Project Management What are businesses trying to achieve by using Operations Management? (done on AS) EFFICIENCY.

Slides:



Advertisements
Similar presentations
Lecture Network Analysis
Advertisements

464 Lecture 09 CPM Revision. Scheduling Techniques r The scheduling techniques are î To plan, schedule, budget and control the many activities associated.
Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.
 Chapter 6: Activity Planning – Part 1 NET481: Project Management Afnan Albahli.
Productive Efficiency
D1: Critical Events And Critical Paths. D1: Critical Events And Paths A critical path is the list of activities on an activity network that, if they are.
Scheduling The Project  Scheduling Planning, budgeting and scheduling are all part of the same process Planning a project, developing a budget for it,
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
CS3500 Software Engineering Project Management (1) In 1986 one well-known software engineer (Tom DeMarco) made the simple but important observation: “You.
Manjari Akella Pranava Nagpal B-Tech(CSE) 4 th Year.
Welcome to your final year at school! Introductions.
5.8 Project Management Chapter 37 HL - Only.
Operations Management
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
1 Operations Management Lesson 5 Project Management.
ISP-2010 Network Evaluation & Analysis ISP Project Management.
Module 5 – Networks and Decision Mathematics Chapter 24 – Directed Graphs.
Monitoring and Control
Project Time Management
Business Studies Grade 11.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
System Analysis & Design Chapter V: Information System Planning 1.Introduction Nowadays, Information Systems plays the main role in success or failure.
PROJECT MANAGEMENT Syllabus Outcomes : Construct and interpret a network, identify the critical path, and calculate the free and total float. Evaluate.
5.1 Principles of Project Management. So what is Project Management? Definition: Is the process of planning, organizing, and managing tasks and resources.
University of Sunderland COM369 Unit 8 COM369 Project Monitoring and Control Unit 8.
Chapter 6: Project Time Management
MODULE 5: OPERATIONS MANAGEMENT UNIT 5.8 – PROJECT MANAGEMENT
A brief summary of Critical Path (or network) Analysis Critical Path Analysis is a way of planning complex projects. It allows one to find those parts.
IB Business and Management 5.8 Project Management (Critical Path Analysis)
Topic 5.8 ( only HL ) IB Business & Management Project Management Mr L Greenbank 1.
O PERATIONAL S TRATEGIES O PERATIONAL S TRATEGIES : L EAN P RODUCTION “Do not wait; the time will never be just right” Napoleon Hill “The clock not the.
Geog 469 GIS Workshop Project Management.
Project Management Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Business Department Session 6 Exam Question –Draw Network diagram –Identify Critical path –Sketch Gantt Chart –‘Crash’ the project Reduce the project completion.
Project Management “Project Planning & Scheduling”
Critical Path Analysis. Planning and Monitoring Tool.
PROJECT MANAGEMENT Approaches
11/02/09 Chapter 7-Project Planning 1 Elements of Project Planning  Divide project into tasks, tasks into subtasks, subtasks into...  Estimate duration.
PROJECT PLANNING AND SCHEDULLING
PROJECT MANAGEMENT Approaches By- Rahul Jain. Plan your work first…..then work your plan.
Lecture 61 Project planning tool Lecture 62 Objectives Understand the reasons why projects sometimes fail Describe the different scheduling tools, including.
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
Operational strategies Lean production. The adoption of techniques that help to reduce waste.
Dr. Hany Abd Elshakour 2/18/ :27 PM 1. Dr. Hany Abd Elshakour 2/18/ :27 PM 2 Time Planning and Control Activity on Arrow (Arrow Diagramming.
A2 Operations Management Critical Path Analysis. How long will it take? n Walls have decided to launch a new Magnum ice cream. Machine delivery will take.
INVENTION, INNOVATION AND DESIGN Invention: A new way of making a product (e.g. walkman) or process (e.g. spray painting). Inventions usually come from.
Critical Path Analysis - Worksheet
Net work Analysis/Critical Path Analysis (L1) Learning Objective – Understand CPA Learning Outcomes - By the end of the lesson students should be able.
Critical Path Analysis. Starter – The Big Breakfast! On Saturday, I want to cook myself a big breakfast.I want to have some toast, scrambled eggs and.
Network planning models These project scheduling techniques model the project's activities and their relationships as a network. In the network, time flows.
First name ??? ist auf Englisch. Critical Path Analysis.
Lean Production: Critical Path Analysis 3.15 Lean Production Objectives; Understand the key requirements of critical path analysis (CPA) Understand the.
Copyright 2006 – Biz/ed Critical Path Analysis.
Critical Path Analysis (CPA)
Critical Path Analysis
ECE362 Principles of Design
Critical Path Analysis
Project Scheduling Lecture # 1.
Critical Path Analysis (CPA)
Activity Planning.
Welcome to your final year at school!
SE Tasks for a Concept Development Project
Activity on Node Approach to CPM Scheduling
PROJECT MANAGEMENT (BSBI 622)
Project Planning By Phaik San Liew.
Importance of Project Schedules
Critical Path Analysis
Critical Path Analysis
Have a think…! What process do you need to go through to make bread or redecorate your bedroom? Are there any activities that could be done at the same.
Presentation transcript:

