Bent 2 – Static Testing Program and Instrumentation Hugo Escobar, Ali Morovat, and Sharon Wood Department of Civil, Architectural and Environmental Engineering.

Similar presentations


Presentation on theme: "Bent 2 – Static Testing Program and Instrumentation Hugo Escobar, Ali Morovat, and Sharon Wood Department of Civil, Architectural and Environmental Engineering."— Presentation transcript:

1 Bent 2 – Static Testing Program and Instrumentation Hugo Escobar, Ali Morovat, and Sharon Wood Department of Civil, Architectural and Environmental Engineering University of Texas at Austin

2 Testing Program – Spring 2006 Overview ―Free-vibration response (modal hammer tests) ―Forced-vibration response (T-Rex) ―Static lateral forces (T-Rex and Liquidator) Additional Instrumentation for Static Tests ―String potentiometers (lateral deflections) ―Linear potentiometers (vertical deformation at ends of columns)

3 Static Testing Program Both static and dynamic tests were conducted to evaluate how the frequency response and damping of the bent varied with the level of damage in the soil, foundation, and structure Lateral forces were applied using the winches attached to the front of T-Rex and Liquidator Due to the location of Bent 2 relative to the property line, lateral forces could only be applied in one direction.

4 Test Designation Each test is numbered from 001 to 043. Between tests 001 and 029, the following sequence was used: ―Free-vibration tests ―Forced-vibration tests ―Static lateral forces Between tests 030 and 043, the following sequence was used: ―Free-vibration tests ―Static lateral forces Liquidator was used to apply the static lateral forces in these tests. Both Liquidator and T-Rex were used to apply the static lateral forces in these tests.

5 Free-Vibration Test

6 Impact Locations for Modal Hammer Tests Project North Location B Location A 2S 2N y z y x

7 Forced-Vibration Test

8 ~ 24 ft

9 Static Lateral Forces (Tests 007 – 029)

10 Liquidator ~ 50 ft Project North 2S 2N Load Cell Reference Frame Static Lateral Forces (Tests 007 – 029)

11

12

13 Load Cell

14

15 Static Lateral Forces (Tests 032 – 043)

16 Project North 2S 2N Load Cell Reference Frame Liquidator T-Rex ~50 ft Load Cell

17

18

19 External Reference Frame 12 in. (1.0 ft) 24 in. (2.0 ft) 45 in. (3.75 ft) Base (0.0 ft) 3.75W3.75E 2.0 0N0S 1.0

20 3.75W 3.75E 2.0 0N 0S 1.0 String Potentiometers

21 3.75W 3.75E 2.0 0N 1.0

22 Linear Potentiometers Column 2NColumn 2S North Top North Bottom South Top South Bottom North Top North Bottom South Top South Bottom

23 Column 2S South, Top Column 2S South, Bottom

24 Column 2N North, Top Column 2N North, Bottom Column 2S North, Bottom