NIU Trigger Workshop CTT Commissioning Trigger Workshop October 22, 1999 WBS 1.1.5.3 & 1.4.3.3 Presented by Fred Borcherding for the D0 Electronics Group.

Similar presentations


Presentation on theme: "NIU Trigger Workshop CTT Commissioning Trigger Workshop October 22, 1999 WBS 1.1.5.3 & 1.4.3.3 Presented by Fred Borcherding for the D0 Electronics Group."— Presentation transcript:

1 NIU Trigger Workshop CTT Commissioning Trigger Workshop October 22, 1999 WBS 1.1.5.3 & 1.4.3.3 Presented by Fred Borcherding for the D0 Electronics Group

2 NIU Trigger Workshop Fred B. - Oct 22, 1999 2 Charge for the Workshop For each of the NIU sessions, we would like to have some prepared talks to cover the following: 1. Schedule of completion of the hardware 2. Test program at the board level (who, where, when?) 3. Test/commissioning of the sub-detector trigger or framework prior to commissioning in the D0 environment in the D0 Hall. (who, where, when?) what other resources are needed (serial links, downloads, COOR, clocks, etc.) 4. Commissioning in D0. What is the sequence, time estimate for the commissioning? How will cosmic ray studies be used? What interactions with other systems are required? Give an estimated schedule for commissioning.

3 NIU Trigger Workshop Fred B. - Oct 22, 1999 3 CTT Project  Four separate installations u CFT Axial u CFT Stereo u CPS Axial u CPS Stereo u (FPS)  Several Steps u Production u Board Test u System Test u Installation u ‘In Place’ Commissioning u Run

4 NIU Trigger Workshop Fred B. - Oct 22, 1999 4 System Size CTT has three sets of boards. CTT has a total of about 10 ‘boards’ CTT has very small signal Analog boards target of 5 fC threshold CTT has very high IO digital boards each DFE has ~15Gbits/sec input each MB has ~20Gbits/sec input & output AFE Board 8-MCM board 12-MCM board MCM daughter card Analog Input board DFE Board Mother board Transition board Daughter Boards Testing DB Tracking ( & cluster finding) collector (octant) DB2 MB Mixing Box Board Input board Output board MB Test Board

5 NIU Trigger Workshop Fred B. - Oct 22, 1999 5 Schedule of completion of the hardware CFT 8* Boards Manufactured 2/1/00 AFE [8-MCM] (8) 12/1/99 Seq/SeqC/VRB/VRBC 1/3/00 DFE+TDB (4) 3/6/00 CDB (1) 3/22/00 DB2 (1) 3/6/00 MB (1set) All Boards Manufactured 7/28/00 AFE [8-MCM] 12/1/99 Seq/SeqC/VRB/VRBC 5/1/00 DFE+TDB 7/3/00 CDB 7/14/00 DB2 7/10/00 MB FPS 8* Boards Manufactured 4/20/00 AFE [12-MCM] (4) 12/1/00 Seq/SeqC/VRB/VRBC 2/7/00 DFE+TDB (1) 4/3/00 CDB (1) 4/24/00 DB2 (1) All Boards Manufactured 7/28/00 AFE [12-MCM] 12/1/00 Seq/SeqC/VRB/VRBC 6/5/00 DFE+TDB 7/28/00 CDB 7/28/00 DB2 CPS 8* Boards Manufactured 4/20/00 AFE [12-MCM] (4) 12/1/00 Seq/SeqC/VRB/VRBC 2/7/00 DFE+TDB (1) 4/3/00 CDB (1) 4/24/00 DB2 (1) All Boards Manufactured 7/28/00 AFE [12-MCM] 12/1/00 Seq/SeqC/VRB/VRBC 6/5/00 DFE+TDB 7/28/00 CDB 7/28/00 DB2 NOTE: All dates subject to change

6 NIU Trigger Workshop Fred B. - Oct 22, 1999 6 Test program at the board level- WHO. AFE Board 8-MCM boardJohn A, Pat S, Paul R, Mike M, Stefan G; 12-MCM boardJohn A, Pat S, Paul R, Mike M, Stefan G; MCM daughter cardJohn A, Pat S, Paul R, Mike M; Analog Input board John A, Pat S, DFE Board Mother boardJ Olsen, Pat S, Transition boardJ Olsen, Pat S, Daughter Boards Special Testing board J Olsen, Kin Y Tracking ( & cluster finding) J Olsen, Kin Y, Stefan G, collector (octant) J Olsen, Manuel M, Juan L, Brian DB2J Olsen, Manuel M, Juan L, Brian MB Mixing Box Board Input boardJ Olsen, M Vaz, Other? Output boardJ Olsen, M Vaz, Other? Test board J Olsen, M Vaz

