NERC Lessons Learned Summary

Slides:



Advertisements
Similar presentations
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Advertisements

NERC Footnote b / 12 – Load Loss
1. Four LLs were published in February Transmission Relaying – Undesired Blocking 2.Lack of Separation for Critical Control Power Supply Leads.
1 PER-005 Update Impact on Operators System Operator Conference April and May 1-3, 2012 Columbia, SC Margaret Stambach Manager, Training Services.
Goshen Area Bus Reconfiguration
NERC Lessons Learned Summary December NERC lessons learned published in December 2014 Three NERC lessons learned (LL) were published in December.
@TxSchoolSafety Continuity of Operations Planning Workshop Devolution & Reconstitution.
System Operator Conference NERC Standards Review for: Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS.
September 2014 Lesson Learned Summary. September 2014 LLs 2 Three NERC lessons learned (LL) were published in September 2014 LL Redundant Network.
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2014 New York Independent System Operator, Inc. All Rights Reserved. Emergency Transfer Criteria NYSRC Reliability.
Remedyforce Value Enablement Kit – Change Management
NERC Lessons Learned Summary March NERC lessons learned published in March 2015 Two NERC lessons learned (LL) were published in March2015 LL
NERC Lessons Learned Summary
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
ERCOT SOL Methodology for the Planning and Operations Horizons Stephen Solis 2014 OTS 1.
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
NERC Lessons Learned Summary April NERC lessons learned published in April 2015 Two NERC lessons learned (LL) were published in April 2015 LL
Project Management By: Dr Madhu Fernando Project Risk Management
EAS Lessons Learned Summary Lessons Learned Published in August 2014.
Reliability Requirements Bill Blevins Manager of Operations Support ERCOT.
Bill Lewis, Compliance Team Lead NERC Reliability Working Group May 16, 2013 Texas RE Update Talk with Texas RE April 25, 2013.
NERC Lessons Learned Summary February NERC lessons learned published in February 2015 Two NERC lessons learned (LL) were published in February 2015.
EAS Lessons Learned Summary Lessons Learned Published in June 2014.
Chapter 12 Implementation and Maintenance
Loss of EMS Events 2015 System Operator Seminar. Training Objectives 2 System Operators will be able to identify the ERO Event Analysis Process Category.
NERC Lessons Learned Summary LLs Published in September 2015.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
NERC Lessons Learned Summary LLs Published in December 2015.
Impacts and Actions Resulting from the August 14, 2003 Blackout Minnesota Power Systems Conference November 2, 2003.
1 NPCC – A-2 Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006 Presented to the NYSRC-RRS.
Lessons Learned Implementing an IEC based Microgrid Power-Management System October 12, 2015 Presented by: Jared Mraz, P.E.
Bert Peters Chair, Path Operator Task Force
Community Health Centers of Arkansas Hazard Vulnerability Assessment Workshop August 11, 2017 Mark Fuller.
NERC Published Lessons Learned Summary
ITIL: Service Transition
Utilizing Your Business Continuity Plan.
NERC Published Lessons Learned
NERC Published Lessons Learned Summary
COMM02 Project Monitoring and Control Unit 8
NERC Published Lessons Learned
NERC Published Lessons Learned
“FRCC RESTORATION PLAN (BLACKOUT & BLACK START)” - TRAINING -
Black Start Overview.
Phase Angle Limitations
NERC Published Lessons Learned
EAS Lessons Learned Summary
NERC Published Lessons Learned
Defect and Enhancement Severities Levels
NERC Published Lessons Learned Summary
Transmission Outage Coordination
NERC Published Lessons Learned Summary
Disaster Recovery Policy & Procedures
CONTINUITY OF OPERATIONS PLANNING WORKSHOP #2
Grid Integration of Intermittent Resources
Western Electricity Coordinating Council
Phil O’Donnell, Manager Operations and Planning Audits
MAC Board Effectiveness Survey
Project WECC-0100 Update Load Modeling Task Force
Pacific Power Seismic Preparedness Update
“TOP-010-1: Data Quality, Analysis Quality, and Alarm Process Monitor”
Presenter: Peter Heidrich, FRCC – BES Drafting Team Chair
NERC Critical Infrastructure Protection Advisory Group (CIP AG)
Impacts and Actions Resulting from the August 14, 2003 Blackout
Phil O’Donnell, Manager Operations and Planning Audits
Business Continuity Program Overview
MAC Board Effectiveness Survey
Project WECC-0100 Update Load Modeling Task Force
Systems Operations and Support
Bert Peters Chair, Path Operator Task Force
Good practices for risk assessment and control activities
Presentation transcript:

