NSTX Team Meeting August 9, 2011 NSTX TF Update Team Meeting August 9, 2011 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto.

Slides:



Advertisements
Similar presentations
Potential Upgrades to the NBI System for NSTX-Upgrade SPG, TS NSTX Supported by Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U.
Advertisements

Study of tearing mode stability in the presence of external perturbed fields Experimental validation of MARS-K/Q and RDCON codes Z.R. Wang 1, J.-K. Park.
NSTX-U T&T TSG Contributions to FY15 JRT NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U.
Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U.
Development and characterization of intermediate- δ discharge with lithium coatings XP-919 Josh Kallman Final XP Review June 5, 2009 NSTX Supported by.
NSTX Team Meeting June 25, 2010 College W&M Colorado Sch Mines Columbia U Comp-X General Atomics INEL Johns Hopkins U LANL LLNL Lodestar MIT Nova Photonics.
Machine Installation and Construction Management Erik D. Perry Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318.
NSTX-U FWP 2015 Budget Planning Meeting-NSTX Upgrade Status- Ron Strykowsky – 4/10/ NSTX Upgrade Progress Overview Ron Strykowsky Erik Perry, Tim.
NSTX NSTX Team Meeting Jan. 3, 2013 NSTX Team Meeting Jan. 3, 2013 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu.
NSTX Team Meeting May 28, 2008 Supported by Office of Science College W&M Colorado Sch Mines Columbia U Comp-X General Atomics INEL Johns Hopkins U LANL.
Quality Assurance Readiness for Operations Review Judy Malsbury, Head of QA Princeton Plasma Physics Laboratory NSTX Upgrade LSB B318 December 9-11, 2014.
PCS Navigation D. Mueller January 26-28, 2010 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS.
ISTP (and other…) Update Stefan Gerhardt NSTX-U Monday Physics Meeting Feb. 20, 2015 B318 NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima.
EP-TSG session Meeting agenda et al. M. Podestà NSTX-U Research Forum 2015 EP-TSG session PPPL, Room B252 02/24/2015 NSTX-U Supported by Culham Sci Ctr.
Non-axisymmetric Control Coil Upgrade and related ideas NSTX Supported by V1.0 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U.
Current status of high k scattering system J. Kim 1, Y. Ren 2, K-C. Lee 3 and R. Kaita 2 1) POSTECH 2) PPPL 3) UC Davis NSTX Monday Physics Meeting LSB-318,
NSTX-U Collaboration Status and Plans for: Charged Fusion Product Diagnostic FIU Werner U. Boeglin Ramona Perez, Alexander Netepenko, FIU D.S. Darrow PPPL.
1 Update on Run Schedule R. Raman NSTX Team Meeting PPPL, Princeton, NJ, 08 February, 2006 Work supported by DOE contract numbers DE-FG02-99ER54519 AM08,
RF Operations: Commissioning the RF systems and antenna conditioning J. Hosea et al. NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima.
Supported by Office of Science Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U.
NSTX Supported by Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Hebrew.
Radiative divertor with impurity seeding in NSTX V. A. Soukhanovskii (LLNL) Acknowledgements: NSTX Team NSTX Results Review Princeton, NJ Wednesday, 1.
NSTX Team Meeting July 21,, 2011 NSTX TF Update NSTX Team Meeting July 21, 2011 NSTX Supported by Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima.
NSTX Effects of NTSX Upgrades on DiagnosticsFebruary 8, NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL Johns.
Prototype Multi-Energy Soft X-ray Diagnostic for EAST Kevin Tritz Johns Hopkins University NSTX-U Monday Physics Meeting PPPL, Princeton, NJ June 25 th,
Direct measurement of plasma response using Nyquist Contour Z.R. Wang 1, J.-K. Park 1, M. J. Lanctot 2, J. E. Menard 1,Y.Q. Liu 3, R. Nazikian 1 1 Princeton.
NSTX-U Program Update J. Menard NSTX-U Team Meeting B318 May 7, 2013 NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto.
Second Switching Power Amplifier (SPA) Upgrade Physics Considerations Discussion S.A. Sabbagh 1, and the NSTX Research Team 1 Department of Applied Physics,
ASC Five Year Plan Chapter Status Stefan Gerhardt NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu.
NSTX Upgrade Project – Final Design Review June , NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL.
1 R Raman, B.A. Nelson, D. Mueller 1, T.R. Jarboe, M.G. Bell 1, J. Menard 1, R. Maqueda 2 et al. University of Washington, Seattle 1 Princeton Plasma Physics.
Xp705: Multimode ion transport: TAE avalanches E D Fredrickson, N A Crocker, N N Gorelenkov, W W Heidbrink, S Kubota, F M Levinton, H Yuh, R E Bell NSTX.
NSTX-U Construction Erik Perry Princeton Plasma Physics Laboratory NSTX Upgrade Readiness to Operate Review LSB B318 December 9-11, 2014 NSTX-U Supported.
Development of Improved Vertical Position Control S.P. Gerhardt, E. Kolemen ASC Session, NSTX 2011/12 Research Forum Location Date NSTX Supported by College.
1 Roger Raman for the NSTX Research Team University of Washington, Seattle NSTX Run Usage 27 February – 5 May, 2006 NSTX Mid-Run Assessment PPPL, Princeton,