7 NIU Trigger Workshop Fred B. - Oct 22, 1999 7 Test program at the board level- WHERE and WHEN. AFE Board 8-MCM boardDAB3 Analog Test StandMar-Jun 12-MCM boardDAB3 Analog Test StandMay-Aug MCM daughter cardDAB3 Analog Test StandMay-Aug DFE Board Mother boardDAB3 Digital Test StandDec-Mar Transition board DAB3 Digital Test StandDec-Mar Daughter Boards Tracking ( & cluster finding) DAB3 Digital Test StandJan-Apr collector (octant) DAB3 Digital Test StandMar-Jun DB2 & others DAB3 Digital Test StandApr-Jul MB Mixing Box Board Input board DAB3 Digital Test StandJul-Aug Output board DAB3 Digital Test StandJul-Aug

8 NIU Trigger Workshop Fred B. - Oct 22, 1999 8 Board Testing  AFE > 8 MCM u bench test - AnTS u (on cassette in lab 3)  AFE > 12 MCM u bench test - AnTs u (on cassette in lab 3)  DFE u bench test - DTS  Mixing Box u bench test - DTS u The AFE testing @ lab3 requires s working cassettes s light pulser system w VTBG s Seq/SeqC/VRB/VRBC s trigger generation logic s 1553 links s PC / bit3

9 NIU Trigger Workshop Fred B. - Oct 22, 1999 9 Board Testing cont.  The DFE testing requires u input pattern generator s test patterns s tracks u output pattern analyzer u download link u 1553 link u PC / Bit3  The MB testing requires u input pattern generator s test patterns s tracks u DFE for output analysis u PC / Bit3  The AFE testing requires u input pattern generator u DFE for output analysis u download link u SASEQ u VTBG system u 1553 links u Bit3 / PC

10 NIU Trigger Workshop Fred B. - Oct 22, 1999 10 AFE Board Testing  Some AFE production boards will be tested @ lab3 stand u Test with ‘real’ inputs u Test with more realistic grounding and noise environment u Test cryo and bias supply functions  Note: [MCM are tested prior to mounting on AFE]  Bench test requires development of analog input method u Low amplitude charge injection s VTBG System s Input conversion u HD connection that can survive 200 boards s FLEX type cable s mated to VTBG

11 NIU Trigger Workshop Fred B. - Oct 22, 1999 11 DFE Board Testing  Special Test Daughter board produced u High speed “Data Pump” db generates patterns and fake event data, and checks the output of the DFE  Each of the different Daughter board types will require different test firmware/PC software  Mother board, Transition board, and daughter board sets are tested.

12 NIU Trigger Workshop Fred B. - Oct 22, 1999 12 MB Board Testing  The ‘Mixing Box Test Board’ serves as input pattern generator and output analyzer u high rate input source u provides high speed and high bandwidth lvds loopback testing  Share PC and test stand with DFE  Bench test requires u Test pattern input board u Test pattern receiver board u Test generation software u Test analysis software

13 NIU Trigger Workshop Fred B. - Oct 22, 1999 13 Test/commissioning of the sub-detector 3. Test/commissioning of the sub-detector trigger.. prior to commissioning in the D0 environment in the D0 Hall. (who, where, when?) what other resources are needed (serial links, downloads, COOR, clocks, etc.)

14 NIU Trigger Workshop Fred B. - Oct 22, 1999 14 Sub-Detector  The CTT systems test/commission in THREE stages 1 - Analog + L3 Readout 2 - Digital (trigger) 2.1 - DFE alone 2.2 - DFE + L1MUON [CFT] 2.3 - DFE + Collector 2.4 - DFE + … + L2pp & L1MTM 2.5 - MB + DFE 3 - Complete System [+ MB for CFT] Stage 1 and Stage 2 can be concurrent!

