Download presentation
Presentation is loading. Please wait.
Published byDwain Simpson Modified over 8 years ago
1
f Tevatron Operations Ron Moore DOE Tevatron Operations Review March 27, 2007 SC-1 Breakout
2
f 2007 DOE Tevatron Operations Review – R. Moore 2 Since the 2006 shutdown ended… 209 HEP stores ( give/take a few…not counting ones lost before HEP) Record delivered lumi / week 24.4 → 44.9 pb -1 Record peak luminosity 180 → 292 10 30 cm -2 s -1 Record # pbars at start HEP ≈ 3072 10 9 Delivered > 1 fb -1 to CDF and D0 Run 2 total delivered now > 2.6 fb -1, recorded > 2.0 fb -1
3
f 2007 DOE Tevatron Operations Review – R. Moore 3 Run II Peak Luminosity
4
f 2007 DOE Tevatron Operations Review – R. Moore 4 2006 Tevatron Shutdown Tasks Fixed known cold leaks in E2, A3, B4; replace failed dipole in F4 Replaced all ≈1200 LHe Kautzky valves Cause of 2 magnet failures prior in Nov 06 and Feb 07 Completed reshimming on remaining 228 dipoles Needed 3 shutdowns to do! Cryostat sagging – causing coupling Unrolled quads in A3 (~10 mrad); unroll ~60 magnets with small rolls Installed 2 new separators (B48, A17), replace 3 separators (A49) Repaired TEL-1 and installed TEL-2 Pulled cables for new sextupole circuits (2 nd order chromaticity correction) Completed IPM detector installation Completed ring-wide hydrostatic level sensor installation Many smaller tasks, lots of maintenance… Smooth start-up after such a long shutdown Run II upgrades effectively complete
5
f 2007 DOE Tevatron Operations Review – R. Moore 5 Highlights since 2006 Shutdown More pbars to HEP Thanks to Pbar Source and Recycler More protons to HEP Injecting more protons Better lifetime @ 150 GeV from new helical orbit Improved luminosity lifetime Additional separators increase beam-beam separation Commission TEL-2 Spare abort gap cleaner & demonstration of beam-beam compensation Smooth orbits to desired HEP position every store Improvement on orbit stabilization Faster halo removal – save few minutes Get to HEP sooner Online luminosity fits and model comparison New tools based on SDA/SuperTable data
6
f 2007 DOE Tevatron Operations Review – R. Moore 6 Injecting More Proton and Pbars 2006 shutdown
7
f 2007 DOE Tevatron Operations Review – R. Moore 7 Improved Proton Efficiency @ 150 GeV 2006 shutdown
8
f 2007 DOE Tevatron Operations Review – R. Moore 8 Improved Proton Efficiency vs Pbar Intensity New injection helix increased separation between beams (Yu. Alexahin)
9
f 2007 DOE Tevatron Operations Review – R. Moore 9 FY07 Integrated Luminosity D32-5 failure feeder 46B fault E39/43 vacuum failure A18 vacuum leak
10
f 2007 DOE Tevatron Operations Review – R. Moore 10 Getting More Proton and Pbars to HEP 2006 shutdown
11
f 2007 DOE Tevatron Operations Review – R. Moore 11 Long-range beam-beam effects degrade lumi lifetime + integral Nearest parasitic crossings (≈59 m from IPs) especially bad Additional separators installed to allow increased separation More separation reduced beam-beam effects ~20% increase @ upstream IP Not as much @ downstream IP Luminosity lifetime improved ~20% compared to pre-shutdown Increased integrated luminosity per store (for similar luminosities and store lengths) Luminosity Lifetimes
12
f 2007 DOE Tevatron Operations Review – R. Moore 12 Comparing HEP Stores to Model without Beam-Beam After shutdown, luminosity evolution agrees better to model without beam-beam effects Most pbars lost during HEP are burned in luminosity That’s good! Protons suffer more from beam-beam effects Especially with smaller pbars V. Lebedev
13
f 2007 DOE Tevatron Operations Review – R. Moore 13 Better Lifetime More Delivered Luminosity Based on luminosity lifetime fits and adjusting to 24 hour store duration
14
