Presentation is loading. Please wait.

Presentation is loading. Please wait.

Lean Production: Critical Path Analysis 3.15 Lean Production Objectives; Understand the key requirements of critical path analysis (CPA) Understand the.

Similar presentations


Presentation on theme: "Lean Production: Critical Path Analysis 3.15 Lean Production Objectives; Understand the key requirements of critical path analysis (CPA) Understand the."— Presentation transcript:

1 Lean Production: Critical Path Analysis 3.15 Lean Production Objectives; Understand the key requirements of critical path analysis (CPA) Understand the purpose, benefits and limitations of using such a tool Apply the principles of CPA to a scenario Objectives; Understand the key requirements of critical path analysis (CPA) Understand the purpose, benefits and limitations of using such a tool Apply the principles of CPA to a scenario Thursday, 29 September 2016

2 An age old problem… How do you make the perfect cup of tea?  Milk then water?  Sugar before milk? What’s your theory?

3 Critical Path Analysis – A decision making tool “…a method of organising the activities in a project to find the most efficient method of completing the project without wasting resources (time, money, materials)” Aims of CPA… To plan complex operations To identify when a project must commence To illustrate the order of activities To identify critical activities – which are those activities which must be completed first To identify the times when resources can be reallocated

4 Nodes… they even grow on trees! The node shows the physical start and finish of an activity or task Nodes are NUMBERED from left to right 1 5 4 3 2 6 1

5 Arrows and Nodes 12 Activities are denoted by an arrow between nodes A 3 mins Activities are labeled above the arrow by a LETTER The duration of the activity is shown below the arrow, and could be minutes, days or another measure Node 1 shows the beginning of Task 1, Node 2 shows the end of Task 1 Other tasks can be started from Node 2

6 Linking tasks 1 A 3 mins 2345 B 1 min C D 2 mins E 1 min e.g. making a cup of Mint Tea… A – Put the kettle on B – Get a suitable cup C – Place bag in Cup D – Pour Hot water and ‘infuse’ E – Remove teabag…enjoy! Some tasks can be undertaken simultaneously, whilst others have ‘prerequisites’ which must be completed first

7 Earliest Start Time 1 A 3 mins 2345 B 1 min C D 2 mins E 1 min The top right box shows the earliest time than an activity can start – the earliest start time (EST). All previous tasks must be completed first 0 Node 1 is always ‘0’. It can be started straight away! Node 2 is only reached after 1 minute (task ‘B’) – so EST is 1 minute Node 3 is only reached after 3 minutes (tasks B+C = 2 but task A = 3) Node 4 is reached after 5 minutes Node 5 is reached after 6 minutes 1 356 This tells us that we are capable of finishing the job after 6m

8 Latest Finish Time 1 A 3 mins 2345 B 1 min C D 2 mins E 1 min The lower right box shows the latest finish time (LFT). This shows when we need to start the next task so as not to delay the project 0 Node 5 here is always the same as EST, as it can’t be reached before and if it is later then the whole project is delayed! So ‘6’ Task E takes 1 minute, so to be ready for LFT of ‘6’ at Node 5, its LFT is ‘5’ Task D takes 2 minutes, so to be ready for LFT of ‘5’ at Node 4, its LFT is ‘3’ Task C takes 1 minute, so to be ready for LFT of ‘3’ at Node 3, its LFT is ‘2’ Task B takes 1 minute, so to be ready for LFT of ‘2’ at Node 3, its LFT is ‘1’ NOT QUITE! There are two tasks to consider here… Task A takes 3 minutes, so to be ready for LFT of ‘3’ at Node 3, its LFT is ‘0’ Where LFT is calculated using more than one activity – we always allow for the longest route. In addition Node 1 always has an LFT of ‘0’ 1 356 For LFT we ALWAYS start from the right! 0 2 356

9 The float  With the network complete, you can now identify any idle time.  This spare time is known as the float.  Resources can be allocated to other duties during the float time.  How do you calculate ‘float’? LFT – (duration + EST)

10 Critical Path Analysis The NUMBER Board 1111 2222 3333 4444 5555 6666 7777 8888

11 1 What does an arrow represent in CPA? Number Board

12 2 What is this called, and when is it used? Number Board

13 3 What information is displayed above and below the ‘arrow’ in CPA? ? ? Number Board

14 4 What goes in here and what does it show? Number Board

15 5 Letter and numbers – each represents something specific in CPA, but what is it? Number Board

16 6 What is the name given to the series of tasks / activities that if delayed will delay the whole project? Number Board

17 7 Twigs float, so does polystyrene. But what does ‘float’ mean in a Critical Path Diagram? Number Board

18 8 What goes in here and what does it show? Number Board

19 Critical Path Analysis  Advantages Maximise efficiency in the use of time Improve efficiency and generate cost saving in the use of resources Beneficial to monitoring cash flow Identify potential problems in implementing operation Identifies where and when resources (including human ones) are needed  Disadvantages Usefulness may be limited in complex and large scale operations Necessity of having clear and reliable information Skilled management and team philosophy is essential CPA is a planning tool – not a decision making tool


Download ppt "Lean Production: Critical Path Analysis 3.15 Lean Production Objectives; Understand the key requirements of critical path analysis (CPA) Understand the."

Similar presentations


Ads by Google