Consultation seminar on the preparation of full Application Form for LSP 6 December 2011, Tartu Consultation seminar on the preparation of full Application.

Similar presentations


Presentation on theme: "Consultation seminar on the preparation of full Application Form for LSP 6 December 2011, Tartu Consultation seminar on the preparation of full Application."— Presentation transcript:

1 Consultation seminar on the preparation of full Application Form for LSP 6 December 2011, Tartu Consultation seminar on the preparation of full Application Form for LSP 6 December 2011, Tartu Environmental Impact Assessment 1

2 EIA - Steps Development of project (incl. technical documentation) Scoping (what should be done?) Decision on EIA needed or not Development concent Environmental impact study Public consultations Decision Approval Public information

3 EU Member states Council Directive of 27 June 1985 on the assessment of the effects of certain public and private projects on the environment (85/337/EEC) and ANNEXES Partner countries Espoo Convention on Environmental Impact Assessment in a transboundary context, done at Espoo (Finland), on 25 February 1991 and ANNEXES Similar provisions in both BUT description in Espoo convention is quite general, so the Directive should also be used as reference for the level of details requested for projects in Partner countries Legal acts

4 Applies to ”projects”: Execution of construction works or of other installations or schemes Other interventions in the natural surroundings and landscape including those involving the extraction of mineral resources Identify, describes and assess the direct and indirect effects of a project on the following factors: human beings, fauna and flora soil, water, air, climate and the landscape material assets and the cultural heritage the inter-action between the factors mentioned above EIA - definition

5 Not needed or Needed – mandatory or Screening to determine whether EIA is needed Using speciffic criteria, e.g. cumulating with other projects, location, etc. If needed: Before the project is approved by programme Except the design-and-build works (when technical documentation can be prepared only at later stage) Decision on EIA

6 Developer The entity elaborating the project Competent authorities Decide on development consent applications Are not necessarily environmental authorities Environmental authorities Have specific environmental responsibilities Are consulted by competent authorities EIA - roles

7 Development of project, including technical documentation Responsibility: Project developer Decision on whether an EIA is needed (mandatory or by screening) Responsibility: Project developer in consultation with competent authority issuing the consent (not necessarily environmental authority) and environmental authority Scoping – answering to the question “what should be covered by the environmental information?” Responsibility: Project developer EIA - roles

8 Request of development consent from a competent authority Responsibility: Project developer Environmental Impact Study which would also examine the alternatives A non-technical summary understandable by the general public should also be prepared Responsibility: Project developer and/or specialised entities EIA - roles

9 Public consultations Responsibility: Project developer in consultation with competent authority and environmental authority Decision, including the reasons for taking it and explanations on what kind of measures were used to consult The project developer should explain how the results of the consultations were taken into account in the final version of the project Responsibility: Project developer in consultation with competent authority and environmental authority EIA - roles

10 Approval of the project Responsibility: competent authority Public information on the decision Responsibility: Project developer EIA - roles

11 Answers the question: is EIA required? The guiding principle: are significant environmental effects likely? If yes – EIA needed If no – no EIA needed IMPORTANT: Screening determination made available to the public Screening

12 1.Project characteristics size, cumulation with other projects, natural resources use, waste production, pollution, risk of accidents … 2.Project location - environmental sensitivity of area likely to be affected: Land use Natural resources Absorption capacity of natural environment Screening

13 3. Potential impact in relation to 1 and 2 extent of impact, transfrontier nature, probability of impact, magnitude and complexity duration, frequency, reversibility... Screening

14 Answers the question “what should be covered by the environmental information?” Opinion by the competent authority (who may subsequently ask for further information) By request of developer Before development consent application is submitted Early interaction between competent authority, developer, environmental authorities Scoping

15 Project description Use of resources, emissions and residues Description of the environment likely to be significantly affected Likely significant environmental effects including: short term, temporary and cumulative effects Forecasting methods & difficulties Mitigation measures Main alternatives and reasons for choice taking account of environmental effects Non-technical summary of ALL RELEVANT INFO Study

16 Public consultations: As wide as possible, not just public institutions Reasonable criteria for defining the public consulted Information published for a reasonable length of time (taking into account holiday periods) Public consultations

17 Neighbouring country can inquire on the infrastructures close to the border, or affecting them in other ways, and also to launch public consultations in their country As it could have a significant impact on the other side, although causing no negative effect on the side of the Beneficiary It is therefore suggested that both sides of the border are involved as much as possible, transboundary consultations organised Dialogue between the competent authorities from both sides of the border to be ensured Transboundary EIA

18 Further Information JOINT TECHNICAL SECRETARIAT Phone: +371 6750 9520 Fax: +371 6750 9523 E-mail: info@estlatrus.euinfo@estlatrus.eu Ausekļa Street 14 – 3 rd Floor, Riga, LV-1010, Latvia

19 19 Thank You for attention!