Expected hardware status and Priority of the commissioning task

Slides:



Advertisements
Similar presentations
Summary of the discussion for the commissioning session 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 6/ 1/ 2006 T.Okugi (KEK)
Advertisements

Status of ATF/ATF2 and machine schedule in this fall Impact of the earthquake Recovery status, alignment Schedule in this fall N. Terunuma, KEK.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
-brief report of October runs and some inputs for the Nov/Dec planning – Nobuhiro Terunuma, KEK, ATF ATF session on LCWS13, Tokyo Univ., Nov. 13, 2013.
ATF2 Status and Plan K. Kubo ATF2, Final Focus Test for LC Achievement of 37 nm beam size (Goal 1) – Demonstration of a compact final focus.
Plan for the summer Nobuhiro Terunuma, KEK ATF day: ATF Collaboration Meeting European Linear Collider Workshop ECFA LC2013, May 28,
1.Beam Tuning Simulation 2.IP Beam Position Stability 2-1 ) Magnet Vibration 2-2 ) IP position jitter subtraction for 2 nd bunch with FONT feedback 2-3.
Discussion on Milestone and schedule Toshiyuki Okugi ATF2 commissioning meeting 1 / 7 / 2009.
Status of very high priority beam tuning software Special ATF2 project meeting, Korea, 1 st October 2008 Cécile Rimbault, on behalf of High Priority task.
ILC RTML Lattice Design A.Vivoli, N. Solyak, V. Kapin Fermilab.
Personal strategy for ATF2 beam operation in 2009 Toshiyuki OKUGI 2009 / 7 /22 ATF2 weekly meeting.
ATF2 commissioning in Autumn 2009 for discussion Philip Bambade LAL & KEK LCWS09 BDS session Albuquerque, New Mexico October 1, 2009 on behalf of the commissioning.
ATF2 optics … 1 3 rd Mini-Workshop on Nano Project at ATF ATF2 optics, tuning method and tolerances of initial alignment, magnets, power supplies etc.
March 7, 2007 LET Issues (Cai/Kubo/Zisman) Global Design Effort 1 Low-Emittance Tuning Issues and Plans Yunhai Cai, Kiyoshi Kubo and Michael S. Zisman.
FFS Issues in the 2011 autumn continuous operation Toshiyuki OKUGI (KEK) 1/13/2011 The 11 th ATF2 project meeting SLAC, USA.
ATF Instrumentation Status and Planning 3 December 2007 Juan Cruz, Justin May, Doug McCormick, Janice Nelson, Tonee Smith, John Wray.
Mark Woodley, SLACATF2 Software Review (June 18, 2008)1 ATF2 Layout/Optics (v4.0) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing ATF Extraction.
Continuous Run in May K.Kubo. Final Focus Test Line IP; ~40 nm beam ATF Linac (1.3 GeV) ATF Damping Ring (140 m) Extraction Line Photo-cathode.
ATF2 Optics for the Commissioning Toshiyuki Okugi, KEK 2008 / 10/ 22 ATF2 commissioning meeting.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
Commissioning Status of Shintake Monitor (IP-BSM) T. Yamanaka, M. Oroku, Y. Yamaguchi, Y. Kamiya, S. Komamiya (Univ. of Tokyo), T. Okugi, N. Terunuma,
Mark Woodley, SLACATF2 Project March 20-21, Summary of Tuning, Corrections, and Commissioning.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
8 th Meeting of the ATF TB/SGC 11 June Hardware Status Fast Kicker – FID pulsers have had a reliability problem: this appears to have been solved.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Low emittance tuning in ATF Damping Ring - Experience and plan Sendai GDE Meeting Kiyoshi Kubo.
Bruno Muratori (for the EMMA team) STFC, Daresbury Laboratory EMMA commissioning 02/09/08.
1 H. Hayano ATF Status June/2004 H. Hayano ATF: emittance status beam study status plan nm-project collaboration & plan ATF review 6/17/2004.
Mark Woodley, SLAC5th ATF2 Project Meeting (December 19, 2007)1 ATF2 Layout/Optics (v3.8) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing.
Commissioning Hardware and IP Configuration of ATF / 12 / 19 ATF2 project meeting at KEK Toshiyuki Okugi (KEK)
Mark Woodley, SLAC6th ATF2 Project Meeting (May 27, 2008)1 ATF2 Layout/Optics (v4.0) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing ATF Extraction.
