Proton Plan PMG 7/27/06 J. Sims 1 Proton Plan Cost and Schedule Report Jeff Sims.

Slides:



Advertisements
Similar presentations
PIP Update Oct Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken Domann.
Advertisements

Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys.
Presented by: Kreg McCall. Baseline Management & Control Define Baseline Baseline Types How to Generate a Baseline Baseline Setup for Success Baseline.
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
Project Management Methodology Project monitoring and control.
W. Freeman, D0 PMG 25-Feb-03 1 Run IIb Schedule Status u Schedule Status u Update on near-term equipment expenditures u Budgeting Update u Summary.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Trish Mast External Independent October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Delivery Ring AIP Jerry Annala Dec 12, µ Scope Beam line aperture improvements Beam line aperture improvements Beam line power supply upgrades Beam.
Microsoft Project Association Building an EV System using MS Project (and Excel) Kirsty C. McLean, MBA, PMP Project Controller, Photonics Division General.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Run II PMG 2/16/06 Martens/Sims 1 Run II Upgrades Status February 2006.
PIP Update June 3 rd Agenda Summary Update – Current Activities – Updates Ken Domann – Budget & Schedule Ryan Crawford – Anode Supply Update – Additional.
Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011.
Proton Study Meeting 4/19/05 Eric Prebys 1 Proton Plan Stage I Eric Prebys.
PIP FY14 PMG W. Pellico 7/8/14 7/8/2014PIP PMG. PIP Activities RIL & Linac – 200MHz RF Power System High Level RF Linac Modulator 7835 Procurement – Accelerator.
PIP PMG Project Controls Elmie Evans-Peoples PIP PMG Oct 25, 2012.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Review Context and Purpose Selection of OMT Design for the EVLA X-band Receiver Mark McKinnon EVLA Project Manager.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken.
Director’s Review 5/5/03 Spalding DRAFT RLS 1 Project Planning  Documentation to DOE June 1  DOE Review ~July 22 Documents Summary Project Overview,
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 1 Five Ways to Build a Microsoft Project Schedule Lynn Frock, PMP Phone
PIP FY15 PMG W. Pellico PIP PMG March 5 th PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.
1 BROOKHAVEN SCIENCE ASSOCIATES CF FY09 Work Plan & Schedule Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11, 2009.
PIP Budget Codes Budget FY12 Updates October 19, 2011 PIP Meeting.
Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
Proton Planning – Major Projects, Schedule, Decisions, and Projections Eric Prebys FNAL Accelerator Division.
Proton Plan PMG 2/23/06 E Prebys 1 Proton Plan Status January Report Eric Prebys.
Proton Plan Expectations Eric Prebys AD/Proton Source.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Proton Improvement Plan (FY13 PMG Q3). William Pellico, Fermilab PMG, Aug PIP FY13 Q3 Summary Task Highlights Budget and Labor Review Summary.
Run II PMG 1/19/06 Pushpa Bhat 1 Run II Upgrades Status January 2006 Pushpa Bhat.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Summary Director’s Review August 2006 Eric Prebys.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
Proton Plan PMG 5/25/06 David Harding Booster Correctors Status and CR David Harding.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Tracking a Project Plan A Case Study. Life Cycle of a Plan  Project Sized  Project Estimated  Project Planned Budget Schedule  Project Tracked.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Answers to Questions Director’s Review August 2006 Eric Prebys.
Proton Plan Eric Prebys, FNAL Accelerator Division.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Proton Plan PMG 4/18/05 E Prebys/J. Sims 1 Proton Plan Status March Report Eric Prebys Jeff Sims.
Where Module 04 : Knowing Where the Project Is 1.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
PIP Update August 12 th Agenda Summary Update Current Activities Update – Ryan Crawford - Booster Anode Power Supplies – Dave Johnson - Laser Notcher.
PAC Meeting, December 12, Prebys 1 The Problem.
Proton Plan 1/10/07 E Prebys 1 Proton Plan Meeting Agenda:  Project/campaign reorganization: Prebys  Status updates: all  Booster Water Proposal: Cooper.
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
Lab-Wide Earned Value Management System Project Core Team Meeting July 10, 2008 Dean. Hoffer / Elaine McCluskey.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
CNGS Review 15 July 2003 M. Meddahi1 EVM for CNGS Definitions Pre-requisites Application to CNGS.
Linac Coherent Light Source (LCLS)
Presentation transcript:

