11 T Dipole Integration & Plans M. Karppinen

Slides:



Advertisements
Similar presentations
LM dipole status & plans – Fred Nobrega 1 Long Quadrupole (LQ) Workshop, February 7-9, 2007 BNL - FNAL - LBNL - SLAC Long Dipole Mirror (LM) Status and.
Advertisements

Mikko Karppinen Nb3Sn Coil Production for 11 T Dipole Model Magnets.
Preliminary Design of Nb 3 Sn Quadrupoles for FCC-hh M. Karppinen CERN TE-MSC.
F. Savary on behalf of the WP11 team Input from V. Baglin, D. Ramos.
11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.
Fred Nobrega. 9 Dec 2014 Model Design & Fabrication – FNAL Fred Nobrega 2 Outline Background Mechanical Design Model Magnet Features Coil Technology and.
Thoughts about the MQXF development plan P. Fessia Thanks to discussions within the MDT section (P. Ferracin, J. C. Perez, E. Todesco, P. Ferracin), L.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
11 T Dipole Experience M. Karppinen CERN TE-MSC On behalf of CERN-FNAL project teams The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded.
Eucard-WP7-HFM 9 th Collaboration Meeting at Warsaw University of Technology Status on SMC & RMC Models J.C Perez on behalf of SMC collaboration team.
F. Savary. Click here to add footer 2 Outline Context Constraints & Boundary conditions Project plan Production strategy A few words on QA Conclusions.
Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design.
11 T Dipole Status at FNAL Fred Nobrega January 21, 2014.
Fred Nobrega, Nikolai Andreev 21 September, 2015.
Title – xxxx 1 LARP & US-HiLumi Contribution to the Inner Triplet Quadrupoles G. Ambrosio Cost and Schedule Review CERN, March 9 th -11 th 2015.
October/7/2011 J.C. Perez TE-MSC-MDT EuCARD WP7-HFM Collaboration Meeting (Geneva) SMC E U CARD WP7 HFM S TATUS UPDATE MEETING O CTOBER 2011 J.C. Perez.
11 T Dipole Informal Coil and Assembly Readiness Review CERN September 2013 Review committee: Herman Ten Kate CERN (Chair) Fred Nobrega FNAL Davide.
S. Caspi, LBNL HQ Progress and Schedule Shlomo Caspi LBNL LARP Collaboration Meeting – CM13 Port Jefferson November 4-6, 2009.
LARP Magnets FNAL contribution to LARP (LHC Accelerator Research Program) FNAL core-program support to LARP DOE Annual Program Review - May 16-18, 2006.
D. Smekens. 2 Coil ID  CableCu DUMMY Cu DUMMY WST DUMMY RRP 54/61 DUMMY RRP 108/127 RRP 108/127 RRP 108/127 RRP 132/169.
MQXF Q1/Q3 Conductor Procurement A. K. Ghosh MQXF Conductor Review November 5-6, 2014 CERN.
F. Savary Question 1 A. Magnet design criteria for the prototype and production magnet to be tested before the installation into the tunnel.
11 T Dipole Project Goals and Deliverables M. Karppinen on behalf of CERN-FNAL collaboration “Demonstrate the feasibility of Nb3Sn technology for the DS.
F. Savary Industrial service contracts for HL-LHC MSC Technical Meeting on
FRESCA2 Technical Meeting 5-Validation of coil winding with Cu coils Françoise Rondeaux 09/06/ CEA-Irfu-SACM-LEAS - 5-Rondeaux- FRESCA2 Technical.
11 T Dipole Project Cold mass integration status & plan F. Savary / TE-MSC-LMF.
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
11 T Dipole Status May 2012 M. Karppinen CERN TE-MSC On behalf of CERN-FNAL collaboration.
MQXF Short model and prototype plans P. Ferracin, G. Ambrosio HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN.
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
Long Quad (LQ) & High Gradient (HQ) Series Alexander Zlobin bnl - fnal- lbnl - slac US LHC Accelerator Research Program DOE LARP review Fermilab, June.
CERN MBHSM0101 and Plan for Future Models F. Savary on behalf of the 11T Dipole Project Team.
2 nd LARP / HiLumi Collaboration Mtg, May 9, 2012LHQ Goals and Status – G. Ambrosio 11 LHQ Goals and Status Giorgio Ambrosio Fermilab 2 nd LARP / HiLumi.
Magnet Components and Assemblies F. Savary
EuCARD-WP7-HFM meeting 15 November 2011 Status of construction of FRESCA2 dummy coil assembly Attilio Milanese, Juan Carlos Perez.
Closing Session Report
P. Ferracin on behalf of the MQXF collaboration
Cryostats for superconducting magnets
Hardware Challenges and Limitations
HL-LHC Magnet components and assemblies
QXF Coil Fabrication & Tooling Reaction / Impregnation
TQS Overview and recent progress
Roadmap for triplet cryostats
Model magnet test results at FNAL
HQ Mirror Assembly R. Bossert
ESAC Review February 2013 CEA Saclay
Status of design and production of LEP connection cryostat
MQXF Goals & Plans G. Ambrosio MQXF Conductor Review
At ICFA Mini-Workshop on High Field Magnets for pp Colliders,
11T Dipole – Single Aperture 2m Model
FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets
J.C. Perez on behalf of SMC collaboration team J.C. Perez
11 T dipole coil features and dimensions
DS11 T Transfer function, integral field and coil length
Mechanical stability and QXF coil winding
MQXF Short Models Status and Plans
Procurement of Nb3Sn strand for coils assembled at CERN
P. Ferracin and G. Ambrosio
the MDP High Field Dipole Demonstrator
11 T Dipole Project Overview and Status
SMC Design overview of the construction and project issues
Introduction to the technical content The Q4 magnet (MQYY) for HL-LHC
Paolo Ferracin, Giorgio Ambrosio
MKQXF FEA Model Haris Kokkinos
Large aperture IR Quadrupole (MQXF) development plan
MQXF updates P. Ferracin October 9th, 2014.
MQXF coil cross-section status
QXF schedule and milestones
Qingjin XU Institute of High Energy Physics (IHEP),
Globus-M2 will be constructed by the end of 2015
Presentation transcript:

