ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.

Slides:



Advertisements
Similar presentations
Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
Advertisements

MICE Refurbishment of CERN RF equipment for MICE M. Vretenar, CERN AB/RF.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
Andrew Moss Daresbury Laboratory August 2013 Latest results of MICE amplifier testing.
Linac Status Eric Prebys DOE Review, Proton Source Breakout Session July 21,2003.
Proton Source Workshop December 7 & 8, 2010 John Reid December 8, 2010.
Tom Kubicki.  Booster HLRF System to be upgraded using 1kW Solid State Driver (SSD) Amplifiers.  Used to drive the 200kW Power Amplifier  Eliminates.
DESIGN OF A HIGH POWER TEST STAND FOR ESS SPOKE CAVITIES
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
Strategy for SPS 200 MHz LLRF upgrade (1)  Each of the four cavities (2x 5 sections, 2x 4 sections):  1-T Feedback (loop around cavity and amplifier)
Reliability Modeling of an ADS Accelerator SNS-ORNL/Myrrha Linac (MAX project) EuCARD 2, GENEVA (20-21 March 2014 ) CERN.
WAO, Trieste, 24th - 28th September 2007 An Overview of the Reliability and the Fault Trends of the SRS Cheryl Hodgkinson Daresbury Laboratory Synchrotron.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
© 2008 Data Power Services, LLC By: Tom Taranto 2010 Energy Expo Hosted by National Grid NYSERDA Reducing Compressed Air Energy Cost Using a Systems Approach.
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
Linac Marx Modulator Update Trevor Butler 5/20/2015.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
ATC / ABOC Days – Session 4 – January D. Smekens AT-MCS-MNC 1 MAGNETS FOR SPS & BEAM LINES MTTR & Spare Policy for the LHC Injectors & Exp.
Christophe Mugnier, on behalf AB/PO Group ATC-ABOC days, 23 January 2008 AB/PO equipment review and Stand-by service description for the power converter.
Major power converter issues for the restart of PS & SPS machines and their experimental areas in 2006 Jean-Paul BURNET for AB/PO PS&SPS days January.
PSB C04 RF system Consolidation or upgrade? M. Paoluzzi – CERN BE-RF 11/23/20151.
Reliability and availability considerations for CLIC modulators Daniel Siemaszko OUTLINE : Give a specification on the availability of the powering.
ATC / ABOC Days 23 Jan LHC injector Chain, E.A., Facilities. MTTR, spare parts and stand-by policy for BI equipments J.Tan AB/BI on behalf of BI.
RF and Transverse Dampers Current Systems Wolfgang Hofle W. Hofle - RF+Dampers - R2E and Availability Workshop OCtober Acknowledgements: RF.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
Almost 40 years of operation with tetrodes in the CERN-SPS CWRF workshop 2014, Trieste Eric Montesinos, CERN-RF, on behalf of RF-SPS team CWRF workshop,
W. Hofle LIU-SPS Meeting SPS BA2 Damper LS1 Progress and plans reported by W. Hofle LIU-SPS Meeting G. Kotzian T. Levens D. Valuch.
Solid State RF High Power Amplifier Developments at SOLEIL Ti RUAN, on behalf of SOLEIL RF Group CWRF10 CELLS-ALBA Barcelona Spain May
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
PIP Budget Codes Budget FY12 Updates October 19, 2011 PIP Meeting.
Commissioning of the ALBA IOT-Transmitters Paco Sanchez - 14th ESLS RF - ELETTRA, September Paco Sanchez, RF Group, CELLS (Consortium for.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
High Gradient RF Issues and 88 MHz test results M. Vretenar for the 88 MHz team: R. Garoby, F. Gerigk, J. Marques, C. Rossi, M. Vretenar -The.
Ingot Niobium Workshop RF Sources Andrew Kimber 4 th December 2015 Thomas Jefferson National Accelerator Facility is managed by Jefferson Science Associates,
28/01/2013 Gerrit Jan Focker, BE/BI/PM 1 Isolde SGIU Beam Instrumentation Remarks on status and possible development.
Agenda 1 BOSS Meeting - 27/5/ : :10 Introduction and aims of the workshop 10‘ 09: :25 Priorities from OP for PSB and transfer lines 15'
13 January 2005 PS&SPS DAYS How can we restart AD in 2006? Slide 1 How can we restart AD in 2006 ? Tommy Eriksson AB/OP/AD.
A new RF system for the PSB. LIU-PSB Working Group Meeting, 10th December 2015 M. Paoluzzi December 10 th Wide working group involved including.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
Practical experience with the AD Stochastic Cooling Murphy’s Law R. Louwerse.
Linac4 status and long-term schedule M. Vretenar, Project Meeting  status  timeline  open issues  status  timeline  open issues.
CS section activities Industrial controls Luca Arnaudon David Glenat David Landre Slawomir Totos Ruben Lorenzo-Ortega Digital hardware John Molendijk.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Radio Frequency Andy Butterworth AB/RF Accelerator Controls Renovation WS 3 Dec 2008.
MO/LO Performance Summary and Maintenance Plans Tomasz Plawski Jefferson Lab OPS Stay Retreat, July 15th, 2015.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
Status of the machines over X-mas standby period, services required and plans for rapid start-up OP Group Meeting KH.
PS Complex Controls Renovation S Baird AB/ABP ATC/ABOC Days: Session Jan 2008.
What’s Falling Apart in the Injector Chain ? PS/SPS Days January 2005.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
Linac4-PSB 160 MeV connection readiness review Tuesday 30 August August 2016 Linac4-PSB 160 MeV connection readiness review 2.
Report Technical Director Storage-Ring-Installation Completed
Situation of the Static Var Compensators at CERN.
Machine operation and daily maintenance management in SOLEIL
Summary of Session 6 ATC/ABOC days
High Energy Proton Synchrotrons
ELENA installation and commissioning status
MPE-PE Section Meeting
AD consolidation activities in LS2
on behalf of the RF group
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
RF operation of REX-ISOLDE
SNS Operational History
How can we restart AD in 2006 ? Tommy Eriksson AB/OP/AD
Presentation transcript:

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of the AB/RF Group

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP Many thanks to all colleagues in the AB/RF Group who have provided material for this presentation and some of their time for discussions and explanations.

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 3 Mean Time to Recovery = average time to recover from a failure  average beam downtime due to a specific failure Mean Time to Repair = total of corrective maintenance time divided by the total of corrective maintenance actions during a given period In this presentation I will consider the as it is directly related to the beam availability Mean Time To Recovery

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 4 The contribution of the RF systems to the beam downtime has been very small in 2007 and during the past years in general. Machine RF Availability In 2007 RF Quota on Fault Linac299.4 %46.5 % Linac3100* (89 – 98)%0* (40 – 50) % PSB99.2 %24.4 % PS99.6 %5.8 % AD99.1 %3.8 % SPS98.8 %5.4 % LEIRData not available The general strategy relies on the availability of hot spares, whenever possible, or at least on a reasonable stock of spare parts. The RF Group contributes to the AB Risk and Impact Register  effective machine consolidation strategy. *Limited operation during 2007.

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 5 We maintain a stock of spare tubes according to the following rule: 1 spare tube / socket, when many sockets are concerned by the same tube model; Multiple spare tubes in the case of single sockets. RF Vacuum Tubes Few critical areas: 1.SPS TWC200 Siemens amplifiers – the tube RS2004 could be soon out of production, spare tubes partly not new  diacrodes; 2.SPS TWC800 – minimum stock of old klystrons  IOTs; 3.Linac2 – tube TH170R limited production still possible, stock sufficient until 2015; 4.Rex – tube TH391 limited set of spares available. Few critical areas: 1.SPS TWC200 Siemens amplifiers – the tube RS2004 could be soon out of production, spare tubes partly not new  diacrodes; 2.SPS TWC800 – minimum stock of old klystrons  IOTs; 3.Linac2 – tube TH170R limited production still possible, stock sufficient until 2015; 4.Rex – tube TH391 limited set of spares available. Long term contract with RF tube manufacturers, agreement on our policy for spare stock management; Alternative suppliers for tubes whose production is discontinued by the traditional manufacturer. For all events requiring the replacement of a vacuum tube a MTTR going from few hours to max 1 day can be estimated.

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 6 Spare parts available, in general; complete (old) amplifier assembly for the 200 MHz 2.5 MW systems + spare parts (common to Linac2 and Linac3); HV power supplies under AB/PO responsibility. Linac2 and Linac3 Critical areas: 1.Linac3 100 MHz amplifiers (2 x 350 kW) – no spares for the HV anode capacitor  production of few spares; 2.Linac3 ramping cavity 100 MHz amplifier – partial stock of spare parts (controls and electronics). Critical areas: 1.Linac3 100 MHz amplifiers (2 x 350 kW) – no spares for the HV anode capacitor  production of few spares; 2.Linac3 ramping cavity 100 MHz amplifier – partial stock of spare parts (controls and electronics). MTTR going from 2 days (event 1) to 2 days (temporary repairing) – 3 weeks (proper fixing) (event 2). Complete renovation of the control and interlock systems, under the Simatic standard. Spare parts are partially available, in general; weak point in the 200 MHz tetrode amplifier (TH391); Low priority, limited set of spares  implement spare policy. Rex MTTR could be relatively long, depending on spare availability

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 7 Complete spare cavities available, ready for installation. Complete set of spare RF amplifiers, ancillaries and discrete components. PS Booster – HLRF (C02, C04, C16) Critical areas: 1.The C04 limited air cooling capability could affect the system reliability in the case of new operation schemes; 2.One spare HV anode power supply for 12 operational power supplies. Critical areas: 1.The C04 limited air cooling capability could affect the system reliability in the case of new operation schemes; 2.One spare HV anode power supply for 12 operational power supplies. MTTR going from 2 days for one complete cavity replacement to 1 week for patching to a different HV anode power supply  degraded operation possible. Complete spare modules are available for Ring and surface equipment. Hot spares available for pick-ups MTTR 1 week in case of PSB damper pick-up and kicker failure. PS Booster – LLRF Critical areas: 1.No hot spares for the PSB damper pick-ups and kickers. Critical areas: 1.No hot spares for the PSB damper pick-ups and kickers.

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 8 Complete hot spare RF system available in the ring (RF cavity + amplifier). Complete set of spares for all the RF components. LEIR MTTR expected shorter than 1 day in all cases. Critical areas: 1.Weakness of the transformer of the HV anode power supply for the RF amplifier  new transformer delivered by the manufacturer. HV anode power supply under AB/PO responsibility. Critical areas: 1.Weakness of the transformer of the HV anode power supply for the RF amplifier  new transformer delivered by the manufacturer. HV anode power supply under AB/PO responsibility.

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 9 When AD was built its operational horizon was 2005 and components from previous systems were used (LEAR, EPA). MTTR 1 week due to pick-up failure  degraded operation possible. Critical areas: 1.Some spares available for the high level RF, but general weakness due to component aging. 2.LLRF Schottky pick-ups have no spare. Critical areas: 1.Some spares available for the high level RF, but general weakness due to component aging. 2.LLRF Schottky pick-ups have no spare. AD Critical areas: 1.No drawings for the pick-up and kicker movement electronics and motors. 2.Control system still based on old, modified CAMAC controller. Critical areas: 1.No drawings for the pick-up and kicker movement electronics and motors. 2.Control system still based on old, modified CAMAC controller. 50 microwave amplifiers are maintained, but old. AD Stochastic cooling MTTR 1 to several weeks depending on fault.

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 10 All high level RF systems have at least one hot spare installed in the ring; complete set of RF amplifiers, ancillaries and discrete components available. 4 out of 6 C02 HLRF systems have been recently renovated. Periodic maintenance and consolidation strategy in place. Reduced MTTR due to hot spare system  degraded operation for AD beam. Critical areas: 1.Some components in the C10 system are old and becoming obsolete, including cavity servos  general consolidation in progress. Critical areas: 1.Some components in the C10 system are old and becoming obsolete, including cavity servos  general consolidation in progress. PS HLRF (C10, C20, C40, C80, C02)

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 11 The system is very complex, with a majority of dedicated equipment for specific beams and some equipment required by all beams. Spare modules and components are generally available. Variable MTTR related to diagnostic time (could take more than a day in rare cases) and spare availability. Critical areas: 1.40 / 550 modules have no working spare  repair / production of working spares in progress; 2.The one-turn delay feedback is not installed on cavity C10 11 (spare system)  degraded operation for AD beam; 3.Obsolete electronics in the Hereward damping system; 4.10 MHz matrix (special chassis, modules but no complete spare available); 5.The whole system availability relies on the operation of the room air conditioning system (system monitoring); 6.Extremely old electrical power distribution from the switchboard to the racks. Critical areas: 1.40 / 550 modules have no working spare  repair / production of working spares in progress; 2.The one-turn delay feedback is not installed on cavity C10 11 (spare system)  degraded operation for AD beam; 3.Obsolete electronics in the Hereward damping system; 4.10 MHz matrix (special chassis, modules but no complete spare available); 5.The whole system availability relies on the operation of the room air conditioning system (system monitoring); 6.Extremely old electrical power distribution from the switchboard to the racks. PS LLRF

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 12 Variable MTTR related to spare availability  degraded operation possible for TWC800 system. Critical areas: 1.Spare couplers (TWC200) and RF windows (TWC800) could not be tested because of lack of manpower; 2.2 out of 3 transformers broken during 2007 on TWC800  new transformers ordered. Critical areas: 1.Spare couplers (TWC200) and RF windows (TWC800) could not be tested because of lack of manpower; 2.2 out of 3 transformers broken during 2007 on TWC800  new transformers ordered. SPS HLRF (TWC200, TWC800) Complete set of spare RF amplifiers, ancillaries and discrete components is available, apart from the RF tubes already mentioned. Periodic maintenance and consolidation strategy in place. The progressive slow replacement of old Siemens amplifiers with new, probably diacrode, amplifiers will reduce the impact of possible failures.

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 13 Variable MTTR depending on the controller component affected. MTTR between 2 and 4 days for replacing one kicker in the machine. Critical areas: 1.The TWC200 cavity controller is equipped with Simatic PLC dating from 1982, with limited amount of spares; 2.The programming machine for that system is obsolete and only few remain (probably) at CERN. 3.No hot spares available for the transverse dampers. Critical areas: 1.The TWC200 cavity controller is equipped with Simatic PLC dating from 1982, with limited amount of spares; 2.The programming machine for that system is obsolete and only few remain (probably) at CERN. 3.No hot spares available for the transverse dampers. Spare modules and components are partially available. SPS RF Controls

ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts MTTR, spare parts and stand-by policy for RF equipments 14 Variable MTTR depending on specialist availability when the “piquet” is not provided or cannot solve the problem. HLRF is providing a piquet service for SPS equipments and PS C02. LLRF is providing a piquet service for PSB, PS and SPS. The HLRF intervention in the PS area (Linacs, LEIR, AD, Rex, PSB, PS) and the LLRF intervention in some of the machines of the PS area (LEIR, AD) is guaranteed by means of a list of specialists available on call. PIQUET In the PS area the HLRF piquet is not possible due to lack of manpower; however the on-call list has assured an effective intervention until now. The presence of hot spares helps. Critical areas: 1.Small number of specialists available for many different systems in the PS area; 2.Limited standardization of modules and equipments (basically due to their different age and to limited renovation). Critical areas: 1.Small number of specialists available for many different systems in the PS area; 2.Limited standardization of modules and equipments (basically due to their different age and to limited renovation).