NERC Lessons Learned Summary LLs Published in June 2015 – Part II

NERC lessons learned published in 2015 Two Additional NERC lessons learned (LL) published in June 2015 LL20150603 - Pre-Contingent Load Shed Event LL20150604 - EMS Recovery Strategy

Real-Time Contingency Analysis Failure due to a Modeling Error Pre-Contingent Load Shed Outage was planned to take a 345-kV circuit breaker out of service for retrofit and maintenance During the planning for this outage, a potential cascading outage was identified for certain conditions affecting generation and loading in the outage area Reliability Coordinator worked with the registered entities involved to develop an operating memorandum, which described shedding load if the pre-contingency conditions met specified parameters

Real-Time Contingency Analysis Failure due to a Modeling Error Pre-Contingent Load Shed Lesson Learned Communication and coordination is an essential aspect of implementing load shedding in order to minimize the impact to affected parties All potentially affected parties should be included in the planning and advised in advance Include the probable duration of the outage. Most should be of relatively short durations or may be rolling black outs. Planning for pre- and post-contingency actions is encouraged In the planning stage, an alternate plan should be considered in case assumptions made for initial plan change Consider expected temperature changes Planning for an outage that may require load shed should be considered only as a last resort

Real-Time Contingency Analysis Failure due to a Modeling Error Pre-Contingent Load Shed Lesson Learned Cont. BA’s and TOP’s should conduct training and drills with their customers (typically DPs and LSEs) on directing customer load shedding Training should include those who may be contacting the DP and LSE operators and the language of a directive using good three-part communication This helps the DP and LSE operators to have a method for identifying an authority who is giving an operating directive Consider the availability of demand-side management in lieu of load shedding In order for this to be effective, it must be considered early in the planning stage and requested early and possibly, in some cases, prior to the actual need arising.

Generator control system impact on Voltage Regulators EMS recovery strategy EMS auto recovery process was configured such that all nodes (servers, workstations) in the EMS were prompted to unload and/or reboot for a particular system condition This complete system restart sequence took 47 minutes to complete Led to a complete loss of control and monitoring functionality until the critical servers and workstations reported their statuses normal and fully functional

Generator control system impact on Voltage Regulators EMS recovery strategy Corrective Actions System was reconfigured such that if this scenario were to occur again, the entire system would not be prompted to unload and reboot Only the offending server would be impacted Lesson Learned Careful analysis of EMS system configurations that initiate a complete system restart should be performed during the commissioning of the EMS to identify and minimize the duration of EMS unavailability

Generator control system impact on Voltage Regulators EMS recovery strategy Lesson Learned Cont. EMS nodes (servers/workstations) should be prioritized during an auto recovery process such that essential nodes are up and available first to give operators the ability to monitor and control the electrical system as quickly as possible Recovery of non-essential servers, workstations, etc. could have a significant impact on the duration of a complete system restart time Scenarios should be evaluated that could trigger an application or system recovery due to a system condition Procedures should be developed and periodically reviewed to ensure minimal recovery time, and to familiarize staff on recovery processes

Link to Lessons Learned Directions to Lessons Learned: Go to www.NERC.com > “Program Areas & Departments” tab > “Reliability Risk Management” (left side menu) > “Event Analysis” (left side menu) > “Lessons Learned” (left side menu) NERC’s goal with publishing lessons learned is to provide industry with technical and understandable information that assists them with maintaining the reliability of the bulk power system. NERC requests that industry provide input on lessons learned by taking the short survey. The survey link is provided on each Lesson Learned.