CHAPTER 3 Aggregate Planning McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved.

Similar presentations


Presentation on theme: "CHAPTER 3 Aggregate Planning McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved."— Presentation transcript:

1 CHAPTER 3 Aggregate Planning McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved.

2 Introduction to Aggregate Planning uGoal: To plan gross work force levels and set firm- wide production plans. Concept is predicated on the idea of an “aggregate unit” of production. May be actual units, or may be measured in weight (tons of steel), volume (gallons of gasoline), time (worker-hours), or dollars of sales. Can even be a fictitious quantity. (Refer to example in text and in slide below.) 3-2

3 Overview of the Problem Suppose that D 1, D 2,..., D T are the forecasts of demand for aggregate units over the planning horizon (T periods.) The problem is to determine both work force levels (W t ) and production levels (P t ) to minimize total costs over the T period planning horizon. 3-3

4 Important Issues uSmoothing. Refers to the costs and disruptions that result from making changes from one period to the next. uBottleneck Planning. Problem of meeting peak demand because of capacity restrictions. uPlanning Horizon. Assumed given (T), but what is “right” value? Rolling horizons and end of horizon effect are both important issues. uTreatment of Demand. Assume demand is known. Ignores uncertainty to focus on the predictable/systematic variations in demand, such as seasonality. 3-4

5 Relevant Costs uSmoothing Costs uchanging size of the work force uchanging number of units produced uHolding Costs uprimary component: opportunity cost of investment uShortage Costs uCost of demand exceeding stock on hand. Why should shortages be an issue if demand is known? uOther Costs: payroll, overtime, subcontracting. 3-5

6 Aggregate Units Aggregate Units The method is based on notion of aggregate units. They may be uActual units of production uWeight (tons of steel) uVolume (gallons of gasoline) uDollars (Value of sales) uFictitious aggregate units 3-6

7 Example of fictitious aggregate units. Example 3.1) One plant produced 6 models of washing machines: Model # hrs. Price % sales A 55324.228532 K 42424.934521 L 98985.139517 L 38005.242514 M 26245.452510 M 38805.872506 Question: How do we define an aggregate unit here? 3-7

8 Example continued uNotice: Price is not necessarily proportional to worker hours (i.e., cost): why? uOne method for defining an aggregate unit: requires:.32(4.2) +.21(4.9) +... +.06(5.8) = 4.8644 worker hours. Forecasts for demand for aggregate units can be obtained by taking a weighted average (using the same weights) of individual item forecasts. 3-8

9 Prototype Aggregate Planning Example (this example is not in the text) The washing machine plant is interested in determining work force and production levels for the next 8 months. Forecasted demands for Jan-Aug. are: 420, 280, 460, 190, 310, 145, 110, 125. Starting inventory at the end of December is 200 and the firm would like to have 100 units on hand at the end of August. Find monthly production levels. 3-9

10 Step 1: Determine “net” demand. (subtract starting inv. from per. 1 forecast and add ending inv. to per. 8 forecast.) MonthNet PredictedCum. Net Demand Demand 1(Jan)220220 2(Feb)280500 3(Mar)460960 4(Apr)190 1150 5(May)3101460 6(June)1451605 7(July)1101715 8(Aug)2251940 3-10

11 Step 2. Graph Cumulative Net Demand to Find Plans Graphically 3-11

12 Constant Work Force Plan Suppose that we are interested in determining a production plan that doesn’t change the size of the workforce over the planning horizon. How would we do that? One method: In previous picture, draw a straight line from origin to 1940 units in month 8: The slope of the line is the number of units to produce each month. 3-12

13 Monthly Production = 1940/8 = 242.2 or rounded to 243/month. But: there are stockouts. 3-13

14 How can we have a constant work force plan with no stockouts? Answer: using the graph, find the straight line that goes through the origin and lies completely above the cumulative net demand curve: 3-14

