MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.

Slides:



Advertisements
Similar presentations
1 Powering Tests and Safety Electrical Safety Hugues Thiesen Power Converter Group.
Advertisements

TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
CRYOGENICS AND POWERING
Acknowledgments: O.Aberle – F.Bertinelli – J.C.Billy - O.Capatina - J.Casas - L.Ceccone - S.Claudet J.Coupard - K.Dahlerup - R.Denz - K.Foraz - J.J.Gras.
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
Powering Group of Circuit Doubts and proposals of the procedure reviewing team (Gianluigi, Rob, Sandrine, Matteo, Boris) Ref document: LHC-MPP-HCP-071.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Powering of the Superconducting Circuits: Procedures and Strategies for Circuit Validation Antonio Vergara on behalf of the Hardware Commissioning Coordination.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
CERN Rüdiger Schmidt FCC week 2015 Long Magnet Stringpage 1 Incident September 19 th Architecture of powering and protection systems for high field.
1 Copper Stabilizer Continuity Measurement Project Copper Stabilizer Continuity Measurement Status & Plans – May 2011 MPE-TM – 12 May 2011 M. Koratzinos,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
PostMortem Workshop January LHC “Post Mortem” Workshop: Introduction Initiative by Robin Lauckner, Adriaan Rijllart and myself, helped by many other.
AT-MEL-PM, R. Denz, CERN, CH-1211 Geneva 23 1 QPS system and its risks  Principal risks  General remarks  Quench heater circuits  Quench detection.
For more info:
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Hardware Commissioning Tools Robin. AB-CO TC 8th February 2007Hardware Commissioning Tools - RJL2 Summary Hardware Commissioning View Slides from Antonio.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
SAFETY DURING HARDWARE COMMISSIONING, 18 October 2007, D. Bozzini, AT/MEL-EM 1 Safety during Hardware Commissioning Davide Bozzini on behalf of the ELQA.
Andrzej Siemko On behalf of the MPP-GMPMA Task Force: (A. Ballarino, R. Denz, B. Khomenko, A.Perrin, P. Pugnat, A. Rijllart, L. Serio, A. Siemko, A. Vergara.
[R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] HWC Workshop ( ) Consolidation and major changes that have impact on the powering circuits.
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
16-17 January 2007 Post-Mortem Workshop Logging data in relation with Post-Mortem and archiving Ronny Billen AB-CO.
Review of Sector th of February Tunnel Access During Powering Tests Hugues Thiesen, AB-PO.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
Roberto Saban TS HC Review bis Outline  Interviews of all the Group Leaders loosely or tightly concerned by hardware commissioning proposing them.
MPP Workshop Status of Powering Interlocks I. Romera on behalf of MPE-MS MPP Workshop, 12 June 2015, I. Romera (TE-MPE)1.
An invitation to an open discussion We are team reviewing its performance globally We want to help each other to reach the objectives We know the other.
Training LHC Powering Robin Lauckner Software Tools for Commissioning Robin Lauckner 28 th March, 2007.
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
AB-CO Review September Session on circuit commissioning Session on circuit commissioning Post-Mortem requirements F. Rodríguez-Mateos on behalf.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
LHC Post Mortem Workshop - 1, CERN, January 2007 (slide 1/52) AB-CO Measurement & Analysis Present status of the individual.
HL-LHC IT STRING and Series test of SC link
Powering LHC magnets version 30/3/2007.
The HL-LHC Circuits: Global View and Open Questions
Superconducting Circuits, a generic view
Giorgio on behalf of ELQA team
Experience: past events and accidents
The LHC - Status Is COLD Is almost fully commissioned
Powering the LHC Magnets
MPE main activities planned for LS2
the CERN Electrical network protection system
Powering from short circuit tests up to nominal
Circuits description and requirements - Closed Session-
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
3 issues identified in review
TEST PLANS for HL LHC IT STRING
Machine Protection Xu Hongliang.
+ many slides from various colleagues (KH, Rudiger, Paul, …)
Machine Protection System Commissioning plans
Brief report of the hardware commissioning activities
Hardware Commissioning
Review of hardware commissioning
Presentation transcript:

MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case of MB1055(26R7) 3)Recommendations for the HWC of 600A in Sector 7-8 4) A.O.B.