15 NIU Trigger Workshop Fred B. - Oct 22, 1999 15 Stage 1  Test AFE and L3 Readout chain  Test lvds links - test fixture is DFE+DB with special firmware

16 NIU Trigger Workshop Fred B. - Oct 22, 1999 16 Stage 1 - AFE  Hardware u Test Stand u Dummy Cassette u VTBG, Input Brd (pulser) u AFE Boards u Sequencer, Crate, Cont. u VRB, Crate, Cont. u DFE + daughter  Software u PC Software for control [a la MCM test software] u AFE board firmware u special DFE board based test firmware  Procedure u Download to SVX on AFE u Read SVX cal-inj patterns u Read ‘pulser’ inputs  Milestones u successful download u see all input channels in SVX data u see all input channels on DFE board with special test firmware

17 NIU Trigger Workshop Fred B. - Oct 22, 1999 17 Stage 2  Work in the trigger end of the system u Test Generator / Receiver is MB test board u Actual MB inserted before DFE for stage 2.5

18 NIU Trigger Workshop Fred B. - Oct 22, 1999 18 Stage 2 - DFE  Hardware u DFE Boards u L1 MUON cables u L1 MUON ‘test’ receiver u Test Generator / Receiver  Software u Test Generator firmware s Need Track Loader software (person) here u Download DFE u 1553 I/O to DFE u PC control and analysis  Procedure u Download to DFE crate and boards u Run Test Generator u Monitor DFE output u Monitor Collector etc. u Monitor L1 Muon  Milestones u successful download u Data seen from DFE u Data seen at L1Muon u Data seen from collector etc.

19 NIU Trigger Workshop Fred B. - Oct 22, 1999 19 Stage 3 - Final Stage  CFT/CPS Axial version with mixing box  FPS/CPS Stereo without

20 NIU Trigger Workshop Fred B. - Oct 22, 1999 20 Stage 3 - Final Stage  Hardware u Combine AnTS to DTS  Software u Same functionality as at Test Stand PCs u But now link the two  Procedure u Same as Stage 2  Milestones u See all Stage 1 and 2 milestones on the combined system

21 NIU Trigger Workshop Fred B. - Oct 22, 1999 21 Commissioning in D0. 4. Commissioning in D0. What is the sequence, time estimate for the commissioning? How will cosmic ray studies be used? What interactions with other systems are required? Give an estimated schedule for commissioning.

22 NIU Trigger Workshop Fred B. - Oct 22, 1999 22 Cosmic Ray Trigger  Trigger on CR that penetrates to center of CFT u require MUON on inward track u require track through beam pipe with CFT  Can trigger down to ~0.5GeV in tracker(?) u Trigger elements s uScintOctant s CFT A-layer-back- to-back s other CFT layers to fine-tune rate u Timing s run at 396-132 s live for CFT window - 80of396ns or 20% u Tests s L3 track finding s L2 trigger s L1 trigger Similar Trigger forward with FPS & Forward Muon?

23 NIU Trigger Workshop Fred B. - Oct 22, 1999 23 ‘In Place’ Commissioning  Four Separate Systems can proceed independently  Each of the systems is commissioned in 3 Stages - u same as sub-system commissioning outlined earlier u Each stage adds more hardware u Each stage requires more software  A 4th stage - CR running - added with no special hardware  NOW Host software is ON-LINE  Can start with ‘one crate’  Can finish within one month after last crate u or about 3-4 months total time (whichever is longer)

24 NIU Trigger Workshop Fred B. - Oct 22, 1999 24 Overall Software Needs  KISS Applies u keep it simple  Have different types of users u technicians u engineers u physicists  Have different environments u Stand alone bench tests u sub-dectector u as part of full detector u possible CR running  Have different goals u test/fix/maintain individual boards u develop system expertise u test/fix/maintain full system

25 NIU Trigger Workshop Fred B. - Oct 22, 1999 25 Software cont.  Bench Tests u traditionally used PC, bit3 and windows /excel based software u need users (technicians & engineers) to be able to understand and modify software  Full system tests u want to run within full D0 system u run Examine’s and Calib’s with ON-LINE  Partial systems u gray area between bench and full system u in use / development at lab 3

26 NIU Trigger Workshop Fred B. - Oct 22, 1999 26 Infrastructure Required  Bench Tests u PC u Trigger / clock generator u Input generator u Output capture u Group will provide s software / firmware s test fixtures s procedures u Need - s Physicists for system design / data analysis s PC based software help

27 NIU Trigger Workshop Fred B. - Oct 22, 1999 27 Infrastructure Required * Need new bodies for these outside of present group  Full system tests u trigger generation u SCL (clock and control) u DAQ u Online u Group will provide s special trigger generator hardware s test fixtures u D0 provides s online system and software s examine and calib shells u Need* s MC Track generation software s MC Cluster generation software s (for CR) found-tracks to survey to new trigger-equations s Examine & calib software s help with special firmware

28 NIU Trigger Workshop Fred B. - Oct 22, 1999 28 Summary  Hardware will arrive relatively late  Much work between production of hardware and running  A lot of support and fixture hardware needs to be designed and built - Schedules will suffer without needed EE support.  A lot of support software needs to be written, and shaken out - Schedules will suffer without needed PH support.