MICE Spectrometer Solenoids Step IV running

Slides:



Advertisements
Similar presentations
K. Long, 18 April, 2015 Beam-line status — red sky at night?
Advertisements

Focus Coil Update Roy Preece / Tom Bradshaw / Mike Courthold STFC – RAL VC 17 th Jan 2013.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
OPTICS UPDATE Ulisse Bravar University of Oxford 3 August 2004.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 The Genoa Tracker Solenoids and their Contribution toward a New Design Michael A. Green Lawrence Berkeley National Laboratory and Pasquale Fabbricatore.
1. Optical matching in MICE Ulisse Bravar University of Oxford 2 June 2004 Constraints Software MICE proposal mismatch MICE Note 49 (September 2004, Bob.
1 Superconducting Magnets for the MICE Channel Michael A. Green Oxford University Physics Department Oxford OX1-3RH, UK.
12 March 2006NFMCC Meeting, IIT, Chicago1 Progress on the MICE Cooling Channel and Tracker Magnets Michael A. Green Lawrence Berkeley Laboratory.
1 Progress on the MICE Cooling Channel Magnets Michael A. Green Lawrence Berkeley National Laboratory 28 June 2005.
CMPB Alain Blondel 14 April STATUS OF MICE.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #26 University of California.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
MICE magnetic measurements Sequence of events and MICE hall movements Alain Blondel – 10-April 2012 revision from 13 December 2012.
Performance of the DZero Layer 0 Detector Marvin Johnson For the DZero Silicon Group.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
LQS01 Test Preparation and Test Plan LARP Collaboration Meeting 12 LBNL - April 8-10, 2009.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Spectrometer Solenoid Test Plan Workshop: Spectrometer Solenoid Overview Steve Virostek - LBNL February 17, 2012.
Electrical & Control Power Supplies Trevor Hartnett.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be Jun at IIT and the 19th at Fermilab right before the.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
1 Mice Collaboration Meeting CM28 Bankya Palace Spa Hotel, Sofia, Bulgaria 3 rd -8 th Oct 2010 Daresbury Laboratory Spectrometer Report Authors : Ian Mullacrane.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Power Supply System John Joseph LBNL Spectrometer Solenoid Controls & Monitoring Review Dec 11 th 2012.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
SPOKESMAN’S UPDATE K. Long Imperial College London/STFC.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
FC Status MPB 1/20 April 2014 OXFORDRALDARESBURY V. BlackmoreV. BaylissT. Hartnett J. CobbT. BradshawS. Griffiths W. LauM. CourtholdI. Mullacrane R. PreeceA.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
MICE Construction Project Update: SSs, PRY, Cavities, Tracker… 1MAP Friday Meeting – January 30, 2015 Alan Bross.
A Gallagher Oct 2015 Electrical Integration MPB October 2015.
Sextupole Single Coil Test Results Giovanni Volpini on behalf of the LASA Team Giovanni Volpini, CERN, 22 April 2015.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.
Progress on AFC Procurement T W Bradshaw Rutherford Appleton Laboratory Harwell Science and Innovation Campus Didcot, OX11 0QX, UK
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
S A Griffiths CM42 June 2015 Electrical & Control.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
Electrical Configuration and System Protection
MICE Absorber and Focus Coil Magnet – Test Results
K. Long Imperial College London/STFC
Instrumentation for status monitoring of SST-1 superconducting magnets
S. Feher MICE Magnet Readiness Review RAL, June 28th, 2016
Completion of the MICE-US construction project
Electrical & Control.
Spectrometer Solenoid Update
Project Manager’s Report + DC/MoM Report
MICE NEWS MICE VC 155 Next Collaboration meeting will be
Spectrometer Solenoid Fabrication Status and Schedule
Focus Coil Quench Detector
Presentation transcript:

MICE Spectrometer Solenoids Step IV running

MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully mapped. Cryogenic operation was very good. Both magnets had significant cooling headroom (SS2 more than SS1) SS2 (in upstream position of the beam line – SSU) has reached full operating current at RAL, but full training (soak, solenoid mode) has not been completed. Cryogenic headroom ~ 50% (3W) Vacuum excellent SS1 (in downstream position – SSD) had a M1 lead failure during training. Cryogenic headroom ~<25% (~1W) Vacuum excellent, but some issues if power feedthrough gets cold What is the path forward for Step IV? MICE CM March 31, 2016 RAL Alan Bross

Reminder: Basic design 5 2-stage CCs 1 single-stage CC 5 Coils Max current ~300A High inductance 10-40H M1 M2 E1 C E2 M1 in SSD Is DEAD MICE CM March 31, 2016 RAL Alan Bross