Initial beam size commissioning for ATF2 T.Okugi 3rd ATF2 Project Meeting, KEK 12/ 19/ 2006.
IP instrumentation configuration for Autumn 2010 ATF2 runs Toshiyuki OKUGI, KEK 2010 / 7/ 1 10 th ATF2 project meeting.
ATF2 Tuning Summary Nov & Dec 2010 Glen White, SLAC 11 th ATF2 Project Meeting, SLAC Jan
Mark Woodley, SLACATF2 Project March 20-21, Next version of MAD decks (v3.7): what needs to be added/deleted?
Task Lists of ATF2 commissioning Toshiyuki Okugi ATF2 Project Meeting 12 / 17 / 2008.
ATF2 beam operation status Toshiyuki OKUGI, KEK The 9 th TB&SGC meeting KEK, 3-gokan Seminar Hall 2009/ 12/ 16.
N. BlaskovicFONT Meeting1 ATF November 2013 shift plan N. Blaskovic.
Summary of Tuning, Corrections, and Commissioning ( Short summary of ATF2 meeting at SLAC in March 2007 ) and Hardware Issues for beam Tuning Toshiyuki.
IP diagnostics Toshiyuki Okugi 2008 / 6 /19 ATF2 Software mini-workshop LAL, Orsay.
DRAFT: What have been done and what to do in ILC-LET beam dynamics Beam dynamics/Simulations Group Beijing.
Simulation of the α, dispersion, coupling and β multiknobs in large β optics Sha Bai, Philip Bambade, Benoit Bolzon, Javier Resta Lopez
FJPPL-FKPPL ATF2 Workshop Jitter studies March 18, 2014 Beam jitter localization and identification at ATF2 Marcin Patecki Jürgen Pfingstner 18 th of March.
1 1 H. Hayano and ATF group ATF Status August/2004 H. Hayano and ATF group Multibunch emittance Instrumentation developments Plans for run Multibunch.
ApEx needs for CeC PoP Experiment December 11, 2015.
ISG – Damping Ring Physics and Design Group ATF – 2003// focus on the TRC challenge Marc Ross – 1.Instability about which little is known: Fast ion,
2nd ATF2 Project Meeting (May 30, 2006)M. Woodley [SLAC]1 ATF2 Layout/Optics (v3.3) nBPM (SLAC) nBPM (KEK) FONT Compton / laserwire ODR Existing ATF Extraction.
Technical Board Summary Preliminary Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France ATF2 project meeting, Technical.
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
Hardwares for commissioning 2 nd ATF2 Project Meeting KEK, Tsukuba, Japan 5/ 31/ 2006 T.Okugi (KEK)
Simulation for Lower emittance in ATF Damping Ring Kiyoshi Kubo Similar talk in DR WS in Frascati, May 2007 Most simulations were done several.
Special ATF Session - ATF/ATF2 day on 28th September -
Emittance Diagnostics
Tolerances & Tuning of the ATF2 Final Focus Line
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
Emittance Dilution and Preservation in the ILC RTML
ILC Z-pole Calibration Runs Main Linac performance
Auxiliary Positron Source
Coupling Correction at the Australian Synchrotron
Beam-based alignment measurements
Status of ATF/ATF2 and machine schedule in this fall
The SPEAR3 Upgrade Project at SLAC
3rd ATF2 Project Meeting, December 18-20, 2006
The SPEAR3 Upgrade Project at SLAC
LAL meeting on e+ studies, Oct. 2010
ATF ICB meeting, LCWS08, UIC, Chicago, 11/18/2008
N. Terunuma (KEK) ILC2010, Beijing, March 29th, /2/28.
ATF2 Layout/Optics (v3.6) Existing ATF Extraction Line
Linac Diagnostics Commissioning Experience
ThomX – Commissioning Meeting – 25/01/2018
Presentation transcript:

Expected hardware status and Priority of the commissioning task Toshiyuki Okugi 2008 / 6 /18 ATF2 Software mini-workshop LAL, Orsay

Expected Magnet Status at the beginning of ATF2 commissioning We have all of the corrector magnets ( ZHs and ZVs ). All of the magnet movers are put to ATF2 beamline. We need study of the coupling of the motion ( x, y, roll, yow ). We need fix the stay position of the magnet. All of the magnet PS are in KEK, and adjusted the ripples. They will be wired to the magnets and will be calibrated with actual loads. We may not have 2 skew quadrupoles (QK2X and QK3X ). The dispersion correction will be able to applied with QS1X and QS2X. We should correct the betatron coupling only with QK1X and QK4X. The two quadrupoles are high priority of JFY2009 budget.

