Commissioning Hardware and IP Configuration of ATF2 2007 / 12 / 19 ATF2 project meeting at KEK Toshiyuki Okugi (KEK)

Similar presentations


Presentation on theme: "Commissioning Hardware and IP Configuration of ATF2 2007 / 12 / 19 ATF2 project meeting at KEK Toshiyuki Okugi (KEK)"— Presentation transcript:

1 Commissioning Hardware and IP Configuration of ATF2 2007 / 12 / 19 ATF2 project meeting at KEK Toshiyuki Okugi (KEK)

2 Commissioning Hardware for ATF2 I proposed the following hardware preparation to SLAC at the ATF2 meeting in March 2007. 1) BPM ; - I, Q information from each readout electronics (SLAC) - Temporal BPM control panel for commissioning (KEK) (x, y) = A * Sqrt (I^2+Q^2) * Sgn ( I or Q ) A ; free parameter I,Q ; from SLAC  First pulse calibration result seems to be good performance. Can we use the BPM information from the beginning of the commissioning? If YES, we don’t have to prepare the temporal BPM control panel. 2) Screen, ICT (KEK) and information of amplitude of reference cavity (SLAC). 3) Quad Movers Calibration and control system should be ready before commissioning (SLAC). First priority of the ATF commissioning is to transport the beam to the end of ATF2 beam line without beam loss.

3 200350 Shintake Monitor Area IP 400 540 567.5 135 200 120100 705 QD0 S-band BPM Sweeping Magnet Honda Monitor 100 180 550 100 Carbon Wire Scanner C-band BPM 180 Screen Monitor 825 Dump Bend 485 200 150 660 180 100 Stripline BPM ICT IP configurations presented at Annecy Meeting IP-BPM 1015 100 180 200 Small vertical aperture How to put all of the devices in the limited space ? Is it possible to shorten - the length of the stripline kicler ? - the Shintake monitor support table thickness ? - the thickness of the adopter of S-band BPM ? - the length of Honda monitor ?

4 SBPM QC3 SBPM FFTB 2.13 S3.00 SF1FF QF1FF 100 450.1 200 180 SBPM QC3 SBPM FFTB 2.13 S3.00 SD0FF QD0FF 100 76.2 450.1 200 18076.2 785380785380 Final Doublet Table Configuration 2630 200mm space is necessary for S-band BPM with adopter.

5 IP BPM Chamber 100mm IP 135mm100mm IP BPM will be located on the chamber. Honeycomb Table IP BPM chamber will be mounted in the hole of the Shintake monitor honeycomb table

6 Sweeping Magnet Flange to Flange Length150 mm Electrode Length80 mm Electrode Gap40 mm Power Supply SpecificationDC +/- 100V, double pulse, bipolar Kick Angle6.1nrad / V Scan Position at IP 3.7nm / V Dynamic Range+/- 370nm - enough for Shintake monitor, carbon wire and IP FB. - However, it is too week for Honda monitor. The old stripline kicker will be modified for the sweeping magnet. For the nominal operation, one side of electrodes should be open, and use DC PS. For the first feedback, one side of electrodes should be connect to the load.

7 200 150 IP 400 425 567.5 135 200 100 607.5 QD0 S-band BPM Sweeping Magnet Honda Monitor 100 180235 100 Carbon Wire Scanner C-band BPM 180 Screen Monitor 825 Dump Bend 485 200 660 180 100 Stripline BPM ICT New IP configurations 1015 100 180 185 IP BPM

8 Stripline BPM Device List Blue ; wide beam pipe Red ; Long Electrode ( High Resolution) Old BPM Name Electrod e Length Pipe Diamet er OriginalModifiedBellows Magnet Thicknes s Pipe Length Total Length Magnet Thickness Pipe Length Total Length OriginalModified Electrode Side No Electro de Electrode Side No Electrode ML1X40Narrow601551203356015560275○○ ML2X40Wide60180120360180155330665×○ ML3X40Wide6018012036018015560395×○ ML4X40Wide1801206036018015560395×○ ML5X40Wide1801556039518015560395○○ ML6X40Wide1801206036018015560395×○ ML7X40Narrow18012060360180155220555×○ ML8X120Narrow602708041018022060460○○ ML9X120Narrow18022030070018022060460○○ ML10X120Narrow18022030070018022060460○○ ML11X120Narrow18022030070018022060460○○ ML12X120Narrow180220300700N/A22030250○○ ML13X40NarrowN/A 170N/A 170×× ML14X40NarrowN/A 37518015560395×○

9 nameold namefunctiontype locationcomments ML1XML2XBPMstripline (L.R.)d/s end of QF1X (Hitachi 180) MS1X move by +35mm ML2XML3XBPMstripline (L.R.)d/s end of QD2X (Hitachi 180) ML3XML4XBPMstripline (L.R.)d/s end of QF3X (Hitachi 180) ML4XML5XBPMstripline (L.R.)d/s end of QF4X (Hitachi 180) ML5XML6XBPMstripline (L.R.)u/s end of QD5X (Hitachi 180) ML6XML7XBPMstripline (L.R.)u/s end of QF6X (Hitachi 180) ML7XML1XBPMstripline (L.R.)d/s end of QF7X (Hitach 60) ML8XML14XBPMstripline (H.R.)d/s end of QD8X (Hitachi 180) ML9XML8XBPMstripline (H.R.)u/s end of QF9X (Hitachi 180) ML10XML9XBPMstripline (H.R.)d/s end of QF13X (Hitachi 180) ML11XML10XBPMstripline (H.R.)d/s end of QD14X (Hitachi 180) ML12XML11XBPMstripline (L.R.)d/s end of QF15X (Hitachi 180) QBPM1X BPMC-band cavityd/s end of QD10X (QEA 180) No mover QBPM2X BPMC-band cavityd/s end of QF11X (QEA 180) No mover QBPM3X BPMC-band cavityd/s end of QD12X (QEA 180) No mover QBPM4X BPMC-band cavityd/s end of QD16X (QEA 180) No mover QBPM5X BPMC-band cavityd/s end of QF17X (QEA 180) No mover QBPM6X BPMC-band cavityd/s end of QD18X (QEA 180) No mover QBPM7X BPMC-band cavityd/s end of QF19X (QEA 180) No mover QBPM8X BPMC-band cavityu/s end of QD20X (Hitach 60) C-band BPM with Hitachi QBPM9X BPMC-band cavityd/s end of QF21X (Hitach 60) C-band BPM with Hitachi nameold namefunctiontype locationcomments ML1FFML12XBPMstripline (H.R.)between QM12FF and QM11FFpulse-to-pulse feedback ML2FFML13XBPMstripline (L.R.)d/s dump bend