MICE CM March 31, 2016 RAL Alan Bross Power delivery system 2 Vacuum feedthroughs bring power into vacuum space One for ECE, one for M1 and M2 Copper leads to HTS IL/A = 3.6 X 106 A/m HTS: HTS-110 500A (M1, M2, C) and 250A E1 and E2 LTS: Vacuum feedthrough: Proprietary Wang design based on SSC superconductor Inside He space: Cu stabilized conductor MICE CM March 31, 2016 RAL Alan Bross

On 9/13/15 @1800 BST, SSD became Self-aware SS magnet protection and powering scheme after the September 13th, 2015 incident has been re-visited and, during the investigation process, it was realized that there are several problems in the protection and powering scheme that need to be addressed. Although there is no solution that will provide a perfect protection scheme, the existing one has been significantly improved upon. The improved protection scheme follows. MICE CM March 31, 2016 RAL Alan Bross

MICE CM March 31, 2016 RAL Alan Bross E-C-E Power system II MICE CM March 31, 2016 RAL Alan Bross

MICE CM March 31, 2016 RAL Alan Bross M1, M2 Power System II MICE CM March 31, 2016 RAL Alan Bross

External Dump Pack Resistors Centre Coil Resistor Trim Coil Resistor Match Coil Resistor MICE CM March 31, 2016 RAL Alan Bross

MICE CM March 31, 2016 RAL Alan Bross Operation During powering of the magnet circuits all the switches are closed. Several different scenarios can occur and the following actions will be taken: If magnet quench or ground fault on a circuit is detected: For all three circuits (M1, M2, E-C-E) the two main switches (primary and redundant) open – all together 6 switches open. If HTS or LTS quench occur: the External Dump Pack (EDP) switch of the circuit that experienced the lead quench opens. For E-C-E resistors located near magnet; M1 & M2 in RR2 In order to decrease the detection voltage threshold significantly the protection and monitoring scheme has changed: MICE CM March 31, 2016 RAL Alan Bross

MICE CM March 31, 2016 RAL Alan Bross Operation II A DCCT (direct-current current transformer) based current readout system was added to precisely measure the magnet current values and provide dI/dt signals for QPS: The “old” QPS still provides a quench trigger signal if any coil, HTS or LTS leads show resistive voltages. The protection scheme has changed: A dI/dt based protection (using the DCCT system) scheme with mutual coil balancing is used for SSD M2 and SSD E-C-E and for SSU M1 and SSU M2 circuits that monitors the magnet coil voltages; SSU E-C-E Half-Half coil based protection circuit threshold value was significantly lowered (by lowering the noise level of the circuit); An additional new protection layer (secondary) was added to the HTS and LTS protection scheme. It will produce a separate trigger for each circuit (M1, M2 or E-C-E) if HTS or LTS lead quench occur in that circuit. This trigger will be used to open the EDP for the circuit that detected HTS or LTS lead quench MICE CM March 31, 2016 RAL Alan Bross

MICE CM March 31, 2016 RAL Alan Bross Operations III NO additional individual “training” of either SSU or SSD is planed Obviously, we have not “trained” the channel: SSU-FC-SSD. Additional quenches must be assumed This presents the greatest risk to SSD because of potential damage to the power feedthrough for M1/M2 on SSD (vacuum to He space) Initial SSD operations limited to E-C-E MICE CM March 31, 2016 RAL Alan Bross

Fundamental issue with SSD M2 of SSD looks fine, but given that we do not know in detail the condition of this feedthrough, running first with M2 off is envisioned. However, any quench in SSD (from E-C-E) will produce a pressure pulse Has been checked once and feedthrough held (still vac tight). Next time…???? MICE CM March 31, 2016 RAL Alan Bross

MICE CM March 31, 2016 RAL Alan Bross Conclusions SSU is in good shape Magnetically Cryogenically Vacuum SSD not so much. M1 is not retrievable Cryogenic headroom OK, but worse Vacuum is fine The new PS/QD/QPS system will have a significant upgrade and will protect these magnets as well as possible (limited by the magnets intrinsic design). MICE CM March 31, 2016 RAL Alan Bross

MICE CM March 31, 2016 RAL Alan Bross Conclusions Installations of components, re-configuration of the QPS modules and finalization of the DCCT system input to the QD system is ongoing. Final install and initial commissioning is scheduled to begin on April 27th. A second round of work in May will be needed to full commission the SS PS/QD/QPS systems for full magnet operations. SSs ready in June for Step IV operations MICE CM March 31, 2016 RAL Alan Bross