Expected Monitor Status at the beginning of ATF2 commissioning - All of the C-band and S-band cavity BPMs will be put to the beamline, and the readout electronics will be wired. We need to devolop the readout software. We need to study of the calibration and position offset measurement. We need to study of the reliability of the readout electronics. All of the screen monitors and OTR monitor will be ready. All of the wire scanners will be ready. We can use the Carbon wire scanner, but we cannot put the sweeping magnet. One of the ICT (MICT1X) will not be placed in the beamline. - IP BPM will not be placed in the Shintake monitor chamber.

Stripline BPMs Phase Advance from MQF1X MQF1X 0.000 0.000 MQD2X 168.066 4.651 MQF3X 169.934 5.568 MQF4X 172.341 175.627 MQD5X 173.557 176.841 MQF6X 342.993 179.821 MQF7X 364.341 201.254 MQD8X 442.892 209.395 MQF9X 499.201 224.782 MQF13X 680.337 463.554 MQD14X 723.433 485.897 MQF15X 782.005 502.695 MFB2FF MBUMP The number of the stripline BPM depends on the length of the present BPM cables. The number of BPM will be fixed by September 2008. Since red BPMs are high priorities than others, we can use the BPMs at the beginning of the commissioning. Since blue BPMs are a little bit low priorities than others, some of them may not be wired at the beginning of the commissioning. Even if we cannot wire some of BPMs, we will wire the BPM in JFY2009.

Priority of the Commissioning Task The main task of the commissioning team is to achieve the 35nm vertical beam size at ATF2 IP. But … The 1st priority of the ATF2 commissioning in 2008 is to pass the radiation inspection. The radiation inspection is not only for ATF, but also for all of KEK accelerators. In the radiation inspection, we must operate the ATF with 10% of maximum beam power (2x1010 20 bunches 12.5Hz). The beam intensity is far from the normal operation. We must concentrate not only ATF2 beamline commissioning, but also reduction of the injection loss to DR. - We will install new RF gun to reduce the dark current. - We must put more radiation shield etc. . Thereby, we have no idea how much time will be prepared for the ATF2 beam study in 2008. I think most of the beam study will be started from early 2009.

Schedules of ATF2 commissioning early December Fast Kicker Study ?? ( Not yet decided ) Radiation Inspection The “fast kicker study” will be used the special setting. ATF2 Start early 2009~ ? DR study ( fast ion, DR emittance … ) Beam line commissioning Hardware study at the extraction line ( FONT, Laser Wire … ) Reduction of radiation loss Extraction line tuning and study ( dispersion, coupling correction , emittance growth at extraction… ) ATF2 final focus line study ( beam size tuning, stabilization … ) Device Commissioning for ATF2 (cavity BPM, Mover, Guarder, Magnet PS )

Beam deliver to the dump with small beam loss I think it is better to use the simple and easy optics to deliver the beam to the dump at the beginning of the ATF2 operation. Normal Optics Advantage Easy to shift to the beam tuning phase Disadvantage Large beam size Large number of ambiguity

Mechanical alignment of bending magnet rotation Example of Special Optics for Commissioning Extraction section same to the nominal Final focus section turn on only 4 quads QF9AFF 0.293 1/m QD8FF -0.387 1/m QF7FF 0.144 1/m QF3FF 0.195 1/m MSPIP MS1FF QF9AFF QF7FF QF3FF MS2FF QD8FF Advantage Disadvantage Small beam size Small number of beam steering knob Possible to be BPM calibration Difficult to put IPBPM Possible to be first step of BBA Mechanical alignment of bending magnet rotation Fix the strength of the bending magnet and easy to make a orbit reference