MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.

Slides:



Advertisements
Similar presentations
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Advertisements

MICE: Hall Infrastructure Chris Nelson CEng CM15 8 th June 2006.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
SS and AFC Control Systems Brian Martlew 21 st Sept 2011.
Status of Electronics and Control System P J Smith University of Sheffield 20 th August 2009.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
MICE CM26 March '10Jean-Sebastien GraulichSlide 1 Detector DAQ Issues o Achievements Since CM25 o DAQ System Upgrade o Luminosity Monitors o Sequels of.
EMMA Electrical Engineering July 06 EE & PS Group EE & PS Group – EMMA 06
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
MICE - UK Project Progress Roy Preece 30 th April 2013.
Cryo Update and Power Distribution Alan Bross Tracker Parallel – MICE CM October 7, 2007.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
S A Griffiths Target Review Jan 2009 Target Electrical / Control Schematic HexBridge Power electronics Interface PSU Capacitor Bank Local Control Interface.
MOM Report Galina Vankova RAL, MICE Video Conference.
MICE Controls Progress 15 th March 2007 * Controls Infrastructure * Controls network * Target * Superconducting Solenoid * Magnet Power Supplies * Hydrogen.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Electrical & Control Power Supplies Trevor Hartnett.
1 MICE MPB/RLSR Integration of Step IV Readiness of the major subsystems Installation sequence and schedule considerations Logistics, staffing and local.
Project Status Update Mark Petree LCLS Self Seeding Status: Management put it on hold. – Preliminary conceptual design completed – Interference.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update.
Tracker Summary Alan Bross MICE CM October 10, 2007.
Installation issues - update, July 2006A.Fabich1 MERIT installation: Update July 2006 A.Fabich CERN AB-ATB July 2006.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Decay Solenoid – what do we have to do to make it work?
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
Extraction and beamline progress B.Goddard TE/ABT.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
S A Griffiths CM42 June 2015 Electrical & Control.
Chris Booth Sheffield 29th March 2006
MICE RF System Power Supplies, Control and Monitoring Status report
Electrical & Control.
MICE Target Report Video Conference 29/11/07
Introduction Jason Tarrant – Integration Engineering Step IV Removal
LCLS Cavity BPM Electronics Undulator Week January 22, 2008
Undulator Vacuum System
Report on ATF2 Third Project Meeting ATF2 Magnet Movers ATF2 Q-BPM Electronics Is SLAC ILC Instrumentation Group a good name?
Undulator Vacuum System
LCLS Control System Personnel Linac & BC2 Controls progress
Presentation transcript:

MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses controls VME crate & magnet ON lamp monitoring –Awaiting delivery of monitoring crate. Due end July-07 –Rack 95% complete –Wiring & Termination drawings complete –Electrical & controls checkout w/c 30-July-07

MICE Project Progress Update Decay Solenoid Solenoid power supply tested & ready for return to RAL –To be located on mezzanine floor –Mezzanine floor requires strengthening –Control interface requirements known –Drawings to be updated to show requirements

MICE Project Progress Update Cable Management Basic tray & trunking layout complete Drawing sheets 1 to 7 issued –Installation can now proceed Main MICE Hall cable routes & to LCR design complete Cable schedule complete for magnet power converters Mains distribution for power converters & LCR complete Mains distribution boards to be purchased & installed LCR tray work design complete –Rack support frames to be manufactured –Tray work to be installed –Raised floor to be installed Phase 2 electrical requirements under review –Detailed information for all systems required

MICE Project Progress Update Personnel Safety Rack Internal wiring 75% complete Terminals & relays installed Control crates in build UPS on order Testing at DL mid-August Delivery to RAL end August