NSTX Upgrade Project – Final Design Review June , NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL.
NSTX-U Collaboration Status and Plans for: X Science LLC Ricky Maqueda NSTX-U Collaborator Research Plan Meetings PPPL – LSB B318 April / May 2014 NSTX-U.
NSTX Upgrade Project – Final Design Review June , NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL.
Some Halo Current Measurements in 2009 S.P. Gerhardt Thanks to: E. Fredrickson, H. Takahashi, L. Guttadora NSTX Results Review, 2009 NSTX Supported by.
NSTX Upgrade Project – Final Design Review June , NSTX Supported by Vacuum Pumping, Gauging and RGA Systems W. Blanchard Princeton Plasma.
Safety Jerry Levine Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318 May 2 - 3, 2012 NSTX-U Supported by Culham.
NSTX Team Meeting February 7, 2007 Supported by Office of Science College W&M Colorado Sch Mines Columbia U Comp-X General Atomics INEL Johns Hopkins U.
Development and characterization of intermediate- δ discharge with lithium coatings XP-919 Josh Kallman XP Review - ASC Feb 2, 2009 NSTX Supported by College.
NSTX-U Collaboration Plans for UCLA PI: Neal A. Crocker Co-PI: Prof. Troy Carter Grad. Student (planned 2 nd year onward) PPPL Research Contacts and Collaborators:
NSTX Team Meeting December 21, 2009 College W&M Colorado Sch Mines Columbia U Comp-X General Atomics INEL Johns Hopkins U LANL LLNL Lodestar MIT Nova Photonics.
Effect of 3-D fields on edge power/particle fluxes between and during ELMs (XP1026) A. Loarte, J-W. Ahn, J. M. Canik, R. Maingi, and J.-K. Park and the.
NSTX-Upgrade Magnetics And Related Diagnostics SPG NSTX Supported by Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu.
NSTX NSTX Team Meeting May 7, 2013 NSTX Team Meeting May 7, 2013 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu.
First results of fast IR camera diagnostic J-W. Ahn and R. Maingi ORNL NSTX Monday Physics Meeting LSB-318, PPPL June 22, 2009 NSTX Supported by College.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
NSTX NSTX TF, PF and umbrella Upgrade Internal ReviewFeb 24, NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL.
NSTX NSTX LidsJuly 6, NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL Johns Hopkins U LANL LLNL Lodestar.
NSTX Team Meeting June 30, 2009 College W&M Colorado Sch Mines Columbia U Comp-X General Atomics INEL Johns Hopkins U LANL LLNL Lodestar MIT Nova Photonics.
NSTX Team Meeting December 4, 2008 College W&M Colorado Sch Mines Columbia U Comp-X General Atomics INEL Johns Hopkins U LANL LLNL Lodestar MIT Nova Photonics.
Supported by Office of Science NSTX S.M. Kaye, PPPL ITPA PPPL 5-7 Oct Confinement and Transport in NSTX: Lithiumized vs non-Lithiumized Plasmas Culham.
Planning for Toroidal Lithium Divertor Target for NSTX and Supporting Experiments on CDX-U/LTX R. Kaita Boundary Physics Science Focus Group Meeting July.
Upgrades to PCS Hardware (Incomplete) KE, DAG, SPG, EK, DM, PS NSTX Supported by Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo.
NSTX 2007 MHD XP Review – J. Menard 1 Optimization of RFA detection algorithms during dynamic error field correction Presented by: J.E. Menard, PPPL Final.
Presently Planned Vacuum-Side Diagnostics for the NSTX-Upgrade Center Column NSTX Supported by Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima.
XP-945: ELM Pacing via Vertical Position Jogs S.P. Gerhardt, J.M. Canik, D. Gates, R. Goldston, R. Hawryluk, R. Maingi, J. Menard, S. Sabbagh, A. Sontag.
NSTX NSTX Team Meeting –Masa Ono May 1, 2015 NSTX-U Team Meeting May 1, 2015 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto.
Preliminary Results from XP1020 RFA Measurements J.W. Berkery Department of Applied Physics, Columbia University, New York, NY, USA NSTX Monday Physics.
NSTX NSTX Team Meeting –Masa Ono August 15, 2014 NSTX-U Team Meeting August 15, 2014 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo.
NSTX-U Collaboration Status and Plans for: M.I.T. Plasma Science and Fusion Center Abhay K. Ram, Paul Bonoli, and John Wright NSTX-U Collaborator Research.
Monitoring impact of the LLD Adam McLean, ORNL T. Gray, R. Maingi Lithium, TSG group preliminary research forum PPPL, B252 Nov. 23, 2009 NSTX Supported.
Comments on HC Measurements for NSTX- Upgrade SPG CS Upgrade Meeting 11/2/11 NSTX Supported by Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima.
Neutron diagnostic calibration transfer XMP D. Darrow and the NSTX Research Team XMP & XP review meeting Control Room Annex June 11, 2015 NSTX-U Supported.
NSTX Team Meeting April 5, 2006 Supported by Office of Science College W&M Colorado Sch Mines Columbia U Comp-X General Atomics INEL Johns Hopkins U LANL.
XP-950: XP-950: Dependence of metallic impurity accumulation on I p and the outer gap in the presence of lithium deposition S. Paul, S. P. Gerhardt are.
NSTX NSTX Upgrade Project – Final Design ReviewJune 22-24, NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL.
Presentation transcript:

