1 Status of ATF/ATF2 and machine schedule in this fall
Impact of the earthquake Recovery status, alignment Schedule in this fall N. Terunuma, KEK

2 Rough Alignment (LINAC)
Recovery History for Test Beam Mar 11 14 21 28 Apr 4 18 25 May 2 9 16 23 30 Jun 6 13 20 27 Jul KEK MW 1.7 2 / 5 MW (day/night) 24 MW Blackout ½ power Power line recovery ATF Shield ATF2 Shield Radiation Safety Test Beam KEK Requested Standby at Home Summer Shutdown Power Distri-bution Cooling Water Vacuum RF Rough Alignment (LINAC) (BT) (DR)

3 Impact of the earthquake on ATF
Photo: 2011/March/11 15:55

4 Main Power Lines Recovered in April

5 ATF LINAC All were repaired in March!
QM2L table was backed to the original. Chambers were exchanged. QD10L bellows was exchanged. All were repaired in March!

6 ATF LINAC Klystrons Repaired in April.

7 Beam Transport Repaired in April. Fallen Pb blocks were cleared.
Ceramic of the CT monitor and a bellows were exchanged. Repaired in April.

8 Damping Ring Repaired in April/May

9 ATF2 beam line Magnet Mover Dust on the IP-BSM Optics
Repositioning Dust on the IP-BSM Optics Outside of ATF2 end Dust on the FD mover 10 cm slide

10 ATF2 FD/IP shield works: re-positioning
Big work! 3 weeks

11 ATF2 FD-IP area Recovered in May

12 Checkout of Electricity and Water in May
Cooling Water pipes DR magnet PW station, 6.6kV

13 A test beam passes all beamline
Single bunch, 0.78 Hz, 0.3 x 1010 e/bunch DR&ATF2 6/3 MSPIP 6/3 MS1FF 6/2 MS1X 6/3 MS2FF 5/27 BT end 6/2 DR storage 5/31 DR 1st turn 2011/5/25 Injector 2011/5/26 LINAC 2011/06/03 N.Terunuma

14 Stored beam in DR (x1010 e/bunch) A stored beam was delivered to the dump of ATF2. No critical damage on the accelerator was found. 3 trains 3 trains 1.0x1010 XSR ready Inspection of the radiation safety FONT V-emittance (XSR) ~30pm Freq. Adjust 0.5x1010 Compton 2-mirror FFTB mover HAPS Cavity BPMs 6/1 6/3 6/8 6/10 6/13 6/17 6/24 6/30 DR rough alignment for checkout was continued in daytime.

15 Welcome back from oversea
17 persons May - August

16 Alignment of the beamline - continued work -

17 Status of Alignment All in the ATF building was shaken (10 cm or more?) by Great East Japan Earthquake. ATF2: Just surveyed. Waiting the alignment work in October. DR: North-South was longer than the design about 1.5 mm. Is it caused by earthquake?  made new optics to minimize the alignment Linac/BT Lift up the downstream section close to the BT/DR level. It will improve the difficulty of the injection.

18 Alignment: LINAC/BT level
comments Re-aligned Cavity Re-aligned LINAC Table Measured after earthquake BT was re-aligned but plots were not yet prepared. LINAC’s drop to end and jump to BT had been known since the DR startup. It might be caused by the DR construction after LINAC alignment. It brought a troublesome tuning to us. We corrected these by using a long shutdown for power-recovering after the earthquake.

19 DR displacement (Enlarged image)
after earthquake Rough alignment in May 1.5 mm wider(N-S) than the original design. When?? New design was defined as wider but same circumference.

20 Alignment: DR level Vertical (mm) aligned in June, aligned in summer
0.5 Target: |x|< 90 um 0.0 Vertical (mm) -0.5 East Arc is under realignment. North West Arc South -1.0

21 Alignment: DR Horizontal (mm) Longitudinal (mm) aligned in summer
Others aligned in May 1.0 0.5 Target: |x|< 90 um Horizontal (mm) 0.0 -0.5 North West Arc South East Arc is under realignment. 1.0 0.5 Longitudinal (mm) 0.0 -0.5 -1.0

22 Waiting for alignment: ATF2
Level of the EXT-ATF2 magnets Floor of ATF2 sank about 1.5 mm. 0.0 Target: mm -1.0 QF1 mover is ON Vertical (mm) -2.0 QD0 mover is OFF FFTB movers are “zero” position. EXT FF -3.0

23 ATF2 Q-magnet Setup Q magnet (KEK,SLAC,IHEP) QBPM (Cavity BPM)
(KEK,PAL) FFTB mover (SLAC) QBPM electronics (SLAC) (2008/6) Concrete Base Stand (KEK)

24 Waiting for alignment: ATF2
Horizontal Longitudinal (mm) (mm) 1.0 Target: mm 0.0 0.0 -1.0 -1.0 -2.0 -3.0 -2.0 Datum on floor -4.0 -3.0 EXT FF EXT FF We are checking the definition of the datum on the floor used at the ATF2 construction. Offset?

25 Waiting for alignment: ATF2
Roll of magnets (mrad) 1.0 - 1.0 EXT Target: mrad Pitch (mrad) FF

26 Schedule (draft for discussion)
Sep.26 Oct. 3 10 17 24 31 Nov. 7 14 21 28 Dec. 5 12 19 26 Beam Alignment ATF2 &TB meeting DR DR survey survey survey EXT-FF Checkout of beam instruments Low emittance, Compton and Others ATF R&D Recovery of 10 pm (DR) ATF2 R&D extraction Recovery of 300 nm Goal-1 and others

27 2012 Schedule (draft for discussion)
Jan. 2 9 16 23 30 Feb 6 13 20 27 Mar.5 12 19 26 Apr May 7 14 21 28 Jun 4 11 18 25 GDE meeting? JPS meeting Summer Shutdown New IP-BPM installation at IP Low emittance, Compton and Others Goal-1? and others Goal-2? and others

28 Additional slides

29 New Pol e+ system will be installed in this fall (DR)
Upgrade of the 2-mirror system to 4-mirror system is underway. (Hiroshima, KEK) Old 2-mirror system in DR was replaced with a dummy chamber in August. New 4-mirror system is under testing beside the beamline. Installation will be done in the maintenance week after the full checkout of the optical system. It will be in October or later.

30 Alignment: DR all B Q Sx Horizontal Longitudinal
After earthquake, aligned in June, aligned in summer Horizontal Longitudinal all - 2.0 mm +2.0 mm - 2.0 mm +2.0 mm B Q Sx