WSDOT Design Build Contracting – an innovative partnership Society of American Military Engineers September 16, 2014 Phil Fordyce, P.E. WSDOT.

Similar presentations


Presentation on theme: "WSDOT Design Build Contracting – an innovative partnership Society of American Military Engineers September 16, 2014 Phil Fordyce, P.E. WSDOT."— Presentation transcript:

1 WSDOT Design Build Contracting – an innovative partnership Society of American Military Engineers September 16, 2014 Phil Fordyce, P.E. WSDOT

2 Agenda Why Design Build? Preliminary Engineering Project Goals Selecting a Design Build team Design Build Partnerships Design Build: Design and Construction Contact Administration Project Closeout WSDOT Design Build projects Questions

3 Why Design Build for WSDOT? Speed of delivery Resources Early price certainty Innovative delivery

4 Preliminary Engineering Design/Contract Development Preliminary/Conceptual Design –15% level of design –Cost estimates Right of Way Utilities Deviations Risk Agency/Stakeholder/Open Houses –Aesthetics and Noise walls

5 Project Goals (example)  Congestion Relief - Open the new northbound auxiliary lane to traffic as soon as possible and no later than December 31, 2010.  Excellent Quality - Meet or exceed technical quality requirements for design and construction through implementation of a clear and thorough Quality Management Plan.  Permit Compliance - Meet or exceed environmental requirements with no permit violations by adopting WSDOT’s permitting and environmental compliance standards.  Smooth Start-up - Maximize project development effectiveness through implementation of a well-planned start-up that ensures efficient delivery of the Project and begins construction as soon as possible.  Technical Approach - Utilize technical innovations that provide added value to the project.

6 Selecting a Design Build Team Request for Qualifications (RFQ) Selection process based on goals Shortlist 3 to 5 teams Reference Checks Philosophy in Scoring Evaluation Manual Debrief with firms

7 Selecting a Design Build Team Request for Proposal (RFP) Meetings with proposers Q and A’s ATC’s Confidentiality Addendums Quiet period Technical score and price

8 Calculating Best Value Proposal price - Technical score Lowest score is best value Team Price Technical Credits Score A $185,740,751 - 10,660,000 = 175,080,751 B $202,874,000 - 11,820,000 = 191,054,000 C $157,800,001 - 9,630,000 = 148,170,001 D $155,500,001 - 6,500,000 = 149,000,001

9 Design Build Partnership Keys to Success Co-location Formal and informal partnering Discipline task forces Shifting focus of the organization –Learning curve for everyone WSDOT has oversight

10 The Design Of Design Build Design Builder moves project from 15% conceptual plans to 100% RFC plans. Design Builder submits plan sets to WSDOT for review and comment (preliminary and final) – not approval Construction starts before design is complete, but not without RFC plans. Post design services – Process to get AS-built plans (RFI,FDC, NDC)

11 WSDOT - Roles and Responsibilities Design WSDOT owns Basic Configuration elements WSDOT provides oversight: Most review happens in Task Force meetings through “over the shoulder” reviews Ensure design meets the Contract Requirements / Mandatory Standards established Manage review comments and resolution; beware of preferences Do not direct work Management – tracking (doc. control) WSDOT provides design quality audits –DQMP WSDOT approves the design at the end of the project

12 The Construction of Design Build Quality Management Plan (QMP) Design Builder responsible for Quality Control (QC) and Quality Assurance (QA) –Quality Assurance must be independent from Quality Control –Quality Manager must report to non-production management WSDOT responsible for Quality Verification (QV) –Lab certification and tester qualifications –Testing asphalt –Fabrication inspection Environmental –WSDOT responsible for permitting –Design Builder responsible for compliance The Design Builder responsible for solutions to problems

13 Contract Administration Roles and Responsibilities Document control Materials/Record of Material Payment Change orders RFI/FDC/NDC (post design services) As-Builts Final Records

14 Project Closeout - Design Design Document Control Develop closeout plan at beginning of project Define requirements – Design deliverables For WSDOT: DDP/PF Importance of early engagement

15 WSDOT Design Build Projects 29 Design-build project to date starting in 2001 www.wsdot.wa.gov/biz/contaa/DESIGNBUILDCONT RACTS/default.htmwww.wsdot.wa.gov/biz/contaa/DESIGNBUILDCONT RACTS/default.htm

16 Questions? Phil Fordyce, P.E. (425) 456-8590 Fordyce@wsdot.wa.gov