NSTX Team Meeting August 9, 2011 NSTX TF Update Team Meeting August 9, 2011 Culham Sci Ctr U St. Andrews York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Hebrew U Ioffe Inst RRC Kurchatov Inst TRINITI NFRI KAIST POSTECH ASIPP ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Nova Photonics New York U ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Washington U Wisconsin NSTX Supported by

NSTX Team Meeting August 9, Time: 1:00 ~ 2:30, August 9, 2011 Place: LSB 318, PPPL TF Update (40 minutes) Engineering Operations Update (10 minutes) Research Operations Update (10 minutes) Project / Program Items (30 minutes) NSTX Team Meeting Agenda

NSTX Team Meeting August 9, TF Bundle Lifted Without Breaking High Vacuum July 25 - Disassembled lower TF hub for further examination July 26 – Decided to remove TF bundle out for better examination and formulation of repair strategy July 28 – TF bundle lifted out of NSTX in to the stand in the South High bay area without disturbing high vacuum. August 1 – Present focus is to pinpoint the shorted location by electrical and borescopic measurements No additional visible damages observed on the inner TF bundle

NSTX Team Meeting August 9, 2011 TF Bundle Placed in Its Stand on July 28 The NSTX TF center bundle was removed and placed in its stand in the south high bay area. Cleaning and inspections are in progress so we can develop a repair plan. E. Perry

