PLATO Focal Plane Assemblies (FPA) Roser Urquí Centro de Astrobiología (CSIC-INTA)

Similar presentations


Presentation on theme: "PLATO Focal Plane Assemblies (FPA) Roser Urquí Centro de Astrobiología (CSIC-INTA)"— Presentation transcript:

1 PLATO Focal Plane Assemblies (FPA) Roser Urquí Centro de Astrobiología (CSIC-INTA)

2 PLATO Kick off meeting November 2010Roser Urqui2  FPA design present status  FPA development planning  Drivers:  High rigidity and mechanical stability  Low mass (32+2 units are needed!)  CCD temperature <-70 C, with passive cooling PLATO Focal Plane Assemblies (FPA)

3 PLATO Kick off meeting November 2010  A preliminary design has been produced  Design is mainly driven by interface constraints and budgets  Design refinement still on-going CCD (4x) Thermal Strap (4x) Flexi (4x) Support Ring Mask Baseplate Thermal Strap Clamp (4x) FPA design 3Roser Urqui

4 PLATO Kick off meeting November 2010 FPA design 4Roser Urqui FPA TOU

5 PLATO Kick off meeting November 2010 FPA design 5Roser Urqui CCDs (detector side, 4x) Thermal Straps (4x) Support Ring Mask

6 PLATO Kick off meeting November 2010 FPA design 6Roser Urqui Baseplate Thermal Strap Clamps (4x) CCD packages back side (4x)

7 PLATO Kick off meeting November 2010 FPA design 7Roser Urqui Support Ring Flexies (4x)

8 PLATO Kick off meeting November 2010  Current design is close to fulfill all requirements –First eigenfrequency 255 Hz (> 300 Hz) Margin still available to increase the frequency. –Mass (including 4xCCDs - 180g each) 1.49 Kg(< 1.6 Kg) If CCDs mass ~ 225 g, ~1.69 Kg –CCD Temperature <-73 ºC(<-70 ºC) –Only NORMAL FPAs considered up to now.  Interfaces –CCD-FPA Interface has already been agreed –FPA-TOU I/F still open Current interface would impose a weird design. Trade off in progress. FPA status 8Roser Urqui

9 PLATO Kick off meeting November 2010Roser Urqui9 Next steps  Design Refinement until late November –Further Mass reduction –Adapt to updated Requirements and Interfaces  Mock-Up Start of Manufacturing mid December –After CDR/MRR  Mock-Up Delivery mid March  No delays are foreseen