: 6.8 s (Assuming 7.5  machine aperture) Vert. separation bump Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Experience 2008 Some MKI magnet breakdowns occurred (nominally: 1/operational year) One magnet had shown a breakdown, probably by over-voltage during lab conditioning due to a calibration error Indications of MKI flashovers triggered by beam loss during aperture studies Results in larger kick (short circuit) or smaller kick (emptied PFN): system kick strength can vary between 75 % and 125 % of nominal for a part of the pulse: beam onto TDI / TCDD For small errors beam can graze the TDI: additional collimators TCLI and normal collimators in point 3 and 7. Measures SoftStart of the injection kickers if not pulsed for more than 1 hour. Automatic ramp up to nominal operational voltage before beam Installation of additional Beam Loss Monitors at the MKI to monitor beam losses: improve understanding and later possibly interlock For 2009: injection quality check which includes an automatic analysis all MKI pulses and compare to references (similar as for beam dumping system) Main protection is the TDI / TCDD Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Transverse Damper Also used for abort gap cleaning BE/RF Also used for abort gap cleaning Worst possible failure scenario: Full strength, at injection energy at wrong phase resulting in coherent excitation Results in 1  growth after 4 turns With collimators set-up correctly will loose the beam on the collimators Beam Loss Monitors at collimators should see this as soon as losses are significant and trigger beam dump request Reaction time of beam dump < 3 turns: beam should be dumped before any losses which can damage equipment If collimators not set-up correctly: BLMs are positioned to have a machine wide coverage and will dump before damage See also W. Höfle, review on Machine Protection and Interlocks, April 2005 Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

MKQA kicker and AC-Dipole Four Systems: 2 planes x 2 beams Three generators working on each magnet Tune kicker MKQ: Kick strength limited by system power converter: 0.41  at 7 TeV 1.6  at 450 GeV Should not imply any risk Aperture kicker MKA: also kick strength limited by system power converter: 1.6  at 7 TeV 6.1  at 450 GeV Operation potentially dangerous Can only be operated with ‘safe beam’ – MKA has a maskable interlock on the BIC which is always active Physical key required to switch between MKQ –MKA – AC-dipole Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

AC-dipole operating on tune: beam loss in about 45 turns: ok BE/CO Operation on tune, injection energy, nominal strength (normally gives 7  for  = 0.025), ramp up of kick strength over 200 ms = 2000 turns If excitation too important: beams lost on collimators and detected by Beam Loss Monitors If BLMS trigger beam dump, beam dump within < 3 turns Only to be used with safe beam. See also LTC meeting 6 June 2007 Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009

Conclusions By their nature kickers are a good candidate for possibly causing important damage to the LHC Great care has been taken to avoid this Redundancy and surveillance of the beam dumping system Absorbers on both beam dumping and injection system Limitation of power on tune and aperture kicker MKQA AC dipole and Transverse damper (not really kickers) Also limited power Slow enough as to trigger beam dump via Beam Loss Monitors Requires thorough commissioning of the fully connected system for Machine Protection Systematic and rigorous tests with formal approval before beam current or beam energy can significantly be increased Awareness is present: keep time for it on the schedule ! Jan Uythoven, TE/ABT LHC Risk Review, 5 March 2009