f 2007 DOE Tevatron Operations Review – R. Moore 14 Bunch-by-Bunch Tune Shifts: Store 5245 Higher pbar intensities proton/pbar head-on tune shifts ≈ equal! Proton / pbar intensity ≈ 3, but proton/pbar emittance ≈ 3, too! Consistent beam intensities store-to-store is helpful operationally Otherwise, tune changes needed in advance to prevent lifetime problems Pbar intensities vary more - lost stores, problems in upstream machines, etc. Bunch leveling in Recycler also helpful for Tevatron and experiments More uniform bunch dynamics, more uniform bunch-by-bunch luminosity
15
f 2007 DOE Tevatron Operations Review – R. Moore 15 Tune Footprint Currently operate between 7/12 and 3/5 for collisions Considering moving near ½ integer
16
f 2007 DOE Tevatron Operations Review – R. Moore 16 Beam Lifetimes Pbar lifetime dominated by luminosity – good Most protons lost in non-luminous processes – not so good Luminosity [μb -1 /s] Pbar Lifetime / Expected Lifetime from Luminosity Store 5245 Proton Lifetime / Expected Lifetime from Luminosity
17
f 2007 DOE Tevatron Operations Review – R. Moore 17 Smaller Pbar Emittance Worse Proton Lifetime
18
f 2007 DOE Tevatron Operations Review – R. Moore 18 Schematic of Beam-Beam Force on Proton Bunch
19
f 2007 DOE Tevatron Operations Review – R. Moore 19 Example of Tight Tune Space for Protons Operator error – tune pushed too high Longitudinal shaving Store 5008 L = 207
20
f 2007 DOE Tevatron Operations Review – R. Moore 20 Store 5245 – Comparison to Model w/o Beam-Beam Initial Lumi = 286 μb -1 /s ~10% loss from beam-beam
21
f 2007 DOE Tevatron Operations Review – R. Moore 21 Reliability Replaced all He Kautzky valve poppets in 2006 shutdown Successfully tested higher bandwidth quench protection electronics (VFCs) Implemented in 3 houses, gradually propagate to whole ring Helps detect quench and pull abort in ≈350 μs (< 20 turns) Migrated control applications from VMS to Linux A BIG job requiring careful testing and implementation in operational environment 2 Tevatron failure-driven shutdowns since June 2006 Mouse-induced feeder glitch resulted in D3 dipole failure (Oct) Failed O-ring caused loss of E3 cryo insulating vacuum (Nov) New pbar cogging for ramp since early Jan 2007 Pbars were in the abort gap previously – quench if abort up ramp Now clear abort gap should prevent needless quenches (OK in only “trial” so far) Implement new BLM electronics to allow aborts on high beam losses Current system too inflexible – BLM aborts masked out during HEP
22
f 2007 DOE Tevatron Operations Review – R. Moore 22 Tevatron Reliability
23
f 2007 DOE Tevatron Operations Review – R. Moore 23 Integrated Lumi and Store Hours per Week 5 store running average scaled to 1 week
24
f 2007 DOE Tevatron Operations Review – R. Moore 24 Looking Ahead Implement 2 nd order chromaticity correct @ low β Correct second-order chromaticity @ low β better lifetime Also required for possible new working point (near ½ integer) Work with experiments in optimizing integrated vs peak luminosity Multiple interactions cause difficulties for trigger and tracking When is peak too high? Do we need higher intensities afforded by new working point? Other minor improvements – they all add up! Scrape (higher intensity) protons @ 150 GeV Remove beam that would be lost anyway on ramp and squeeze Get “brighter” protons to HEP Investigating new cogging between pbar injections Reduce beam-beam effects by changing locations of long-range crossings Improve proton lifetime @ 150 GeV (bunch-dependent) More reliable tune measurements New 1.7 GHz Schottky electronics designed by FNAL (LARP) for LHC (better dynamic range) New digital tune monitor to measure individual bunches (with tickling) Better helices, improved transfer line matching, faster shot-setups, etc.