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Hardware Commissioning Training  In March we will start to power cold LHC circuits. The first activity will be to commission the equipment safety systems which are mainly the responsibility of the QPS, PIC and Power Converter teams. Commissioning will involve these experts as well as Hardware Commissioning Coordination, the CCC Operations Engineers and Technicians as well as key support services such as cryogenics, technical services and accelerator controls.  In order to prepare an efficient approach to this activity a one day training session on March 15th is being organised for the people involved. Looking towards parallel commissioning of the LHC sectors later this year we are aiming to spread the knowledge rather widely. As a first estimate we believe about people should be familiarised with LHC powering and the systems involved.

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Hardware Commissioning Training  First half day Introduction (L.Evans) Powering LHC (R.Schmidt) Overview: from Individual System Tests up to Powering to Nominal (B.Perea) - presentation possibly shifted to the afternoon - Superconducting elements (K.H.Mess) Power converters (D.Nisbet) Quench protection (R.Denz) Powering Interlocks (M.Zerlauth)  Second half day Cryogenics and powering (L.Serio) DFBs, Current Leads (A.Ballarino) General services (T.Pettersson) Powering from short circuit test up to nominal (A.Vergara) Overview: software tools for commissioning (R.Lauckner) Risks for personnel during commissioning (P.Proudlock) Organisation of hardware commissioning (R.Saban)

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Training Programme  Introduction (L.Evans – 15min) What hardware commissioning? Why is it needed (no such term for LEP). How is it related to other phases: LHC construction, installation and beam commissioning. General schedule.  Powering LHC (R.Schmidt - 30min) Why so many magnets? Magnet types and their function (very brief). Magnets powered individually and magnets powered in series, layout DB. Why so many circuits, 8 sectors, 28 powering sub-sectors, challenges and constraints, circuit DB. Example scenario (to be reused throughout the talks): RB circuit. Introduction of the different elements / systems (QPS, Energy Extraction, PIC, PC,..). Machine Protection: Risk during powering, why equipment protection is required, link between protection during powering and beam operation,  Overview: from Individual System Tests up to Powering to Nominal (B.Perea Solano - 15min, talk possibly shifted to later during the day ) Short Circuit Tests, preparation/execution of cool down, ELQA, PIC1 and PIC2, powering to nominal, … within overall planning

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Training Programme  Superconducting system and its elements (K.H.Mess – 20min) what is inside the cryostats: magnets, busbars, current leads, … what is a quench, quench propagation (magnet to magnet, slow quenches in busbars at low current), what parameters have an impact (temperature, field, current density), operation of superconductors at different T what are the constraints during powering? max current, etc., view by the “sc equipment owners”  Power converters (D.Nisbet – 20min) normal conducting part of the circuit, converter and their types (modular), cabling, what is required to switch a power converter ON (water, electricity, controls, powering permit, …), when does it trip, state diagram  Quench protection (R.Denz – 30min) magnet types, busbar types, methods of detection (local and global), methods of protection (diode, heaters, EE) for magnets in series and for stand-alone magnets, cryogenic conditions, what is required for giving powering permit different types of circuits (with/without energy extraction, …) QPS supervision levels, for experts, operators and observers

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Training Programme  Powering Interlocks (M.Zerlauth - 20min) why PICs are required? main functionality, interactions with AUG, UPS, cryogenics and QPS introduction to interlock drawings PIC supervision (illustration)  Cryogenics and powering (L.Serio – 20min) what condition to start powering, when do we have to stop powering, protection signals (CryoOK etc), commissioning constraints, how commissioning operators get an overview of the cryo process, how to check that cryo is OK or not OK?, what to do before a (forced) quench and during quench recovery? What does the cryogenic system need to do its job? (vacuum, electricity, water cooling, …)  DFBs and Current Leads (A.Ballarino – 20min) what is inside a DFB, how to commission them for the first time, what can go wrong, what has to be respected during powering, what needs to be watches, constraints to powering  General services (T.Pettersson – 15min) AC distribution, cooling and ventilation, access Water circuits (demineralised / chilled water), how is it distributed? What is required for a smooth operation of the system? How can the correct functioning be verified? Alarms and Logging?

