1 Tracking a Project Plan A Case Study

2 Life Cycle of a Plan  Project Sized  Project Estimated  Project Planned Budget Schedule  Project Tracked

3 Constituents of a Plan  Schedule Duration by WBS Task Project Start (or end) Constraints (Internal/External)  Budget Assigned Resources to Tasks

4 Plan  Schedule  +  Budget  =  Plan

5 Project Plan  Sized Appropriate Units of Size (SW: KSLOC)  Estimated Duration Effort  Scheduled WBS Assignment of Resources

6 Project Tracking and Oversight  Data Collection  Forecasting  Reporting  Eliminate Variances

7 Taxonomy/Artifacts  Tasks  Resources  Assignments (Task + Resource)  Work  Duration  Summary Tasks (Titles)  Tasks (Imperative Mood and Unique)  Constraints (Internal/External/Calendar)

8 Data Collection Methods  Using Project Web Access (PWA)  Methods Hours/day % Complete* Total Hours *Note: “% Complete” NEQ to “% Work Complete”

9 Chosen Method  Hours/day/Resource Hours Worked Remaining Work  Notes (Other data Supplied) Unplanned/Planned Work interruptions Unplanned/Planned Delays Other pertinent information

10 Data Collection Process  Resource Using PWA, enters  Hours worked, Remaining Hours Sends update to PM via PWA*  PM (or representative) Updates Plan *Note: Automatic e-mail notification occurs

11 Forecasting  Computes new Forecast  Publishes update* *Note: Automatic e-mail notification occurs

12 Reports Out  Prepares and Distributes Reports* *Note: Automatic e-mail notification occurs

13 Elimination of Variances*  Critical Path mandatory; others voluntary  Add resources  Change Scope  Change Baseline *Notes: Qualified by Criticality Must eliminate negative schedule variances; positive are voluntary Must eliminate positive cost variances; negative are voluntary

14 Add Resources  Reassign  Procure additional Comes from Reserve or Requires Change Board Action or Obtain from Reserve

15 Change Scope  Change Baseline Duration and/or Baseline Work Requires Change Board Action if affects overall contract cost and/or schedule Requires Change Board Action if Contracted functionality is changed

16 Change Baseline*  Cost or Schedule Cost  Take from Reserve  Reallocate Schedule  Reduce Slack  Change constraints *Note: These changes do not affect the Contract provisions aka scope of the contract

17 Settings for PWA  Resources are in the Resource Pool; i.e. have User Account  PM has Client/Server account on the Project Server  Options set  Method selected

18 Resource Accounts  Required Windows Authentication  Had e-mail address entered  E-mail server identified in Project Server  Hourly cost set Set to $1, then costs are hours

19 Project Options  Schedule Options  Calculation Options  Collaborate Options  Save Options  Published Fields  Timesheet View  E-Mail Notification

20 Schedule Options

21 Calculation Optons

22 Collaborate Options

23 Save Options

24 Set Published Fields

25 PWA Tracking Settings (1)

26 PWA Tracking Settings (2)

27 Timesheet View

28 E-Mail Notification

29 Other Considerations  Server is implemented  Sharepoint is initialized  Permissions are set appropriately  Security is set appropriately  Views are arranged  Server Configuration is set

30 Other Methods  IPT Lead Reports  Earned Value Methods  Schedule Only

31 IPT Lead Reports  Make the IPT Lead the Resource on the Tasks  Set data to be collected: Start and finish dates only + Remaining Hours/Duration or Total hours only + Remaining Hours or % Complete + Remaining Hours/Duration

32 Earned Value Methods  Set Tasks to use “Physical % Complete”  Resources report only Actual Starts, Finishes and Remaining Duration

33 Schedule Only  Collect only Remaining Duration