11 T Dipole Integration & Plans M. Karppinen From short models to the series

M. Karppinen CERN TE-MSC 11 T Nb3Sn Dipole Project Short model program Magnetic and mechanical design validation Conductor development Magnet protection Material choices Fabrication process validation Scale-up Coil fabrication (winding, curing, reaction, impregnation) Handling Cold mass integration (collaring, yoke assembly) Cold mass integration Cold bore tube Bus-bar routing Interconnects Spool correctors Heat exchanger Instrumentation Alignment Cryo-assembly (5.5 m) Cold-test in SM18 Collimator integration Collimator dimensions Interfaces (powering, instrumentation, vacuum, cryogenics, ...) Cryostat design QC and testing Transport & handling 12 June 2013 M. Karppinen CERN TE-MSC

M. Karppinen CERN TE-MSC 11T Dipole Coldmass (5.3 m) 5´772 5´911 5´546 6´257 (Ltotal) 242.5 5´772 (LCM) To reduce the length by 0.2 m the B0 shall be 11.66 T, which requires additional ~530 A (wp 81% => 85%) TF correction requires -300 A, so a bi-polar 600 A trim PC could do the job. 12 June 2013 M. Karppinen CERN TE-MSC

FNAL 1-in-1 Model Magnet (1m) & CERN Coils Courtesy of D. Mitchell, FNAL 22 May 2013 M. Karppinen CERN TE-MSC

CERN Construction Status Coil fabrication tooling: Winding, curing, and reaction fully operational Vacuum impregnation system now commissioned Practice coil fabrication PC-#1-2 (Cu-cable) reacted, being impregnated PC #3 Nb3Sn (low-Jc WST strand) scrapped Nb3Sn (RRP-54-61) reacted, to impregnate Magnet R&D: Cable insulation (braided S2-glass & Mica) ODS (oxide dispersion strengthened) wedges Selective laser sintering (SLS) end spacers Coil pre-loading concept (“pole-loading”) Magnet protection (inter-layer heater) Coil reaction Coil impregnation Reacted Nb3Sn (RRP-54/61) coil 12 June 2013 M. Karppinen CERN TE-MSC