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Training Programme  Powering from short circuit test up to nominal (A.Vergara / R.Lauckner) Commissioning of the powering interlock systems: PIC1 and PIC2 Steps foreseen up to nominal powering (e.g. quench features, recovery time) Test in parallel (parallelism of circuits, of powering subsectors) How the schedule will affect the testing, highlighting the expected 'parallel test' scenarios  Overview: software tools for commissioning (A.Vergara / R.Lauckner) HWC sequencer SOC (set of circuits), Alarms, EquipState, Fixed Displays LSA database + operational and configuration data for HWC Software tools available to validate experiments and diagnose problems (post mortem) Recording of tests results: MTF Who need which tool (relation tool – operator/specialist)?

MPP Meeting 07/03/2007 A. Siemko/AT-MTM  Case of MB1055

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Case of MB1055  The context Case of MB3004 Case of MB2239  Case of MB1055  The risk identification  The risk analysis and evaluation  Recommendations

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Predecessors - Case of MB3004 MB3004 Example of normal signals

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Predecessors - Case of MB2239  MB2239 First training quench

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Predecessors - Case of MB2239 MB st 6.5kA provoked QUENCH MB st 9kA provoked QUENCH MB2239 2nd 6.5kA provoked QUENCH

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Predecessors - Case of MB2239  MB2239 Short location Courtesy of Marta Bajko

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Case of MB1055  Abnormal voltage signals similar to known seek cases such as dipoles 3004 and 2239 (i.e. compatible with the turn-to-turn short- circuit during the quench and action of Lorentz forces) were recorded during the first and second training quenches and last provoked quench at nominal current.  The amplitude of the observed oscillations has increased after each quench.

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Case of MB1055  1 st training quench

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Case of MB1055  2 nd training quench

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Case of MB1055  Provoked quench at nominal current

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Case of MB The risk identification  What can happen Further degradation of the electrical integrity of the magnet Damage of the coil preventing powering of the entire MB circuit Break of the electrical integrity of the neighboring magnets (flush of the diodes up to the whole sector) and proximity electronics (QPS) due to uncontrollable HV oscillations Break of the vacuum and cryogenic integrity (contamination of the beam vacuum of the entire sector with He and Carbon debris)  How it can happen Quench of the MB1055 magnet above the critical current level in the coil

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Case of MB The risk analysis  The probability of the risk is proportional to the current level and the amount of stored energy Natural training quench is unlikely below 9kA Natural training quench is highly probable at and above I nominal With beams the quench is probable at any current between I injection and I nominal  Levels of the risks Consequences of a quench below 2kA are limited to the magnet itself Consequences of a quench above 2kA can affect the entire sector 7-8  The controls The current level in the magnet (in the circuit) and resulting stored energy Quench (only provoked quenches for the HWC purpose) in the MB1055 and neighboring magnets

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Case of MB The risk evaluation

MPP Meeting 07/03/2007 A. Siemko/AT-MTM Case of MB1055 – MPP Recommendations  No risk scenario Recommendation:  Replace the MB1055 magnet before HWC powering tests  Risk scenario limited to the local damage Recommendation:  Limit powering of the MB circuit to 2kA  Do not provoke quenches in MB1055 and neighboring magnets  Replace the MB1055 magnet after the “engineering run” before the HWC to nominal current  Operation of this magnet with or without beams above 2kA puts the entire sector 7-8 into sizeable risk of a damage necessitating the opening of all interconnects in the sector and possible replacement of the significant part of the equipment

MPP Meeting 07/03/2007 A. Siemko/AT-MTM  The MPP Recommendations for HWC current rating in case of 600A circuits in Sector 7-8

MPP Meeting 07/03/2007 A. Siemko/AT-MTM HWC current rating for 600A circuits in Sector 7-8