SCT Project Management Issues

Slides:



Advertisements
Similar presentations
Metrolinx is an agency of the Government of Ontario Planning, Design and Engineering (PDE) Workplan February 20, 2009.
Advertisements

A Model for Common Services Process Approach Assessment Planning Decision-Making Management.
Reliability Center Data Request Task Force Report WECC Board Meeting April 2009.
PROCESS FRAMEWORK Lecture - 3. Topics covered PROCESS FRAMEWORK PROCESS MODELS DIFFERENCE.
1 PROJECT MANAGEMENT ROLE OF KEY PERSONNEL Bernd Madauss International Space University Strasbourg February, 2011
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
T /5115 Software Development Project I/II Project Planning Jari Vanhanen Ohjelmistoliiketoiminnan ja –tuotannon laboratorio Software Business and.
Making Sense of the WIC EBT IAPD IAPD Session of the 2014 WIC EBT User Group Meeting July 23, :00 AM to 12:00 PM Presented by Cheryl Owens, MAXIMUS.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
LSU 07/24/2004Defining Project Tasks1 Defining the Project Tasks Project Management Unit, Lecture 4.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Module 1 Session 1.1 Visual 1 Managing the Implementation of Development Projects Course Overview and Introduction.
Project Life Cycle.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
QA Methodology By Rajib Roy Independent Consultant Qcon.
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
Chapter 6: THE EIGHT STEP PROCESS FOCUS: This chapter provides a description of the application of customer-driven project management.
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
Software Project Management (SEWPZG622) BITS-WIPRO Collaborative Programme: MS in Software Engineering SECOND SEMESTER /1/ "The content of this.
Project Organization Chart Roles & Responsibilities Matrix Add Project Name.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
1 Project Management Software management is distinct and often more difficult from other engineering managements mainly because: – Software product is.
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
Project Delivery Working Group FY2016 EFCOG Annual Meeting Robert P. Miklos Idaho National Laboratory Battelle Energy Alliance Working Group Chair June.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
BSBPMG502A Manage Project Scope Manage Project Scope Project Scope Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit.
Process and customizations
Global Youth Tobacco Survey (GYTS): Overview
Camera PDR/CD1 Planning 19 September 2008
AMICI WP1 – Management, coordination and dissemination
Phase II, The Pilot Area Kick-off
CMGT 410 aid Education Begins/cmgt410aid.com
ANSI/EIA-748-B Earned Value Management Systems (EVMS)
By Wilmer Arellano Spring 2010
Software Project Configuration Management
Business (Agency) Process Discovery and Documentation Workshop
Scope Planning.
Completion and Pre-Exploitation Costs for the Initial ATLAS Detector
Status of the MICE Construction Project
System Planning To Programming
Software Configuration Management
WORK BREAKDOWN STRUCTURE
IEEE Std 1074: Standard for Software Lifecycle
[Project Name] Post-Mortem
S4 will be a “big” Collaboration:
PROJECT NAME POST-MORTEM
Project Management.
IS Project Management How to Close a TPM Project
Defining the Activities
Project Organization Chart Roles & Responsibilities Matrix
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
Preparations for a Lehman Review
NASA Independent Reviews -Lessons Learned-
PCC Update 01/27/2010 Planning Phase
COMP 208/214/215/216 Lecture 3 Planning.
AMICI WP1 – Management, coordination and dissemination
[Project Name] Post-Mortem Presentation Template
HART Technologies Process Overview
Project Name Post-Mortem
DOD’S PHASED SYSTEM DEVELOPMENT PROCESS
Overall Project RAG Status:
Effective Project Management: Traditional, Agile, Extreme
GEF Project Cycle Sub-Regional Workshop for GEF Focal Points
Project Management Techniques Project Management Life Cycle
Preliminary Project Execution Plan
Executive Project Kickoff
LCLS Instrument MIE Project: Staffing, Schedule
[Project name] [Presenter name]
By Wilmer Arellano Summer 2013
Information system analysis and design
Presentation transcript:

SCT Project Management Issues Rob Cameron KIPAC, SLAC rac@stanford.edu

SCT Project Office Organization As shown in the submitted MRI proposal to NSF Should add a Quality Assurance function later, during manufacture and testing

Management for CTA-US R&D It is not cost effective to implement a full project office during the SCT R&D, because of lower funding levels during the phase; so start with limited functions We should ramp up Project Management activities to be ready to support Prototype SC telescope construction Systems Engineering work can proceed in parallel to design work in the Design Phase Project Office can take on resource use and budget reporting task for smaller groups within collaboration

SCT and CTA Project Management SCT Project must maintain its own schedule Not consistent with CTA schedule and might it change But should track possible coordination of activities for resource sharing and cost savings SCT Project will have its own progress tracking and status reporting functions for the US funding agencies Try to avoid doubled reporting duties as much as possible SCT must have its own Systems Engineering support But coordinate closely with CTA Systems Engineering Look to having a common Document Control function as much as possible with CTA Project Look to having common QA and Change Control functions as much as possible with CTA Project

Near-term Project Office Tasks Several management tasks have early priority for the SCT R&D Development of WBS for CTA-US work Get agreement by all US partner institutions for specific work areas, and also re-collect resource data from each institution The degree of WBS management will be appropriate to size of groups within CTA-US Outputs generated while producing the WBS: Schedule: do more detailed task scheduling, plus identification of milestones. Also refine CTA-US schedule in comparison to overall CTA schedule. Deliverables: hardware items, documents, reports etc. Resources: Produce a Resource Allocation Matrix across WBS and groups Costs: Refine CTA-US R&D and Project cost estimates Implement a simplified resource and cost tracking process Avoid full Earned Value Management system in R&D phase because of reduced funding levels Implement status/progress reporting for the funding agencies

Project Management Infrastructure Needs Resource and cost tracking and reporting system Will be needed in Design Phase Will work with agencies to establish needed level of detail A Document Database and Document Control System Look to CTA Project for common use if possible Initially need to draft a Document Tree for the SCT Project Define required documents such as Specifications, Interface Control Documents etc for systems and sub-systems. Look at commonality and consistency of defined documents with CTA Project. Later: Change Control process To be in place at the time of the final design of the prototype

Backup Slides

Backup Slides

Project Office Roles and Responsibilities Project Scientist/Deputy Project Scientist Project Manager Systems Engineer IT Manager Administrative Support