Alignment of the 12 GeV CEBAF Accelerator

Slides:



Advertisements
Similar presentations
Hall A Collaboration Meeting S. Nanda, June 23, 2005 Hall A Compton Polarimeter For Hall A Collaboration Meeting June 23 rd 2005 Sirish Nanda Thomas Jefferson.
Advertisements

Overview of the GlueX Tagger and Photon Beamline..
12GeV Project CD-4 Leigh Harwood Associate Project Manager Accelerator Systems.
Chris Tennant Jefferson Laboratory March 15, 2013 “Workshop to Explore Physics Opportunities with Intense, Polarized Electron Beams up to 300 MeV”
1 Institute of High Energy Physics 13/09/2010 Comparison and Study in Measurement Accuracy of Height Difference between Laser Tracker and Level Men LingLing.
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
Pre-alignment solutions applied to girders 1/19 Sylvain GRIFFET, 06/07/2010.
Jefferson Lab Presentation to Teacher Education Program November 8, 2006 Subatomic Particles: What do we study at Jefferson Lab? Dr. Allison Lung 12 GeV.
HPS Test Run Setup Takashi Maruyama SLAC Heavy Photon Search Collaboration Meeting Thomas Jefferson National Accelerator Facility, May 26-27,
Thomas Jefferson National Accelerator Facility Page 1 23 rd Annual HUGS Program June 2-20, 2008 CEBAF Overview HUGS08 June 3 CEBAF Overview HUGS08 June.
Thomas Jefferson National Accelerator Facility Page 1 IPR October 18-20, 2011 John J. LeRose Independent Project Review of 12 GeV Upgrade Jefferson Lab.
F Antiproton Source Apertures Steve Werkema DOE Tevatron Operations Review March 22, 2006.
12 GeV Upgrade Project Status Allison Lung Hall C Users Meeting Jefferson Lab January 18, 2008.
J EFFERSON L AB – A N I NTRODUCTION Hugh Montgomery; May 14, 2012.
BEPCII Prealignment Installation Survey and Alignment Accelerator Center of IHEP Xiaolong Wang
Contractor Assurance System Peer Review April Page 1 NSTAR 2011 May 16, 2011 Jefferson Lab Hugh Montgomery.
CASA Collider Design Review Retreat HERA The Only Lepton-Hadron Collider Ever Been Built Worldwide Yuhong Zhang February 24, 2010.
Welcome to Jefferson Lab R. D. McKeown Jefferson Lab Hypernuclear Workshop May 27, 2014.
Overview: Primary Sensitivities Nov S. Childress Page 1 NuMI Overview: NuMI Primary Beamline Sensitivities NuMI requirements are for a very large.
BIA’s Director Review, September Accelerator Improvements FY11-16 Fulvia Pilat.
Overview of the GlueX Tagger and Photon Beamline..
Thomas Jefferson National Accelerator Facility Page 1 SPL Cryogenic and vacuum sectorisations 9-10 November, 2009 Joe Preble Workshop on cryogenic and.
Y. R. Roblin Hall A beamline and accelerator status.
Thomas Jefferson National Accelerator Facility SensL 6-Oct CHL-2 12 GeV CEBAF Upgrade magnets and power supplies Two 1.1GV linacs Enhanced capabilities.
Hall A Installation Review John J. LeRose 2/25/2009.
Results From the Radphi LGD Dan Krop 12/11/03. The Radphi Experiment Radphi Experiment Took Data in Jlab Hall B From May to July Hours Of Beam.
MeRHIC Internal Cost Review October, Dmitry Kayran for injector group MeRHIC Internal Cost Review October 7-8, 2009 MeRHIC: Injection System Gun.
Beam collimation in the transfer line from 8 GeV linac to the Main Injector A. Drozhdin The beam transfer line from 8 GeV Linac to the Main Injector is.
Jefferson Lab Cryomodule Cost and Optimization. Based Jlab energy upgrade Cryomodule design and produced to increase the energy gain of CEBAF to 12 GeV.
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
Communication Tools Used For Commissioning the 12 GeV CEBAF Accelerator Brian Freeman WAO (Mainz, Germany) October 2014.
Review of Alignment Tolerances for LCLS-II SC Linac Arun Saini, N. Solyak Fermilab 27 th April 2016, LCLS-II Accelerator Physics Meeting.
Cost Optimization Models for SRF Linacs
12 GeV Project Status Glenn R. Young 12 GeV Project Status
Arun Saini, N. Solyak Fermi National Accelerator Laboratory
Preliminary Review of LERF as Cryomodule Testing Facility for LCLS-II
Correlated Misalignments Studies for LCLS-II SC Linac
Process Simulation for the LCLS-II Cryogenic Systems
Test of Hybrid Target at KEKB LINAC
Workshop on Tau-Charm at High Luminosity
Online Helium Inventory Monitoring of JLab Cryogenic Systems
ILC Z-pole Calibration Runs Main Linac performance
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
CLAS12 Torus Magnetic Field Mapping
Jefferson Lab Reliability Task Force and Initiatives
Jefferson Lab, Newport News, U.S.A.
Beam-Based Feedback in LCLS-II
Status of ATF/ATF2 and machine schedule in this fall
The SPEAR3 Upgrade Project at SLAC
The SPEAR3 Upgrade Project at SLAC
26AUG16.
The Storage Ring Control Network of NSLS-II
Introduction to Jefferson Lab
Operations Department
A brief Introduction of eRHIC
Preparation of the CLAS12 First Experiment Status and Time-Line
Other issues and concepts under study Conclusions References
Bubble Chamber – Beam Requirements
Extract from today’s talk given to DCB
Operations Department
View from Lab Management HPS Collaboration Meeting
Advanced Research Electron Accelerator Laboratory
RLA WITH NON-SCALING FFAG ARCS
Linac/BC1 Commissioning P
Jefferson Lab Users Group Meeting Start of the 12 GeV Era
SOLID Collaboration Meeting
Field Emission and Mitigation in the CEBAF Linacs R Legg, R Geng Jlab SRF Ops Dept. TTC,
Comparison between 4K and 2K operation performance of CEBAF injector cryomodules Grigory Eremeev Monday, August 19, 2019.
Andrew Hutton Concept suggested independently by Haipeng Wang
DYNAMIC APERTURE OF JLEIC ELECTRON COLLIDER
Presentation transcript:

Alignment of the 12 GeV CEBAF Accelerator Christopher Curtis Thomas Jefferson National Accelerator Facility, Newport News , Virginia, USA

Jefferson Lab Site c.2006

Jefferson Lab Site 2014

Enhanced capabilities CEBAF 12 GeV Upgrade New Hall Add arc Enhanced capabilities in existing Halls Add 5 cryomodules 20 existing cryomodules 20 existing cryomodules Upgrade arc magnets and supplies CHL upgrade E.Arc N. Linac S. Linac W.Arc

CEBAF 12 GeV Upgrade - Linacs

CEBAF 12 GeV Upgrade - Arcs Steel Added Arc 10

Hall D Complex – July 2011 Tagger Area Beam Line Hall D N. Linac Cryo Plant

Hall D Tagger & Service Building – May 2011 Tagger Area Service Bldg Electron Beam Dump Photon Beam Pipe to Hall D

Survey Network for Construction Penetrations Penetrations

Preliminary Accelerator Survey Network Network Survey Results - 2008 Laser Tracker – Free Stationed

“Skeleton” Survey Network 2009 Theodolites – Force Centered

Current Survey Network Network Survey Results - 2012

Dipole Alignment in East Arc

Instrument Station Variations Differences between individual instrument stations and final solution (4 stations) for dipole stack #4 (9 magnets) Average Differences (9 mags) DZ DX DY Center Stations 0.04 mm 0.05 mm 0.01 mm Upstream Stations 0.02 mm 0.23 mm 0.03 mm Downstream Stations 0.11 mm 0.15 mm 0.06 mm Maximum Differences 0.08 mm 0.10 mm 0.09 mm 0.37 mm 0.19 mm 0.20 mm 0.13 mm

Linac Distances Mar-13 North Linac Avg Dist. Diff 2012 HNL0030-420 361.57716 +2.1 ppm HNL0030-455 390.39103 +3.2 ppm HNL0060-420 340.35929 +2.6 ppm HNL0060-455 369.17304 +3.6 ppm Avg. Temp 21.0 NL Avg: +2.9 ppm South Linac HSL0010-420 376.56254 HSL0010-445 395.75880 +4.0 ppm HSL0040-420 354.99806 +5.6 ppm HSL0040-445 374.19450 +6.9 ppm 20.7 SL Avg: +4.9 ppm NOTE: Average temp of 2012 distance measurements: 29.0 (5ppm on 350m is 1.75mm)