M. Karppinen CERN TE-MSC CERN 11 T Dipole Coil Loading plate 2 mm 316LN SLS End Spacers with “springy legs” ODS Cu-alloy Wedges Braided 11-TEX S2-glass on “open-C” Mica sleeve Courtesy of D. Mitchell, FNAL 12 June 2013 M. Karppinen CERN TE-MSC

CERN Short (2 m) Model Program Assemble and test the RRP-54/61 coil (reacted) as single coil assembly (MBHSS101) using existing collars, yoke, welded outer shell, and end plates Two RRP-108/127 coils to assemble and test the 1st 1-in-1 model (MBHSP101) Two RRP-132/169 coils to assemble and test the 2nd 1-in-1 model (MBHSP102) Collared coils from MBHSP101 & 102 to assemble and test the 1st 2-in-1 model (MBHDP101) Idem for PIT-cable: 2 x 1-in-1 model (MBHSP103-4) to have tested collared coils for the 2nd 2-in-1 model (MBHDP102). Will be conflicting with MQXF and other magnet projects in terms of human resources and infrastructure 12 June 2013 M. Karppinen CERN TE-MSC

CERN Single Coil Assembly Courtesy of C. Kokkinos & T. Lyon CERN TE-MCS Aftrer assembly at 293 K At 1,9 K, 11.02 T, 14.1 kA Azimuthal coil stress (Mpa) Azimuthal coil stress (Mpa) 12 June 2013 M. Karppinen CERN TE-MSC

CERN Short Model Schedule Oct-Nov -13 Jan-Feb -14 Apr-May -14 1-in-1 #1 Test Nov -14 – Jan -15 Feb-Mar -15 1-in-1 #2 Test Apr-Jun -15 2-in-1 #1 Test 1-in-1 #3 Test 1-in-1 #4 Test 2-in-1 #2 Test 12 June 2013 M. Karppinen CERN TE-MSC

CERN Prototype (5.5 m) Schedule Start with winding trials using Cu-cable: simplified trials coil with bare cable first practice coil with insulated Cu-cable to react and pot (PC-1). First Nb3Sn practice coil with possibly low-performance (cheaper) cable (PC-2) First “real” coil (PC-3) to cold test as a single coil (mirror?) Four (or eventually more..) more coils for 2 collared coils to construct the full-scale proto and test it in Mid-2016. the 5.5 m schedule is compatible with the present LMF plans including the major procurements Additional coil production lines will be required for series magnets It is also vital to get the industry on board during the prototype construction to be ready for the series units 12 June 2013 M. Karppinen CERN TE-MSC

CERN 5.5 m Prototype Schedule May-June 2015 July-August 2016 Single coil Qualification Test 5.5-m-long 2-in-1 Prototype Test 12 June 2013 M. Karppinen CERN TE-MSC

Series production (First impression) LS2: Ions: Install 2 x units (4 X 5.5 m CM) in IR2 + 1 spare Protons: Install 4 x units (8 X 5.5 m CM) in IR7+ 1 spare Deliver 6-10 fully tested 5.5-m-long 11 T Dipole cold masses Integrate 2-4 fully tested 15.6-m-long cryo-assemblies in the LHC Coil production: 12-20 off 5.5-m-long coils to deliver 1 Production line/2 production lines 1/2 coil in 12 w, 2/4 coils in 17 w All coils: 26-43 months / 13-22 months Cold mass integration: Two collared coils 8 months / 5 months Cold mass assembly 1 month Cryostat assembly 1 month Cold test 2 months 6-10 CM X 11 / 9 months = 48-84 / 34-54 months Cryo-assembly: Cold mass integration: 2 months Cold test: 2 months 2 complete units min. 28 months 12 June 2013 M. Karppinen CERN TE-MSC

Cold mass vs. coil production lines 12 June 2013 M. Karppinen CERN TE-MSC

2 Off Cryo-Assemblies for IR2 12 June 2013 M. Karppinen CERN TE-MSC