ML Tunnel Design Change High Energy Accelerator Research Organization KEK- LC Project Office Masanobu Miyahara 5th Nov. 2015.

Slides:



Advertisements
Similar presentations
Homework of HLRF 1 Shigeki Fukuda KEK 2012/4/23 HLRF Homework1 in KILC12 (Fukuda) 1.
Advertisements

CERN TS Department / Civil Engineering Group 8 February 2008 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC/ILC Collaboration Meeting 8 Feb 2008.
SPL Integration Layout Impact on cryo and vacuum sectorisation ◊ Underground obstacles, constraints on slope and length of the SPL ◊ Continuous cryostat.
CONVENTIONAL ELECTRICAL TDR DESIGN Randy Wielgos March 22, 2012 ILC CFS Baseline Technical Review.
CFS near term & Required ADI input CFS near term & Required ADI input 6-12 month activities, required ADI information 10. AUG 2014CFS-ADI Joint Meeting1.
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Reduced Bunch Number 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
ALCW15 Mike Harrison AD&I and Change Request status.
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
Marc Ross Nick Walker Akira Yamamoto XFEL – based HLRF scheme 07 Sept 2010 BAW 1 - Backup HLRF 1.
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Positron Source Relocation 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
Global Design Effort - CFS LCWS CONVENTIONAL FACILITIES AND SITING GROUP Parallel Session Overview A. Enomoto, V. Kuchler, J. Osborne.
TS Department / Civil Engineering Group 17 October 2007 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC workshop – Working group: Two beam hardware.
ILC CFS AD&I Daresbury Lab Summary J.Osborne / V.Kuchler / A.Enomoto.
LINEAR COLLIDER COLLABORATION Designing the world’s next great particle accelerator Detector Hall Configuration Overview New baseline (Hybrid A’) proposed.
Finding VOLUME DeMarco. The OBJECTS FORMULA? L x W x H Length = 6cm.
Finding VOLUME. What is VOLUME? The amount of space that a 3-dimensional object takes up. Anything that exists, has volume…
November 17, st XFEL / ILC Meeting 1 ILC GLOBAL Design Effort The Current ILC Twin Tunnel Design Wilhelm Bialowons and Nicholas Walker · MPY.
More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison.
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions Ewan Paterson Technical Board June 23,
TDR Status of Asian CFS Team Part II: The ILC Baseline Reference Ch.SectionSubsectionsAuthor1 st draft 112: Asian Region Siting Studies Overview Location.
Current CLIC Energy Stages D. Schulte1. Main Beam Generation Complex Drive Beam Generation Complex Layout at 3 TeV D. Schulte2.
Report from ILC CFS and Cryogenics Workshop
BAW1 RDR Confg For Mntn Rgn (S. Fukuda) 1 RDR configuration for Mountain Region S. Fukuda/KEK.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
Radiation safety evaluation for “KAMABOKO” Main Linac Tunnel KEK-APL : T.Sanami, S.Ban KEK-ACC : A.Enomoto, M.Miyahara ILC Mechanical & Electrical Review.
Civil Engineering and Services - drawings for CDR - CDR chapter J.Osborne and M.Gastal for CES WG 1.
Global Design Effort - CFS ILC10 Beijing, March, Single-Tunnel Accelerator Configuration Of Asian Region Atsushi Enomoto (KEK)
Electron Source Configuration Axel Brachmann - SLAC - Jan , KEK GDE meeting International Linear Collider at Stanford Linear Accelerator Center.
The fourth Baseline Technical Review (BTR) - Conventional Facilities and Siting March 2012 All changes made to the CFS 2007 Reference Design during.
LEP3: integration issues at the LHC tunnel M. Koratzinos 2 nd LEP3 day, 23 October 2012.
Aug 23, 2006 One-vs-Two Tunnel Tradeoffs (America’s Specific) Chris Adolphsen With contributions from the Civil Group, John Carwardine, Ray Larsen and.
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Global Design Effort - CFS AD & I Meeting - DESY AD & I Meeting - DESY 1 AD&I Meeting CONVENTIONAL FACILITIES AND SITING GROUP Main Linac Tunnel.
March 22,  Overview of Asian Civil Design  Previous Case Study  Feature of Beam Tunnel  Tunnel Typical Cross Section  Beam Tunnel.
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions Ewan Paterson ADI Meeting July 2, ADI Meeting Ewan Paterson 7/2/15.
Global Design Effort - CFS Oct IWLC ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto.
M. Ross, N. Walker, A. Yamamoto th ATF2 Project Meeting Accelerator Design and Integration – New Baseline Proposal for ILC – ‘Strawman Baseline.
Jan Low Energy 10 Hz Operation in DRFS (Fukuda) (Fukuda) 1 Low Energy 10Hz Operation in DRFS S. Fukuda KEK.
June Recent Development of DRFS (Fukuda) SCRF-Meeting 1 1 Recent Development of DRFS (Based on Japanese CFS Tunnel Plan) S. Fukuda KEK.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Global Design Effort - CFS ILC Integrated Design Meeting, DESY, May ML Single Tunnel Configurations In Deep Underground Accessed with Long.
Access Hall Study for Cryogenics High Energy Accelerator Research Organization KEK- LC Project Office Masanobu Miyahara 2 Nov
The LEP Superconducting RF system has reached its maximum configuration of 288 four-cell cavities powered by 36 klystrons in In 2000, this system,
Civil Design for Tunnel Case Studies
Experimental Hall in Mountain Regions
CLIC Civil Engineering Update
Introduction and Meeting Objectives
CLIC Civil Engineering Update
CLIC Civil Engineering & Infrastructure
Q &A for the questions from CFS of April 29,2011
Summary of WG2 :CFS for staging
Staging in the TDR.
FCC Civil Engineering update
Latest ILC tunnel cross section May 2017
FCC-ee MDI Civil Engineering update
Radiation protection of Linac4 M. Silari Radiation Protection Group
Mass & Volume 6th grade.
Special LS1 day on 12 June 2012, EDMS:
Summary Some Issues of Future Consideration
Status of Cryogenics Facilities Design
CLIC Civil Engineering Update
General presentation about recent status of DRFS
ILC CFS AD&I Daresbury Lab Summary
Cost Comparison of Undulator and e-Driven Systems
Electron Source Configuration
8-10 April 2014 CFS-ADI Joint Meeting
Overview of Day One – 29 Feb 2016
Central Region Working Group
Presentation transcript:

ML Tunnel Design Change High Energy Accelerator Research Organization KEK- LC Project Office Masanobu Miyahara 5th Nov. 2015

CFS Work after TDR ML-Tunnel Standard Section in TDR Beam Line RF Gallery ML-T Cross Section ML-T 3D Image Beam Line RF Gallery Shielding Wall Drainage Trench Cross Section Tunnel Section : W11.0 m× 5.5m, Excavation Area : 62.7 m 2 Shielding Wall : W3.5 m × 5.5m, Wall Area : 15.5 m 2

ML-Tunnel Standard section in New Baseline 66kV & 6.6kV High Voltage Line Cooling Water(S,R) & CHW(S,R) Underground Water ML-Tunnel Cross Section in New Baseline ML-Tunnel Layout PartDimensions BLW: 3.8m Shielding WallThickness: 1.5m RFW: 4.2m Total Beam Tunnel Length : 25,000m

Baseline SW3.5m Option-1 SW1.5m, BL3.8m, RF3.7m Option-2 SW1.5m, BL3.8m, RF4.2m W11m x H5.5m Designed Ex Area 62.7 m2 W9m x H5.5m Designed Ex Area 53.6 m2 W9.5m x H5.5m Designed Ex Area 55.8 m2 Schedule (Monthly Progress) 92.8 m/month101.2 m/month99.0 m/month Construction Cost Unit kJPY/mUnit kJPY/mUnit kJPY/m kJPY/m Total 60,250 MJPYTotal 47,880 MJPYTotal 49,130 MJPY - 12,370 MJPY- 11,120 MJPY Cost Comparison (TDR:100%) 79.5%81.5% Comparison Study of Construction Cost 2014 CFS 4 TDR Baseline 11.0 × m 2 Reviced Option -2 9m × 5.5m 53.6 m 2 Reviced Option m × 5.5m 55.8 m 2 Confidential Document

Option-1 SW1.5m W9.0m x H5.5m Ex Area 53.6 m2 Total Kamaboko Tunnel length : 25,000m Baseline SW3.5m W11m x H5.5m Designed Ex Area 62.7 m2 - Beam line : Width 3.8m - Klystron gallery: Width 3.7m - Tunnel Ceiling: Height 5.5m - Beam line : Width 3.8m - Klystron gallery: Width 3.7m - Tunnel Ceiling: Height 5.5m Scheme Change Concept TDR Baseline:  Possible to enter the RF area during the beam operation New Baseline:  Person's entering restriction during the beam operation  Considering the dark current Variation of the Change Option Tunnel cross section CFS Work after TDR - Beam line : Width 3.8m - Klystron gallery: Width 4.2m - Tunnel Ceiling: Height 5.5m - Beam line : Width 3.8m - Klystron gallery: Width 4.2m - Tunnel Ceiling: Height 5.5m Option-2 SW1.5m W9.5m x H5.5m Ex Area 55.8 m2 - Beam line : Width 3.8m - Klystron gallery: Width 3.7m - Tunnel Ceiling: Height 5.5m - Beam line : Width 3.8m - Klystron gallery: Width 3.7m - Tunnel Ceiling: Height 5.5m

Back Up

Connecting Passage between both tunnels Under Discussion

New Baseline Additional Tunnel 13, , /4/138 CFS Work after TDR 3km Extension of ML Tunnel QuantityUnit PriceCost for this scheme change 3,000 kJPY/m5,895,000 kJPY  Civil Cost neccesaried for CR-004 : 5,895,000 kJPY.  This cost is equivalent to approximately 53% of amounts of money managed to come up with by an ML tunnel section change.

TDR Baseline 11.0m × 5.5m 62.7 m 2

Reviced Option m × 5.5m 53.6 m 2

Reviced Option m × 5.5m 55.8 m 2