NSTX Team Meeting August 9, 2011 Damaged TF Area (7/29/2011) The damaged TF area after the TF bundle is placed in the stand. The blackened lead is the TF #13. The short appears to be internal. TF Bundle Before Installed on NSTX

NSTX Team Meeting August 9, 2011 Inner TF Bundle Turn Designation NORTH ~ 1 Ω short among TF #30, TF # 13 and TF # 14 Maximum voltage can be minimized for the affected turns by clocking TF Maximum voltage drop ~ difference in the # times 30V TF is connected to a 1 kV supply. ~ 500 V can be applied between #30 and #13 but only ~ 30 V between # 13 and #14.

NSTX Team Meeting August 9, 2011 Inner TF Bundle Electrical Test Indicates a Short at ~ 2 Feet From the Bottom

NSTX Team Meeting August 9, 2011 TF Bundle Short Located by Electrical Measurement: –Electrical short involving TF # 13, 14 and 30 located ~ 2 feet from the bottom. –Borescope measurement being performed to internally examine the location of the short – melted solder must be removed. –The location is where the general stress level is relatively low. PF 1A and PF 1B effect being investigated TF Bundle Electrical Short Location

NSTX Team Meeting August 9, 2011 The location of the short (2 feet up from the joint) preclude a possibility of quick repair: –The shorted TF bars will need to be repaired. –The bar will need to be removed from the bundle. –Spare conductor bars were located which would give us some additional options such as preparing the replacement bars in parallel with the TF short investigation and the damaged conductor removal. An external team of experts will be invited to advise on the TF fault and the TF Upgrade Design once sufficient information is gathered. If the TF repair is determined to take too long, we may revise our upgrade strategy. –The upgraded TF design to reflect what we learned best we can. –By starting the outage early, we maybe able to start up the upgraded machine that much sooner in FY The TF Repair Will Not Be Quick

NSTX Team Meeting August 9, 2011 –TF conductor length increases ~ 0.6 cm during the pulse due to the temperature rise from ~ 12 °C to ~ 80°C. –If we take out turns, those turns would not grow causing the sheering force between them and the conducting turns resulting in possible turn-to-turn insulation failure. –It is also not clear what can be gained from the de-rated operation (lower and shorter TF pulses). –If we put back the TF bundle as is and operate it, this has its own risks and it also prevents further examination of the bundle. Should we run with de-rated TF? It is not easy.

NSTX Team Meeting August 9, 2011 We will look for options to repair the TF coil while investigating the cause of fault. –We need to find the cause and if possible repair the coil as soon as possible. –We also need to take advantage of this down time to make as much progress as possible on the Upgrade Project. NSTX Research Team: –Complete whatever you need to do on the machine such as commissioning etc. –Please take your long over due vacations! –Continue analyzing data for publications and meetings assuming no new data (e.g., APS) NSTX Engineering Team: –TF failure diagnose and repair will be pursued at highest priority. –Machine will be kept under high vacuum for the time being. –Tasks which benefit the Upgrade Project get high priority. Let us make the best of the situation

NSTX Team Meeting August 9, 2011 OH/TF Manufacturing Area The Inner TF/ OH fabrication will occur at PPPL in the CS High Bay area (Former NCSX Test Cell) Crane capacity (45 T), environmental control and adequate work space 12 Setup for Inner TF Bundle

NSTX Team Meeting August 9, 2011 Present TF bundle (Diameter is ~ ½ of the Upgrade TF) Upgraded TF bundle Upgraded TF Have Much Improved Design Complicated two layer design Complicated cooling water path 3/16” refrigeration cooling tube B-stage insulation Identical simple conductors Simple straight cooling water path 3/8” K-type straight copper tube More robust VPI insulation

NSTX Team Meeting August 9, ES&H Issues (J. Levine) Even though we are now in a stand-by mode, your safety is still highly important wherever you maybe. Have fun vacationing but please keep the safety in mind for you and your family. We just had a tragic bicycle accident of our dear colleague who had decades of riding experience. Safely, Safely, Safely