25
f 2007 DOE Tevatron Operations Review – R. Moore 25 New Sextupole Circuits Move 22 elements from existing SF&SD circuits to 12 new circuits Correct 2 nd order chromaticity in low-β lattice Should reduce non-luminous proton losses Operational with new power supplies since early February Cables pulled during 2006 shutdown Still configured as “normal” chromaticity sextupoles Conducting proton-only studies to implement in final configuration New circuits to run at zero current except @ low-β Need short access to flip polarity of some elements when ready Could be operational in ~1 month Simulation results in Alex Valishev’s slides
26
f 2007 DOE Tevatron Operations Review – R. Moore 26 Luminosity Projections Refer to slides in R. Dixon’s talk Projections assume ≈100 store hrs/week on average Takes into account possible unplanned downtime (failures) Based on current pbar stacking rate, appear on track to deliver 5.5-6.5 fb -1 total Likely need increased stacking rates to go higher Approaching design 320 μb -1 /s peak luminosity Consult with experiments if higher is OK for them Goal is to maximize integrated luminosity on tape
27
f 2007 DOE Tevatron Operations Review – R. Moore 27 Integrated Luminosity Peak Pbar Stacking Rates We’re in this area now 2.6 fb -1 ≈ 22 mA/hr March ‘07
28
f 2007 DOE Tevatron Operations Review – R. Moore 28 One Example of Model Parameters In general, weekly integrated luminosity ≈ independent of store length in 20-30 hr range → flexible running schemes Pbar stacking rate important factor
29
f 2007 DOE Tevatron Operations Review – R. Moore 29 Summary Tevatron delivering record peak and delivered luminosity Great start-up following long 13-week shutdown Higher beam intensities to HEP, improved lifetime Protons suffering more from beam-beam effects Operationally challenging to stay in desired tune space when pbar intensities vary from store-to-store Implementing 2 nd order chromaticity compensation circuits Should improve lifetimes in collisions Prerequisite for investigating ½ integer working point Maximize integrated luminosity to CDF and D0 On track for 5.5-6.5 fb -1 at current pbar stacking rates Let’s find the Higgs!
30
f 2007 DOE Tevatron Operations Review – R. Moore 30 Backup Slides
31
f 2007 DOE Tevatron Operations Review – R. Moore 31 AcceleratorHighest Energy Cockroft Walton750 keV Linac400 Mev Booster8 GeV Main injector150 GeV TEVATRON980 GeV NuMI (120 GeV) MiniBoone (8 GeV) P1 Line A1 Line
32
f 2007 DOE Tevatron Operations Review – R. Moore 32 FY Integrated Luminosity
33
f 2007 DOE Tevatron Operations Review – R. Moore 33 FY07 Peak Luminosity
34
f 2007 DOE Tevatron Operations Review – R. Moore 34 FY05-FY07 Weekly Integrated Luminosity 5 store running average scaled to 1 week
35
f 2007 DOE Tevatron Operations Review – R. Moore 35 FY 2007 Average Store Hours per Week
36
f 2007 DOE Tevatron Operations Review – R. Moore 36 Machine Studies and Maintenance Averaged ≈6.5 hrs / week since last shutdown Does not include parasitic studies Exploit natural breaks in machine operation Lost stores, pbar stacks, etc. Exploit end-of-store studies Focus on specific, well-prepared studies Be efficient, prevent unnecessary quenches/downtime Start with proton-only stores before trying in HEP If we really need study time to implement something new for HEP, will get the time e.g., proton-only for commissioning new sextupole circuits
37
f 2007 DOE Tevatron Operations Review – R. Moore 37 Bunch-by-Bunch Proton Losses @ 150 GeV Lifetime of a proton bunch degrades when it has a parasitic crossing with pbar bunch near B13 Proton #1 [E9] Proton #19 [E9] Pbar Int. [E9] Pbar cog [bkts] Proton #22 [E9] Proton #34 [E9]
38