15 From the previous graph, we see that cum. net demand curve is crossed at period 3, so that monthly production is 960/3 = 320. Ending inventory each month is found from: Month Cum. Net. Dem. Cum. Prod. Invent. 1(Jan)220 320 100 2(Feb)500 640 140 3(Mar)960 960 0 4(Apr.) 1150 1280 130 5(May) 1460 1600 140 6(June) 1605 1920 315 7(July) 1715 2240 525 8(Aug) 1940 2560 620 3-15

16 But - may not be realistic for several reasons: uIt may not be possible to achieve the production level of 320 unit/mo with an integer number of workers uSince all months do not have the same number of workdays, a constant production level may not translate to the same number of workers each month. 3-16

17 To overcome these shortcomings: uAssume number of workdays per month is given uK factor given (or computed) where K = # of aggregate units produced by one worker in one day 3-17

18 Finding K uSuppose that we are told that over a period of 40 days, the plant had 38 workers who produced 520 units. It follows that: uK= 520/(38*40) =.3421 = average number of units produced by one worker in one day. 3-18

19 Computing Constant Work Force Assume we are given the following # working days per month: 22, 16, 23, 20, 21, 17, 18, 10. March is still critical month. Cum. net demand thru March = 960. Cum # working days = 22+16+23 = 61. Find 960/61 = 15.7377 units/day implies 15.7377/.3421 = 46 workers required. 3-19

20 Constant Work Force Production Plan Mo # wk days Prod. Cum Cum Nt End Inv Level Prod Dem Jan 22 346 346 220 126 Feb 16 252 598 500 98 Mar 23 362 960 960 0 Apr 20 315 1275 1150 125 May 21 330 1605 1460 145 Jun 22 346 1951 1605 346 Jul 21 330 2281 1715 566 Aug 22 346 2627 1940 687 3-20

21 Addition of Costs uHolding Cost (per unit per month): $8.50 uHiring Cost per worker: $800 uFiring Cost per worker: $1,250 uPayroll Cost: $75/worker/day uShortage Cost: $50 unit short/month 3-21

22 Cost Evaluation of Constant Work Force Plan uAssume that the work force at end of Dec was 40. uCost to hire 6 workers: 6*800 = $4800 uInventory Cost: accumulate ending inventory: (126+98+0+...+687) = 2093. Add in 100 units netted out in Aug = 2193. Hence Inv. Cost = 2193*8.5=$18,640.50 uPayroll cost: ($75/worker/day)(46 workers )(167days) = $576,150 uCost of plan: $576,150 + $18,640.50 + $4800 = $599,590.50 3-22

23 Cost Reduction in Constant Work Force Plan In the original cum net demand curve, consider making reductions in the work force one or more times over the planning horizon to decrease inventory investment. 3-23

24 Cost Evaluation of Modified Plan uI will not present all the details here. The modified plan calls for reducing the workforce to 36 at start of April and making another reduction to 22 at start of June. The additional cost of layoffs is $30,000, but holding costs are reduced to only $4,250. The total cost of the modified plan is $467,450. 3-24

25 Zero Inventory Plan (Chase Strategy) uHere the idea is to change the workforce each month in order to reduce ending inventory to nearly zero by matching the workforce with monthly demand as closely as possible. This is accomplished by computing the # units produced by one worker each month (by multiplying K by #days per mo.) and then taking net demand each month and dividing by this quantity. The resulting ratio is rounded up and possibly adjusted downward. 3-25

26 I got the following for this problem: Period # hired #fired 1 10 Cost of this 1 10 Cost of this 2 20 plan: 2 20 plan: 3 9 $555,704.50 3 9 $555,704.50 4 31 4 31 5 15 5 15 6 24 6 24 7 4 7 4 8 15 8 15 3-26

27 Optimal Solutions to Aggregate Planning Problems Via Linear Programming 3-27 uLinear Programming provides a means of solving aggregate planning problems optimally. The LP formulation is fairly complex requiring 8T variables and 3T constraints, where T is the length of the planning horizon. Clearly, this can be a formidable linear program. The LP formulation shows that the modified plan we considered with two months of layoffs is in fact optimal for the prototype problem. uRefer to the latter part of Chapter 3 and the Appendix following the chapter for details.


Download ppt "CHAPTER 3 Aggregate Planning McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved."