1 This presentation will probably involve audience discussion, which will create action items. Use PowerPoint to keep track of these action items during your presentation In Slide Show, click on the right mouse button Select “Meeting Minder” Select the “Action Items” tab Type in action items as they come up Click OK to dismiss this box This will automatically create an Action Item slide at the end of your presentation with your points entered. Levan Babukhadia D  Collaboration Meeting, October 11 - 13, 2000, Fermilab http://www-d0.fnal.gov/~blevan Status of the L1 Trigger SUNY at Stony Brook

2 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia CTPT/FPS Components –Analog (Fermilab - DØ) AFE-8MCM (primarily CFTax): –10 here, ready by 11/01, 54 more by 12/15, balance 01/30/01 Crates/Cables on hand, installed when required Power supplies delayed until new year (partial). –Mixer ( Fermilab - CD ) –Super-sector (1/5th) mid-November –Full Mixer 1/01 –Digital ( Fermilab - DØ ) –All MBs here and in testing –Transition boards expecting in ~2 weeks –CTPT DBs (single-wide, 5 Virtex 2.5v FPGAs) by mid-November –FPS DBs (double-wide, 3 Virtex 2.5v FPGAs) partial order out –Xilinx/Virtex FPGAs for CTOT on order, others held until further decision, Virtex vs. Virtex-E –Crates/Cables/PS all here by mid-November

3 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia CTTP/FPS Firmware: CFT/CPS Axial –DFEA (80) : Jamieson Olsen (Kin is gone) Both L1/L2 firmware in good shape 4 FPGAs find tracks in 4 Pt and report to 5-th FPGA and to Muon Backend (5-th) FPGA does CPS cluster finding and track matching –firmware has to be re-written, concerns on the chip size –expect functional and tested firmware in a couple of months –CTOC (8) : Juan Lizarazo, now Ricardo Rodrigez Both L1/L2 firmware completed and tested in testbench Minor issues and additions will be addressed by Ricardo/Manuel –CTQD (4) : Pavel Polozov now gone L2CFT part completed functionally with some minor issue Needs implementation, L2CPS, and all of this tested in the hardware –CTTT (1) : Jerry Blazey Algorithm/VHDL/Functional/Implementation at ~20% 2 out of 64 Trigger Terms done through the implementation phase L1->L3 sender, finish all VHDL, implementation, hardware test stand

4 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia CTTP/FPS Firmware: CPS Stereo –DFES (5) : Qichun Xu, MSU No link to L1 TM, straight to L2 and L3, thus has time! Main issue is cluster finding in the large number (~500) of CPS stereo strips in a sector but having time may save the day... New MSU student Qichun Xu, just started –Made a good head-start with an overall algorithms and the cluster finding algorithms in particular Start writing VHDL, expect functional code in about 1-2 months –CPSS (2) : ?! Nobody yet! Perhaps Qichun will take on this one as well...

5 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia CTTP/FPS Firmware: FPS –DFEF (32) : Levan Babukhadia Challenge: cluster finding in 144 FPS strips at the L1 rate L1 U/V algo developed, coded, and implemented; test stand is next –L1U and L1V each takes Xilinx/Virtex 400 FPGA (~75%, 63 MHz) Develop L2 priority reporting algo to take care of truncation. It is aimed at the 3rd FPGA –Transferring clusters within a DB or find clusters anew?... –FPSS (4) : Mrinmoy Bhattacharjee L1 algo developed, coded, and implemented w/o the L3 sender –fits in one Xilinx/Virtex 400 FPGA (~30%, 66 MHz) Develop L2 algorithm –FPTT (1) : Satish Desai L1 algo developed, coded, and implemented w/o the L3 sender –fits in one Xilinx/Virtex 400 FPGA (~20%, 64 MHz) Complete all L1 functionally, test stand by the end of October

6 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia CTPT/FPS Installation/Commissioning Assembling test stands for digital/VHDL testing –Hardware: 2 PCs, MBs, 2 Data Pump Boards, PS, cables, CTPT/FPS DBs »1 fully stuffed double-wide DB »10 fully stuffed single-wide DBs –Personnel: Jamieson Olsen, Brian Connolly (very short time), Ricardo Rodrigez, and a new part-time tech –Had 1 working test stand but recently moved to DAB3/NE; will be made operational this week –Aiming at having 2 “single board” bench-tops and 1 “multi-board” test stand (for a one sparse system test -- available now, Jamieson) Installing cables/crates on platform Crates/Cables installed in MCH

7 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia –Components Scintillator (48) complete CAFÉ boards (175) on hand Completing ADC (~12) board layout, ordering parts Vertex board, FPGA 75% complete, layout commencing Procuring signal cables (~60) soon Crate/PS on hand –Installation/Commissioning Installed scintillator (4/00) Cabling awaits FPS, commissioning thereafter –Software/Firmware Working on embedded software Download currently underway Database under development –Schedule (on time) Electronics installed, February 1; Lum Monitoring March 1 And/Or terms, March-April Luminosity Monitor Status

8 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia –Timing signal generation and distribution Some work has been done and some tests have been made Initial implementation will probably cover just the CC racks –L2/L3 readout complete (by November) Uses much of the same equipment as the readout from the TF All circuit boards exist and initial designs of all the FPGAs exist –Analog input circuit (pick-off) boards (320) Prototypes of this exist and some testing has been done 1FTE month to production –Quadrant Terms Circuit board (40) and FPGA design work has been started No prototypes exist yet Will not be pushed in the immediate future –Schedule (late but well before 3/01) Inactive until TF complete 11/00. Resume within a month Start with analog pick-offs L1 Calorimeter Trigger Status

9 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia  L1MU Hardware (4 crates, prod beginning UAz) –Crate Manager (MTCM) Production card testing in progress –Motherboard (MTCxx - Trigger Card) Production cards beginning fabrication –Flavor Boards Production Trigger Manager (MTM) boards ready for fabrication Production wire DB (MTC10) design in progress (finish in ~2 weeks) Preproduction scintillator DB (MTC05) in fabrication –SLDBs (Gbit/s Serial Links) Production board testing in progress  Software/Firmware –Download infrastructure in place –Preproduction versions of all firmware exist –No alarms, monitoring L1 Muon Trigger Status

10 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia  MCEN Hardware (5 crates, in preprod testing BU) –Crate Manager (MCCM) Preproduction card layout in progress –Centroid Finder Cards (MCEN) Preproduction card testing in progress –Physics Boards (MCPB) Preproduction board testing in progress  Infrastructure –Custom VME backplanes completed –Power supplies Prototype assembled and tested VICOR supplies ordered but with 20-22 week lead time –Platform Services -- on hold pending final cable plant design –Cabling (~1,600) Production at Fermilab and NIU in progress L1 Muon Trigger Status

11 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia  Near Term Commissioning Goals –Mid-August Stable operation of one (sparse) L1MU trigger crate and the L1MU MTM crate –still using preproduction cards –Early October Add L1CTPT MTM crate to the above –Mid-October Begin commissioning production of L1MU crates and cards  Longer Term Commissioning Goals –Begin full crate testing in late Dec or early Jan Two octant triggering until then MCEN cards ~2 months behind above Temporary power supplies for full crate tests L1 Muon Trigger Status

12 DØ Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia –All equipment operational and installed Defective SCL cables are being repaired –L3 readout Finish up making readout to L3 available for normal use (by 1/11) –Master Clock synchronization with the Tevatron beam This work now starting –Operational permit Need to install 5 fuse blocks and write the documentation –L1 Specific Trigger Fired Mask to L2 Needed to make the Pseudo-Terms work Deferred until some progress on getting L1 Cal Trigger running again –Firmware Completion of pseudo-terms Commissioning run-control –Personnel Major loss of two engineers. Replacement uncertain Trigger Framework Status