PRE-PLANNING FOR CONSTRUCTION PROJECTS. OVERVIEW ASSESSING OWNER CAPABILITIES ANALYSIS OF RESOURCES REGULATORY REQUIREMENTS SITE DEVELOPMENT REVIEWING.

Slides:



Advertisements
Similar presentations
Implementing Service First References & Recommendations.
Advertisements

1 DEBRIS MANAGEMENT OVERVIEW PRESENTER: GREG KELLER, Disaster Recovery Branch Grants Administrator/Public Assistance Officer (614)
UNRESTRICTED Infrastructure Assessment as Viewed by Technology Holders IAEA Technical Meeting December 10-12, 2008 R. Godden.
NATURE OF CONSTRUCTION BUSINESS Aleš Tomek Faculty of Civil Engineering Department of Economics and Management CZECH TECHNICAL UNIVERSITY IN PRAGUE.
Module 11 Session 11.2 Visual 1 Module 11 Executing and Controlling the Work Session 11. 2: Managing Contracts.
Alternative Project Delivery
Contractor Management and ISO 14001:2004
PROJECT DELIVERY SYSTEMS
Western States Energy & Environment Symposium October 27, 2009.
THE PROJECT TEAM TYPICAL REQUIREMENTS AND RESPONSIBILITIES OF THE PROJECT TEAM TRADITIONAL TEAM ORGANIZATION AND VARIATIONS THE OWNER’S TEAM THE DESIGN.
TEL382 Greene Chapter /27/09 2 Outline What is a Disaster? Disaster Strikes Without Warning Understanding Roles and Responsibilities Preparing For.
PROCEDURES FOR SELECTING THE CONTRACTOR
1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015.
Regulatory Body MODIFIED Day 8 – Lecture 3.
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
Transportation Management Plan Overview. TMP Overview2 Is that the impression people have?
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
I n t e g r a t I n g C S S Practitioner Module 6 1 Module 6: CSS and Livability in Construction, and Maintenance.
Advancing environmental sustainability in WHO/PAHO and in the health sector.
IAEA International Atomic Energy Agency How do you know how far you have got? How much you still have to do? Are we nearly there yet? What – Who – When.
ISO EMS OVERVIEW May ISO EMS OVERVIEW TRAINING Contents What is an EMS? Why ISO & Certification? EMS Basic Elements Environmental.
Sustainability and Total Cost of Ownership Strategies for Higher Education.
Organization Mission Organizations That Use Evaluative Thinking Will Develop mission statements specific enough to provide a basis for goals and.
1 NG KIH / I Way UK Analytics & Technologies Service Showcase 2015 August 6, 2015 Presented by Finance and Administration Cabinet Commonwealth of Kentucky.
Workshop of the Medical Education Subcommittee of the Strategic Planning/Educational Policy Committee Board of Governors July 20, 2005.
McGraw-Hill/Irwin Copyright © 2004 by The McGraw-Hill Companies, Inc. All rights reserved. Chapter 13 Marketing Channels.
Module 10 Session 10.4 Visual 1 Module 10 Organizing Procurement Session 10.4 Procurement of Services: Use of Consultants and Developing Terms of Reference.
1 Professional Development Training – Enhancing the Delivery of Services Marcela E. Stanislaus facilitator Blackmon Roberts Group, Inc.
Projects and procurement (lecture). Procurement Acquiring hardware, software, materials, services, spare parts, skills, workforce etc. which are necessary.
TOPIC-9- PROJECT ORGANIZATION
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
JACK O’CONNELL State Superintendent of Public Instruction 1 Program Guidelines for Students who are Visually Impaired PRESENTATION TO: California Transcribers.
สถานการณ์ ท่านดูรับผิดชอบเรื่องการ เตรียมการและตอบโต้ภาวะฉุกเฉิน ของหน่วยงาน ขณะนี้ท่านได้ จัดทำแผนเผชิญเหตุของ หน่วยงานเสร็จเรียบร้อยแล้ว ท่าน ได้รับคำสั่งจากหัวหน้าหน่วยงาน.
Embedding Sustainability in the Supply Chain Philip Duddell, Sustainable Procurement Limited 10 th September 2015 Conference.
Legal Aspects of Special Education and Social Foundations The Americans with Disabilities Act (ADA) The Americans with Disabilities Act (ADA)
Foundations of Technology.  To familiarize students with the function, applications, and requirements of construction management.
08 October 2015 M. Ammar Mehdi Introduction to Human Resource Management & SSG-16 Actions 4 th Steering Committee on Competence of Human.
CERTIFICATION In the Electronics Recycling Industry © 2007 IAER Web Site - -
Transportation Management Plan Overview. TMP Overview2 Is that the impression people have?
Construction Engineering and Management 1 Cost Benefits Structural Safety Architect Feasibility Assessment of architects Functional Aesthetic constructability.
BZUPAGES.COM. Presentation Chapter#7 The Business plan: Creating & Starting the Venture Presented to: Sir Ghulam Abbas.
1 Asset Management Steering Committee Briefing on Senate Bill 408 (Access Management) August 2013 Harold Lasley, P.E. Access Management Program.
Sustainable Procurement What is Sustainable Procurement? Effective protection of the environment Prudent use of natural resources Social progress that.
Programme Performance Criteria. Regulatory Authority Objectives To identify criteria against which the status of each element of the regulatory programme.
4733 Bethesda Ave, Suite 600 Bethesda, MD (P) Developing Criteria for Project Programming.
Management of Change ► The health, safety, security, environmental, technical and other impacts of temporary and permanent changes are formally assessed,
Unit 8.2: Effective Implementation Planning HIT Implementation Planning for Quality and Safety Component 12/Unit 81 Health IT Workforce Curriculum Version.
TOPIC-9- PROJECT ORGANIZATION
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
ISO Registration Common Areas of Nonconformances.
McClain County Multi- Jurisdictional Multi-Hazard Mitigation Plan Update Image from
Chapter 9 THE FUTURE OF BUSINESS Gitman & McDaniel 5 th Edition THE FUTURE OF BUSINESS Gitman & McDaniel 5 th Edition Chapter 9 Managing Human Resources.
COSCDA Annual Conference PROGRAM PURPOSE Goal: To encourage communities to focus on workforce development as a long-term economic development strategy.
Elementary School Administration and Management GADS 671 Section 55 and 56.
Erman Taşkın. Information security aspects of business continuity management Objective: To counteract interruptions to business activities and to protect.
Lecture(3) Sequence of Studies for a Single Major – Infrastructure Projects 1 A preliminary (or reconnaissance) report. 2 A feasibility report.
Preparation Plan. Objectives Describe the role and importance of a preparation plan. Describe the key contents of a preparation plan. Identify and discuss.
3-1 McGraw-Hill/Irwin © 2004 The McGraw-Hill Companies, Inc., All Rights Reserved. CHAPTER THREE Planning Screen graphics created by: Jana F. Kuzmicki,
California Department of Public Health / 1 CALIFORNIA DEPARTMENT OF PUBLIC HEALTH Standards and Guidelines for Healthcare Surge during Emergencies How.
Introduction to Procurement for Public Housing Authorities Alternatives to Procurement: Force Account Labor Unit 9.
Organizations of all types and sizes face a range of risks that can affect the achievement of their objectives. Organization's activities Strategic initiatives.
Organization and Implementation of a National Regulatory Program for the Control of Radiation Sources Program Performance Criteria.
 What is EWP & How Does the Program Work? Emergency Watershed Protection Program.
Technical External Management Requirements Technology Complexity Interfaces Reliability / Performance Quality Planning Controlling Funding / Resources.
PRESENTATION OF FINDINGS GRANTEES NEED ASSESSMENT
PROJECT DELIVERY METHODS
Projects and procurement
Projects and procurement
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

