Project Risk Management Execution FE302 Lesson 5 June 2015 Changed Conditions on Construction Projects.

Slides:



Advertisements
Similar presentations
Contract Disputes Can We All Get Along? Wendy E. Bryant Wendy E. Bryant.
Advertisements

Construction Contracting
CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension.
Contract and Grant Provisions and Administration Section 105 (Page 30) Title I The Act.
CARLIN LAW GROUP, APC Dispute Resolution Procedures Contract Claims Requirements Public Contract Code § (schools) Public Contract Code §20104 Government.
1. Among the most important advisors to a construction firm are: –Professional surety bond producer –Knowledgeable construction/surety attorney –Construction-oriented.
CONTRACT TERMS AND CONDITIONS--COMMERCIAL ITEMS ( ) (FEB 2007)
Presented By: John D. Miller
772 ESS Lesson Learned Briefing
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
OCR Payment Process Training 01/17/2012. Article 9 – Compensation and Payment General Conditions – Article 9 – 9.1 Preconstruction Stage Compensation.
Learn. Perform. Succeed. Protest, Claims, Disputes and Appeals Chapter 7.
Time for a new standard - AS General Conditions of Contract
Lao Contract and Tort Law (2008) Presented by: Santisouk Phounesavath Director of Multilateral Trade Division Foreign Trade Policy Department Ministry.
Project Close Out CTC-470.
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT Defects Liability [Construction Contract Administration] Chapter 11.
Construction Engineering 221 Contracts & Contractor Procurement.
1 341st CONS Home of the Two-Time AFSPC Top Dollar Champions! “Takin Care of Business”
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
CONTROLLING TIME. ”Remember that time is money” Benjamin Franklin 1748.
S10 CONS5Q25 Lara Tookey. Review of estimators workings Decision on what margin to apply Bid submission details Submit your Tender.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
SacProNet An Overview of Project Management Techniques.
CHANGE ORDER & BACKCHARGES PREPARED BY ABDULAZIZ M. AL-BESHR ID# PREPARED FOR Dr. ABDULAZIZ BUBSHAIT.
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
Rabbanai T. Morgan Current as of 26 January 2006 Protests.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Session 5 Elements of Uganda Model Management Contract for Water.
Project Closeout Module #14 Prepared by Dr. Randy R. Rapp July 2005.
Plans and Specifications Plans and specs are contract documents Defects in construction can be caused by design flaw (plans and specs were wrong) Defects.
CVE 4070 Construction Engineering Course Review Prof. Ralph V. Locurcio, PE.
DISTRICT CONSTRUCTION ENGINEER PANEL DISCUSSION Contract Management: Claim Avoidance and Handling Keith Compton, P.E. District 5 Construction Engineer.
CLAIMS MANAGEMENT. PRESENTATION OUTLINE INTRODUCTION TYPICAL CLAIMS AGAINST OWNER TYPICAL CLAIMS AGAINST CONTRACTOR CRITICAL PATH METHODS UTILIZATION.
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
UNIVERSITY OF DAR ES SALAAM t Selection and Employment of Consultants Negotiations with Consultants; Monitoring Performance of Consultants; Resolving Disputes.
CVE 4070 Construction Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
1 1 Effective Administration of Commercial Contracts Breakout Session # Session D06 Name: Holly Walker, CPCM Corporate Learning Solutions and Contract.
Helen S. Henningsen Department of Veterans Affairs Office of General Counsel.
HOW TO PROTECT YOUR INTEREST IN A SALE CONTRACT Focus on what you “get” when you sign!
CCA Adjudication Cashflow, or fair dispute resolution, or both? Opportunities for Improvement in the Act and adjudication procedure Peter Degerholm AMINZ.
Presented to: By: Date: Federal Aviation Administration Ready for Cost Type Contracts - Accounting Systems and Administration Small Business Vendor Day.
1 1 Contract Performance & Administration Breakout Session # XXX Andrew C. Obermeyer Tuesday, July 12, :30-3:45pm.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Amendments to the Public Works Contracts
TD Government Solutions
TD Government Solutions
FE 302 Lesson 5 Project Risk Mitigation
The Value of a Knowledgeable Construction/Surety Attorney
TD Government Solutions
CONTRACT ADMINISTRATION
FE 302 Lesson 5 Project Risk Management Execution
Administration of a FIDIC Contract - Project Control
EPA CONTRACT TEMPLATE Overview
Harpers Ferry Center Office of Acquisition Management August 2010
Administration of a FIDIC Contract - Financial Management
Changed Conditions on Construction Projects
EPA SUBCONTRACT TEMPLATE Overview September 2017
SIMAD UNIVERSITY Keyd abdirahman salaad.
Letter Contracts Rabbanai T. Morgan
Speaker: Sarah Chambers, Esq. Claims Counsel| Professional Liability
ARCH 435 PROJECT MANAGEMENT
Find the Problems with the Provisions May 11, 2016 Presented By:
Construction Contract Performance
Unique General Conditions of the Alabama Building Commission (ABC)
Construction Contract Administration
Grant Implementation Agreement (GIA)
Certified Cost or Pricing Data vs
Directed Change Constructive Change
Presentation transcript:

Project Risk Management Execution FE302 Lesson 5 June 2015 Changed Conditions on Construction Projects

Objectives Goal-Given a construction scenario, analyze project issues and formulate alternative responses. Identify assigned project issues. Analyze project issues in terms of impact to project cost, schedule, and performance. Utilize any pre-project initiation risk mitigation plan to complete full analysis. Recommend the project mitigation strategy to keep the project completion on track. Estimate through the remaining project duration any adjustments to the risk management plan.

