TC CO July 28 2005 HCC report HCC report Summary of the tests of the LSS8L power converters in short-circuit F. Rodríguez-Mateos on behalf of R.Ballet-Thouble,

Slides:



Advertisements
Similar presentations
Hot Water Temperature Maintenance
Advertisements

(Adapted from:D.T. Hall:Practical Marine Electrical Knowledge)
Coil Design and Fabrication Miao Yu Outline Introduction Coil Design –Coil Pole –Coil End Parts –Coil Insulation Coil Fabrication –Winding.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
The following advertisement is created for the sole purpose of understanding the Commissioning process. The following advertisement is created for the.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Powering of the Superconducting Circuits: Procedures and Strategies for Circuit Validation Antonio Vergara on behalf of the Hardware Commissioning Coordination.
LHC Hardware Commissioning Review May 2005, CERN, 1211 Geneva 23 1 LHC Hardware Commissioning Review Contribution ID: 20 – Quality assurance and.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
Lesson 2 How do electric circuits work?. Electric Circuits You know that electric circuits only work when the circuit is closed. OPEN.
The organization and on-site follow up of the electrical installation work for the LHC The organization and on-site follow up of the electrical installation.
BA6 Cooling Towers Test Day Process Control Functionality and Performance Tests TCR – PCR Monitoring.
HC Review F. Rodriguez-Mateos Powering tests The outcome of the work conducted within HCWG and many discussions among colleagues.
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
Roberto Saban LEMIC Coordination of Hardware Commissioning  Sector 78 Cooldown Cooldown Powering Tests Powering Tests Test of software for the.
NERC Lessons Learned Summary LLs Published in September 2015.
Hardware Commissioning Tools Robin. AB-CO TC 8th February 2007Hardware Commissioning Tools - RJL2 Summary Hardware Commissioning View Slides from Antonio.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Review of Sector th of February Electrical Safety for the interventions during Hardware Commissioning of LHC Anne Funken, TS-ICC.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
SAFETY DURING HARDWARE COMMISSIONING, 18 October 2007, D. Bozzini, AT/MEL-EM 1 Safety during Hardware Commissioning Davide Bozzini on behalf of the ELQA.
[R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] HWC Workshop ( ) Consolidation and major changes that have impact on the powering circuits.
LINAC4 COMMISSIONING 1 LESSONS LEARNT DURING MY VISIT AT LINAC4 COMMISSIONING Evangelia Vaena, 02/02/2016.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
16-17 January 2007 Post-Mortem Workshop Logging data in relation with Post-Mortem and archiving Ronny Billen AB-CO.
AB/CO - TC – Cl.Deh. HT section 1 Lessons from Point 8 HW installation Better idea of Where, When and … What ! Periodic meeting (every 2 weeks)
Roberto Saban TS HC Review bis Outline  Interviews of all the Group Leaders loosely or tightly concerned by hardware commissioning proposing them.
R2E relocation & shielding LS1 preparation Anne Laure Perrot EN/MEF- LE Discussion with OP colleagues, 5 th July 2012.
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 1 Claude DEHAVAY - CERN/AB/CO/HT Installation Readiness Report - Controls.
Commissioning HVAC Systems: Lessons learned throughout
HC Review Follow-up – June 22 nd – 23 rd 2006 What has been going on in the field: a status report F. Rodriguez-Mateos, TS-HDO on behalf of the HCC Team.
TRD Gas System Layouts Production Readiness Review 03 – Nov F. Hahn.
Warm cabling, cooling and ventilation L. Tavian, ATS-DO On behalf and under the controls of SWP17.2 and SWP17.3 Conceptual Design Review of the Magnet.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
Pelletron status update Main Injector Departmental Meeting November 11 th, 2009 L. Prost.
CO 2 Cooling Plants for the LHCb upgrade LHCb infrastructure workshop February Burkhard Schmidt With input from Bart Verlaat, Paolo Petagna and Lukasz.
LHC Post Mortem Workshop - 1, CERN, January 2007 (slide 1/52) AB-CO Measurement & Analysis Present status of the individual.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
S A Griffiths CM42 June 2015 Electrical & Control.
LS2 Safety Preparation Thomas Otto, LS2 Safety Support Officer for LHC
Implementation of a MPC on a deethanizer
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K
R. Denz, A. Gomez Alonso, AT-MEL-PM
Minimum Hardware Commissioning – Disclaimer
Markus, Mathieu, Enrique, Rudiger, Serge
Safety in Construction and Upgrade Phases
SPS cryogenic proximity equipment and SM18 validation
How SCADA Systems Work?.
Powering from short circuit tests up to nominal
TEST PLANS for HL LHC IT STRING
Collimator Control (SEUs & R2E Outlook)
Implementation of a MPC on a deethanizer
PEAK’s RMTNET Tool Sarma (NDR) Nuthalapati, Principal NetApps Engineer
Overarching Commissioning Plan
Testing Plan and Status
Piping and Instrumentation for Process Industries
Workshop commissioning Installation Coordination at ESS
Testing Coordination at ESS
Brief report of the hardware commissioning activities
PSS verification and validation
Author Team Supervisor A. Toral M. Mansouri S.L. Birch Y.K. Sin
Hardware Commissioning
Powering and Safety day Underground access during powering tests
Review of hardware commissioning
Presentation transcript:

TC CO July HCC report HCC report Summary of the tests of the LSS8L power converters in short-circuit F. Rodríguez-Mateos on behalf of R.Ballet-Thouble, E.Barbero-Soto, F.Bordry, S.Brown, M.Cayla, P.Charrue, F.Chevrier, Ch.Coupat, PY.Collaud, C.Dehavay, JY.Dutoit, A.Foreste, E.Garde, JC.Guillaume, E.Hatziangeli, J.Iñigo-Golfín, Q.King, M.Lamont, R.Lauckner, E.Molina, B.Ocelli, S.Page, J.Pedersen, R.Saban, H.Thiesen, J.Thomsen, J.Wozniak

TC CO July Outline  Equipment under test configurations  Procedures  Main findings  Conclusions and outlook

TC CO July Q5 RQ5.L8B1 RQ5.L8B2 RCBCH5.L8B1 RCBCHS5.L8B1 RCBCHS5.L8B2 RCBCV5.L8B2 RCBCVS5.L8B1 RCBCVS5.L8B2 Q4 RQ4.L8B1 RQ4.L8B2 RD2.L8 RCBYH4.L8B2 RCBYHS4.L8B1 RCBYHS4.L8B2 RCBYV4.L8B1 RCBYVS4.L8B1 RCBYVS4.L8B2 XL8 RQX.L8 RTQX1.L8 RTQX2.L8 RD1.L8 RCBXH1.L8RCBXV1.L8 RCBXH2.L8RCBXV2.L8 RCBXH3.L8RCBXV3.L8 RQSX3.L8 RCOSX3.L8 RCOX3.L8 RCSSX3.L8RCSX3.L8 RCTX3.L8 [4kA/8V][5kA/8V] [±120A/±10V] [7kA/8V] [±120A/±10V] [±600A/±10V] Equipment under test courtesy H.Thiesen

TC CO July PC 18kV 400V Water UPS RCBYH4.L8B2 RCBYHS4.L8B1 RCBYHS4.L8B2 RCBYV4.L8B1 RCBYVS4.L8B1 RCBYVS4.L8B2 RCBCH5.L8B1 RCBCHS5.L8B1 RCBCHS5.L8B2 RCBCV5.L8B2 RCBCVS5.L8B1 RCBCVS5.L8B2 RCOSX3.L8 RCOX3.L8 RCSSX3.L8 RCSX3.L8 RCTX3.L8 RD1.L8 RD2.L8 RCBXH1.L8 RCBXH2.L8 RCBXH3.L8 RCBXV1.L8 RCBXV2.L8 RCBXV3.L8 RQSX3.L8 Power converters configurations (1) PC2 18kV 400V Water UPS PC1 RQ4.L8B1 RQ4.L8B2 RQ5.L8B1 RQ5.L8B2 courtesy H.Thiesen

TC CO July A4.7kA7kA I.T. En 18kV 400V FIP PIC Water Cal. UPS Chilled Water RQX.L8 RTQX1.L8 RTQX2.L8 Power converters configurations (2) courtesy H.Thiesen

TC CO July

ActionEquipment Group(s) Responsible 1The individual electrical feeder is unlocked and the converter is connected to the grid AB/PO TS/EL 2Tests to verify that the converter shuts down in case of loss of cooling water in the converter or in the cables and tubes AB/PO TS/EL TS/CV 3The converter is turned on and the control loop is tuned AB/PO 4Tests to verify the remote operation of the power converter via the WorldFip AB/PO AB/CO 58-hour heat runs at I ult carried-out with the converter connected to the Control Network AB/PO TS/EL TS/CV Procedures

TC CO July The findings  Cabling Thermal behaviour of cables is very sensitive to their arrangement on trays, ducts, transitions, etc. Corrections have been applied and validated Validation of optimized sections (240 and 35 mm2, respectively, for corrector circuits generically known as “600A”and “120A”): special attention to hot spots A more complete procedure for high voltage tests on water-cooled cables is required The crimped fittings on the flexible tubes of the water cooled cables must be insulated Indirect cooling of cables in the ducts: an alarm must be generated if the temperature exceeds a given value  Water cooling Setting and balancing of water circuits must be done before short-circuit tests start Scheme for three-cable circuits (Q4,Q5) will be changed  Reference Database: ultimate currents

TC CO July The findings (2)  Power converters Estimated times for the different phases are confirmed Contrary to what was initially specified, World-Fip has to be operational from the very beginning of the tests While the individual commissioning of the PC is done in situ, the field control room is really needed for the parallel testing during the 8-h heat runs The power terminals of one of the IT high-current converters seem to be too far apart  “Visites d’inspection” must be scheduled well in advance be documented in such a way that the different Groups see clearly the points which pertain to their systems be attended by the engineers responsible of each system also focus on a global system approach

TC CO July The findings (3)  Controls The sequencer – invaluable tool Logging – not really operational Alarms – not mature but ran solidly Fixed displays – running from the start but needs refinement e-logbook was missing Communication infrastructure – performed as expected  Control room Noisy environment, not easy to have discussions!  MTF has been operational from the first moment, and proves to be very useful and necessary IN THE FIELD

TC CO July Conclusions  It has been a successful start of the LHC HC  We have gathered plenty of valuable information that must be now documented and retrofitted: cabling controls converters cooling coordination environment inspections safety  We need to optimize preparations and procedures update the Reference Database (and drawings) update LHC-R-HCP-0001 refine the procedure for high voltage tests of water-cooled cables implement procedure for the water flow settings define procedure for the “visite d’inspection”

TC CO July Outlook  In September everything we have learnt will be applied to a larger scale i.e. the complete set of converters in UA83  Every finding, every non- conformity, every new lesson must be documented. HCC will follow it up  Everyone has shown great flexibility and collaboration spirit: we must keep it up!

TC CO July Ultimate currents