f 2007 DOE Tevatron Operations Review – R. Moore 38 New Injection Helix Increased separation at “worst” parasitic crossing blue – old red – present Parasitic Crossing Number (from B0) Separation in σ
39
f 2007 DOE Tevatron Operations Review – R. Moore 39 New Collision Helix After adding the A17H and B48V separators in 2006 shutdown blue – old red – present Distance from B0 [m] Separation in σ
40
f 2007 DOE Tevatron Operations Review – R. Moore 40 Better Lifetime More Delivered Luminosity Based on luminosity lifetime fits and adjusting to 24 hour store duration
41
f 2007 DOE Tevatron Operations Review – R. Moore 41 Separation at IPs with different cogging at injection S 1min S 2min Injection cogging n cog =61 n cog - cogging w.r.t. the collision one, n cog =0 Measured helix and optics used, reference emittance 15 mm mrad
42
f 2007 DOE Tevatron Operations Review – R. Moore 42 Beam-Beam Resonance Strengths vs Injection Cogging Nominal values @ injection n cog =61 (before change ) Collision cogging: n cog =0 n cog =-2 is the best for 7Qy n cog =10 is good for 5Qx while not bad for 7Qy 5Qx 7Qy n cog RDTs (Resonance Driving Terms) calculated for 3 amplitude Yuri Alexahin Now implemented for ramp
43
f 2007 DOE Tevatron Operations Review – R. Moore 43 Kautzky Valve Poppets During quench, pressure forces valve open, allows He to escape Poppet can break off, remain in closed position 1 similar failure in 20 years, then 2 in three months → Replaced all ≈1200 He Kautzky valve poppets during 2006 shutdown No poppet failures since replacement Closed Kautzky valve Broken poppet from B17 spool Kautzky valve
44
f 2007 DOE Tevatron Operations Review – R. Moore 44 Online Luminosity Evolution Fits Bunch-by-bunch lumi and beam intensities, too Different fit functions and results stored in database, spreadsheets, etc. Useful for Run Coordinator to determine end-of-store time
45
f 2007 DOE Tevatron Operations Review – R. Moore 45 D32-5 dipole beam tube Holes from arcing Flashover in Feeder 46B cubicle D32-5 Dipole Failure in Oct 2006 Mouse caused feeder fault Glitch → D3 quench response Dipole failed during quench Previous D3 quench 9/11/02 Failure lying in wait?
46
f 2007 DOE Tevatron Operations Review – R. Moore 46 Tevatron Electron Lenses (TEL) TEL-1 installed 2001; repaired & reinstalled 2006 Used mainly to clean abort gap Few studies demonstrating (horz) compensation on pbars (2003) Test bed for electron gun designs TEL-2 installed 2006 Used as spare abort gap cleaner Successful (vertical) tune-shifting on protons during HEP! TEL-2 TEL-2 on P12
47
f 2007 DOE Tevatron Operations Review – R. Moore 47 TEL-2 in Action TEL-2 increases proton lifetime by raising vertical tune away from 7/12 TEL-1 could do same for horz tune on leading bunches of train Little emittance growth, little/no increase in losses Currently doing studies with TEL-1 while TEL-2 cleans abort gap Could try simultaneous operation to level bunch tunes to help lifetime TEL-2 Marx generator suffers from radiation damage – added steel shielding TEL-2 ON P12 TEL-2 off P12/24/36 lowest vertical tune (PACMAN) P12 intensity [E9] P36 intensity [E9]
48
f 2007 DOE Tevatron Operations Review – R. Moore 48 IPM Detectors installation completed during 2006 shutdown Waiting for full complement of production electronics Observed TBT quadrupole oscillations on injection Will improve transfer line matching, emittance dilution Protons & Pbars at Injection Proton Bunch Injection Oscillations Turn # 0 20 1 2 RMS size [mm]
49
f 2007 DOE Tevatron Operations Review – R. Moore 49 Peak Luminosity Peak Pbar Stacking Rates
50
f 2007 DOE Tevatron Operations Review – R. Moore 50 Delivered Luminosity per Week Peak Pbar Stacking Rates
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.