Proton Plan PMG 7/27/06 J. Sims 1 Proton Plan Cost and Schedule Report Jeff Sims

Proton Plan PMG 7/27/06 J. Sims 2 Milestones to End of 2006 Legend Forecast Date – Complete Date- Baseline Date -

Proton Plan PMG 7/27/06 J. Sims 3 Project Reviews Director’s Review – August 15, Planning

Proton Plan PMG 7/27/06 J. Sims 4 Critical Path Analysis to the end of 2006

Proton Plan PMG 7/27/06 J. Sims 5 Earned Value Descoped Thales Prototype Facility Descoped Off Project

Proton Plan PMG 7/27/06 J. Sims 6 EV Analysis M&S Cost and Schedule Variance.  – Linac PA vulnerability (+517k CV) 3 Proton Plan Spares were sold to Proton Source as operational tubes. This $ may be needed to procure operational spares. Labor Cost and Schedule Variance.  – Linac Quad Power Supplies (-61k SV) Design efforts suffered from shutdown activities. We hope to get back on track over the next few months.  – Linac Low Level RF (-121k SV) Modeling and design efforts suffered from shutdown activities. We hope to get back on track over the next few months.  – Booster Correctors (-77k CV) We may have underestimated the average hourly rate of the TD technicians doing the Prototype work. We are working with TD to understand if we need to revise the Tech SWF for the Correctors prototype effort.  – MI RF Upgrades (-131 SV) Lack of adequate RF resources over the last 3 months have caused this task to slip. Now that the shutdown is over RF resources have been assigned and are moving forward on this work.

Proton Plan PMG 7/27/06 J. Sims 7 M&S Cost Performance

Proton Plan PMG 7/27/06 J. Sims 8 Effort for June ‘06 Variance Notes: *Based on June 2006 Status Update 1 1.Booster Correctors Prototype – A substantial increase in effort on Booster Correctors Prototype occurred in May and June.

Proton Plan PMG 7/27/06 J. Sims 9 Change Request Log Ready for Signature

Proton Plan PMG 7/27/06 J. Sims 10 CR-14: 30 hz Harmonic Descope (Ready for Signature)  S cope: Descope Subproject SWF Increase = -$448k M& S Increase = -$1,083k Schedule Impact = No Class A MS impacted CR-17: Corrector System AIP Replan (Ready for Signature)  S cope: Move SS BC out to FY07 Start SWF Increase = $14k M& S Increase = $11k Schedule Impact = No Class A MS impacted CR-18: Thales Prototype Facility Descope (Ready for Signature)  S cope: Descope Subproject SWF Increase = -$521k M& S Increase = -$1,577k Schedule Impact = No Class A MS impacted Pending Changes 1 of 2

Proton Plan PMG 7/27/06 J. Sims 11 Pending Changes 2 of 2 CR-19: MI Collimators Procurements (Ready for Signature)  S cope: Move Procurements out to October 2006 SWF Increase = $0k M& S Increase = $10k Schedule Impact = No Class A MS impacted SSBC and MI Collimator Replans 1) Moves $1,777,741 from FY06 to FY07 (goes back to 2 nd floor held contingency to be held for FY07 use) 2) Adds $ 14,991 in escalation (Increases FY07 M&S budget need) 30 hz and Thales Descoping 3) Reduces FY06 M&S need by $25,725 (Can be used for AD EQ Booster SS RF) 4) Reduces FY07 M&S Budget needs by $2,635,435 plus $1,558,000 related contingency ($4,193,435). So in total the impacts are: Net to go back to Fy06 2 nd floor held contingency (1) = $1,777,741 Net Decrease in FY06 Budget need (3)= $25,725* Net Decrease in FY07 M&S budget need (4-2) = $4,178,444* *Planned to be AD M&O for Booster SS Replacement efforts