PRE-PLANNING FOR CONSTRUCTION PROJECTS

OVERVIEW ASSESSING OWNER CAPABILITIES ANALYSIS OF RESOURCES REGULATORY REQUIREMENTS SITE DEVELOPMENT REVIEWING DESIGN AND CONSTRUCTION ALTERNATIVES CONSTRUCTION CONTRACT ARRANGEMENTS

OVERVIEW The owner must start general planning for the construction project before engaging the contractor. The contractor is responsible for means and methods. Close cooperation of the designer enhances owner’s preplanning activities including: –Analysis of capabilities and resources, –Site development and design reviews; and, –Regulatory and contractual issues.

ASSESSING OWNER CAPABILITIES Owners can engage external consultants to aid in pre-planning. Owners should begin pre-planning with an internal evaluation of the number and extent of project activities that can be managed by existing staff. In addition to design and construction tasks, these may include financial, regulatory, and legal activities.

ANALYSIS OF RESOURCES The resources available to the owner, designer, and contractor influence their respective decisions regarding project objectives, planning and design, contracting strategies, and construction operations. There are 4 general types of resources: –Financial resources –Construction materials –Manufacturing capabilities of suppliers –Human resources

Financial Resources The total funding available and the cash flow schedule affect project decisions. Providing adequate financial support for initial activities (related to establishment of project objectives and design criteria) is a critical step. Inadequate capitalization can create adverse impacts (e.g. inadequate staffing, delays in delivery, equipment failure, or shortages of construction materials) that hamper a participant’s ability to deliver quality service.

Financial Resources (cont.) In some cases, designers and/or contractors are able to enhance overall project quality by offering the owner financial management and consulting services. On public projects, this may include assistance in determining agency requirements for grants and reimbursement. On private projects, this assistance may include identifying new sources of capital or lines of credit. Some contractors are willing and able to finance the entire project, which allows the owner to wait until the project is ready to begin operating and generating revenue before his or her own financial resources are committed.

Construction Materials The cost and availability of construction materials affect planning, design and construction operations. Choosing the right construction materials is a critical process that, by its nature must be undertaken early in the planning process. The owner can benefit from the involvement of as many project team members as possible in the selection process.

Factors Affecting Material Selection Type of soil conditions and foundation alternatives Aggregate sources for concrete Availability of fill materials Site conditions (urban vs. rural) Cost (including transportation) Sustainable development, legislative issues (Buy American, hire local, etc.)

Manufacturing Capabilities of Suppliers During pre-planning, the owner and project team must address the need for specialized permanent equipment, components, or materials that may require sophisticated or specialized manufacturing. With the assistance of specialty advisers, the team can review and evaluates the manufacturing and delivery capabilities of potential suppliers or vendors.

Human Resources In the initial stages of project planning, the owner should evaluate the human resources needed to complete the effort. Key factors are the continuity of management staff and adequacy of the work force. Staff continuity helps to enhance communication, builds better team work and compresses “the learning curve”. Local construction firms, labor unions, contractor associations should be brought on board early to secure a skilled workforce. To mitigate potential labor shortages, consideration should be given to modifying projects, schedules, building systems (e.g. prefab) and initiate additional training programs.

REGULATORY REQUIREMENTS Government agency regulatory requirements can have a considerable impact on pre-planning. Members of the project team must comply with applicable laws and cooperate with agency personnel during each phase of a major project, from conceptual planning through the design and construction phases. Some agencies may specify unique requirements for particular projects.

REGULATORY REQUIREMENTS (cont.) Typical areas of agency monitoring and participation include: –Job site safety, public health and safety laws –Compliance with goals for minority, female, and local residency hiring, and disadvantaged business participation –Grants and loans guidelines –The use and disposal of hazardous materials –Environmental impact assessment and evaluation to assist the owner in obtaining required permits –Compliance with state and federal disability accessibility laws

SITE DEVELOPMENT Some site development activities may take place during planning and design phases-before completion of construction contract documents. Such as: –Constructing access roads –Extending utilities to the site –Constructing temporary buildings and other facilities –Setting up construction laydown areas and fabrication yards –Planning for traffic control, developing traffic detours –Relocating utilities, highways, rail, and other facilities

REVIEWING DESIGN AND CONSTRUCTION ALTERNATIVES At appropriate points in the evaluation of project alternatives, the project team should review alternatives with regard to: –Estimated cost –Schedule –Quality –Construction sequencing –Plant or equipment layout –Sustainable development issues –Constructability –Safety –Construction work plans

CONSTRUCTION CONTRACT ARRANGEMENTS The owner is is responsible for establishing the construction contracting strategy. In general, effective construction contracting strategies are: –Meet the owner’s project goals and objectives –Reflect the owner’s capabilities –Specify responsibilities of the designer and contractor