What Causes Changes on Facilities Government Projects?

What Makes Construction Different? Latent/Patent Ambiguities Contract Interpretation Impact Costs Delays Defective Design Excessive Punch Lists Changed Work Conditions Constructive Acceleration Constructive Changes Over Inspection Superior Knowledge Inspection of Construction Invoicing, Retainage, Withholding FOOH and HOOH Extended OH, Unabsorbed OH Use and Possession Prior to Completion Turnover of Construction Warranties Performance Evaluations Waiver of Completion Date

FAR Changes Clause FAR (Fixed-Priced Construction >$150,000) Policy –Establishes authority to make changes within the general scope of the contract Purpose –Gives government flexibility and compensates contractor Highlights –KTR must give written notification to KO within 20 days of perceived change order –No adjustments after final payment

FAR Differing Site Conditions Clause FAR Policy –Requires KTR to notify GOV of any differing site conditions - promptly and before conditions are disturbed Purpose –Shift risk to GOV and eliminate bid contingencies Highlights –2 categories (Type I and Type II)

FAR Default Clause FAR (fixed-price construction) Policy –Allows GOV to terminate KTR who fails to complete the work –Allows KTR to receive time extensions for delays Purpose –Provides remedy for breach of contract Highlights –GOV can terminate for actual or implied breach –10-day notification requirement

FAR Default Clause FAR Limitations: –The government can’t default a contractor or assess LDs if the delay arises from unforeseeable causes beyond the control and fault of the KTR –Some examples are: Acts of God or public enemy Acts of the government Acts of another contractor Strikes Unusually severe weather Delays from subs and suppliers at any tier arising from unforeseeable causes beyond their control and that of the prime contractor

FAR Disputes Clause FAR –All disputes (and claims) that arise under the contract are resolved under this clause –KTR claims over $150,000 must be certified –KTR claims accrue interest from the date received by the KO –The KO must issue a decision: On claims less than or equal to $150,000 –- Within 60 days of receipt On claims greater than $150,000 –The KO must notify the KTR of the date which a decision will be made –The KO’s decision must inform the KTR of its appeal rights –Alternative Disputes Resolution is permitted

Request for Information (RFI)  RFIs are submitted by the general contractor who has question(s) about the contract’s terms and conditions and wants a government response.  RFIs can appear at any time, but most often:  At the preconstruction conference  At regular progress meetings  On a daily report (CQC or DRI) submitted to the COR  KO must respond in a timely manner or a constructive change might occur

Request for Equitable Adjustment (REA) Submitted by contractors, usually after submitting an RFI, who have encountered a perceived change to the contract, that is not authorized by the KO REAs usually include a request for money, time or both

Constructive Change Definition: Unauthorized change ordered by the government affecting scope of work, including money, time, or both

Differing Interpretations of the Contract Most Common Type of Constructive Change KTR & GOV’T Differ On What Is Required Order Element – GOV’T directs KTR to perform in accordance with GOVT interpretation Case Law Supports that KTR May Prevail If They have a Reasonable Interpretation

Whole Instrument Rule Express Language Rule Conduct of the Parties Knowledge of the Other Party’s Interpretation Prior Course of Dealings Rule Custom in the Trade Rule Miscellaneous Maxims Order of Precedence Rule Contra Preferentem INTENT RULESINTENT RULES MECHANICAL RULESMECHANICAL RULES Don’t Forget the Wild Card: The Duty to Inquire Rule The Hierarchy of Contract Interpretation

Defective Specifications “Protection for the Government” DFARS (b) Contract Drawings and Specifications  The Contractor shall:  Check all drawings immediately  Compare all drawings and verify before layout  Promptly notify the KO of discrepancies  Be responsible for any errors that might have been avoided by complying with above

Defective Specifications “Protection for the Government”  DFARS (d) Contract Drawings and Specifications  What about omissions from the drawings and specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications or that are customarily performed?  These situations: “shall not relieve the contractor from performing such omitted or misdescribed details of the work. The contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.”

Claim A claim is a written demand by one of the contracting parties seeking money, time, or both. Two Types of Claims: –Entitlement – Gov’t Disputes Right for Additional Compensation. –Quantum – Gov’t Considers Meritorious, But Not Agree On Amount

REA vs. Claim “A Claim is an REA but an REA is not Necessarily a Claim” Both can include direct costs, indirect costs, profit, and time. REAs: –The costs of preparing an REA (legal and accounting fees and negotiation expenses are allowable). –But interest is unallowable Claims: –The costs of preparing a claim and the prosecution of a claim are unallowable –But interest will accrue from the date submitted until the date of payment 18

Disputes Process

Alternative Disputes Resolution ADR is defined as “Any procedure or combination of procedures voluntarily used to resolve issues in controversy without the need to resort to litigation.” FAR

Lesson 5 Exercise Instructions: Your team will be given various issues which have arisen in your assigned project. Your task is to propose resolutions identifying and quantifying the impacts. You will also revisit your previously submitted RMP and determine if adjustments need be made Time: