1 Critical Path Example: Preparing for an interview

2 Complete the precedence table Activity duration Shower3 Dry hair8 Fetch car7 Iron clothes12 Dress and make-up10 Drive to interview20

3 Precedence table Activity Immediately preceding activities duration AShower-3 BDry hairA8 CFetch car-7 DIron clothes-12 EDress and make-upB,D10 FDrive to interviewC,E20 The last activities that must be completed before an activity can begin

4 Draw Shadow Diagram AA BB CC DD EE FF

5 Shadow Diagram AA BB CC DD EE FF

6 Draw the network A E B C D FFinish Start

7 Activity Times Start F 20 E 10 B 8 A 3 D 12 C 7

8 Forward Pass Start F 20 42 22 E 10 2212 B 8 11 3 A 3 3 0 D 12 0 C 7 7 0 Minimum Time: 42 minutes

9 Forward Pass Start F 20 42 22 E 10 2212 B 8 11 3 A 3 3 0 D 12 0 C 7 7 0 Minimum Time: 42 minutes- Does this make sense?

10 Forward Pass Start F 20 42 22 E 10 2212 B 8 11 3 A 3 3 0 D 12 0 C 7 7 0 Minimum Time: 42 minutes- Unless someone else does the ironing and fetches the car, you need to do everything and hence the minimum time would be 60 minutes.

11 Backward Pass Start F 20 42 22 E 10 2212 B 8 11 3 A 3 3 0 D 12 0 C 7 7 0 42220 012 2215 12 4 1 0 0 411

12 Backward Pass Start F 20 42 22 E 10 2212 B 8 11 3 A 3 3 0 D 12 0 C 7 7 0 Critical Path: D-E-F 42220 012 2215 12 4 1 0 0 411

13 Gantt Diagram – not realistic

14 More realistic if someone else irons and fetches the car (C and D) Critical Path would be A, B, E, F