East Arc Control Overall scale factor -26ppm

Observed Network Changes Linacs Expand Arcs Contract

Modified Alignment Procedure GOAL: Smooth alignment using 2012 network Magnets were adjusted from a center station, and re-shot from upstream and downstream stations The threshold for adjusting magnets into position was reduced to less than 0.1mm All visible control was measured and used in the survey Instrument stations were located to ensure an overlap from one section to the next

March 2014 Commissioning Initially single pass operations Multi pass operations showed 2 cm short per pass for each of the first 3 passes Path length for 1 pass = 1312 m giving 15 ppm Path length in Arcs = 506 m giving 40 ppm

April 2014 Measurements Measurement of all survey control points in east arc Measurement of quads and dipoles at mid point and end of the east arc Measurement of long distances in each linac

East Arc Control Overall scale factor -8ppm

East Arc Control Overall scale factor -26ppm

April 2014 Results Comparison to June 2012 Network survey Mar-13 7par scale factor -25.7 ppm -7.6 ppm "Traverse" 2012 243.70899 m Traverse length 243.70020 m 243.70654 m Traverse length diff. -8.79 mm -2.45 mm Avg. Sampled Temperature NA 29.8

Linac Distances Mar-13 North Linac Avg Dist. Diff 2012 HNL0030-420 361.57716 +2.1 ppm HNL0030-455 390.39103 +3.2 ppm HNL0060-420 340.35929 +2.6 ppm HNL0060-455 369.17304 +3.6 ppm Avg. Temp 21.0 NL Avg: +2.9 ppm South Linac HSL0010-420 376.56254 HSL0010-445 395.75880 +4.0 ppm HSL0040-420 354.99806 +5.6 ppm HSL0040-445 374.19450 +6.9 ppm 20.7 SL Avg: +4.9 ppm Apr-14 Avg Dist. Diff 2012 361.57648 +0.2 ppm 390.39026 +1.3 ppm 340.35846 369.17222 +1.4 ppm 26.8 NL Avg: +0.8 ppm 376.56169 +0.9 ppm 395.75802 +2.0 ppm 354.99650 +1.2 ppm 374.19290 +2.6 ppm 25.5 SL Avg: +1.7 ppm NOTE: Average temp of 2012 distance measurements: 29.0 (5ppm on 350m is 1.75mm)

May / Aug 2014 Measurements Measurement of all survey control points and 5 quad stacks in east arc Measurement of long distances in each linac Measurement of all survey control points and 5 quad stacks in west arc Measurement of distances between penetrations on the surface

Distance between penetrations East Arc Control Distance between penetrations Overall scale factor -3ppm

May / Aug 2014 Results Comparison to June 2012 Network survey Mar-13 Apr-14 May-14 Aug-14 E. Arc 7par scale factor -25.7 ppm -7.6 ppm -2.9 ppm -2.3 ppm E. Arc "Traverse" 2012 243.70899 m E. Arc Traverse length 243.70020 m 243.70654 m 243.70835 m 243.70795 m E. Arc Traverse length diff. -8.79 mm -2.45 mm -0.64 mm -1.04 mm Avg. Sampled Temperature NA 29.8 29.5 28.7 N. Linac Average Distance +2.9 ppm +0.8 ppm -0.3 ppm -0.6 ppm S. Linac Average Distance +4.9 ppm +1.7 ppm -0.9 ppm

West Arc Control Overall scale factor -5ppm

West Arc Results Comparison to June 2012 Network survey May-14 Aug-14 7 par scale factor -5.2 ppm -3.8 ppm "Traverse" 2012 244.01590 m Traverse length 244.01288 m 244.01304 m Traverse length diff. -3.02 mm -2.86 mm Avg. Sampled Temperature 28.9 30.0

Conclusion Virtually all elements of CEBAF were re-aligned for 12 GeV upgrade Final network measured June 2012 - Accelerator was its warmest Final alignment started March 2013 - Accelerator at its coldest Accelerator expands and contracts unevenly Accelerator has now expanded back to about its 2012 values But 2cm path length difference is currently unexplained Further measurements are planned: increased thermometry beam based measurement additional surveys By better understanding the cause, we may be able to determine if the correction devices employed by accelerator operations to date, will be sufficient to compensate for this effect in the future.