Project Management What are businesses trying to achieve by using Operations Management? (done on AS) EFFICIENCY

Critical Path Analysis  Trying to plan the most efficient way to completing a sequence of jobs.  E.g. a building project. What jobs could be done whilst the walls are being built?

Define a “Project”  A specific and temporary activity  A starting and ending date  Clear goals  Defined responsibilities  A Budget What organisational structure is best suited to a project situation?  MATRIX Structure PROJECT MANAGEMENT: Using modern management techniques to carry out the project

What are the 4 major elements to be managed in a project?  Resources – people, equipment, materials  Time – each activity will take different durations  Money – budget and profit  Scope – scale of the project and specific objectives set

Key elements of Project Management are:  Project Definition – clear objectives for all  Division of project tasks – it needs to be manageable  Control – specific stages or timelines – is the project being done according to timetable  Clear and defined roles for team members  Control – quality and risks

Poor project management will result in:  Increased costs  Penalty payments to customers  Bad PR  Loss of future business Reasons for project failure? Poor Management Poor planning Poor communication Lack of customer involvement Complacent management Lack of skills from team members Lack of funding/resources

So, how do you get it right? Planning Operations... All resources need to be planned for efficiently in terms of time needed, quantity required and staffing to ensure particular elements of a job are done on time... You want to avoid idle staff (costs) and machinery (maintenance) Stocks left lying around could take up space and become damaged Project Management is about keeping your assets busy!

Feature of CPA  NODES– represent a point in time.  They are split into 3:  Number of the node  Earliest start time (EST)  Latest finish time (LFT)

Features of CPA ctd.  Activities – tasks that take place, they consume time. They link the nodes.  Duration – the length of time that it takes to complete an activity  Prerequisite – the task or tasks that need to be completed before another task maybe completed.  Dummies – Tasks that do not consume time but are shown in a network to demonstrate the true sequence of events. EST – the earliest time each activity can begin, taking into account the preceding activities LFT – the latest an activity can finish without delaying the whole project

Node Node number A B Activity A: prerequisite of B EST of B Duration of activity B LFT of B

Constructing a network Diagram ActivityPrerequisite (s) A- B- CA DB & C EA FE GF & D HB & C IG & H JI The activities are for building a house in 42 days... Each activity is a key part of the construction Activities cannot be completed until another task has been completed Sometimes, 2 tasks rely on the previous one...

Constructing a network Diagram ActivityPrerequisite (s)Duration (days) A-8 B-6 CA12 DB & C6 EA14 FE10 GF & D3 HB & C14 IG & H3 JI4 Now to calculate the EST and the LFT How do you find the Critical Path? Now to calculate the EST and the LFT

To recap... The Critical Path – the path along which there is no spare time – the EST and the LFT are equal EST - Where 2 activities come from 1 node, the HIGHEST number is chosen LFT – Where 2 activities go to one node, the LOWEST number is chosen

Floaters !!! There will be some “Float” time available for the non critical activities. TOTAL FLOAT – the amount an activity can be delayed without delaying the WHOLE project LFT – duration – EST Eg – D: – 20 = 6 total float days FREE FLOAT – the length of time an activity can be delayed without delaying the start of the FOLLOWING activity EST (next activity) – duration – EST (this activity) Eg – B: 20 – 6 – 0 = 14 free float days (B can be delay for 14 days without delaying D or H)

Your turn ActivityPrerequisite (s)Duration A-4 BA6 CA7 DB12 EC9 FD & E3 GA16 HG & F3

So, what are the advantages to CPA ???  Can estimate accurate delivery times (particularly if customers expect a certain date!)  Operations Manager – EST - he can order resources as and when needed (JIT, cashflow)  LFT – Ops Manager can identify if on schedule – are we on time to complete?  Identifying the Critical Path – no floats are available so need to ensure tasks done on time  If Critical Path is not on schedule, Ops Manager can see which other activities can be shortened or accelerated  Identifying where resources can be used in other parts of the project – if one activity is delayed resulting in another one being shortened, labour could be used from elsewhere (other floaters!)  Easy to do on a computer!  Forces managers to use a sequential method of planning BUT REMEMBER – projects can still fail even if the best management tool is used

Evaluating the CAP...