Collaboration Mtg Cotober 11, 2000 Installation Status Opening Remarks Overview, logistics Recent events, status Outlook, concerns Conclusions Jon Kotcher.

Similar presentations


Presentation on theme: "Collaboration Mtg Cotober 11, 2000 Installation Status Opening Remarks Overview, logistics Recent events, status Outlook, concerns Conclusions Jon Kotcher."— Presentation transcript:

1 Collaboration Mtg Cotober 11, 2000 Installation Status Opening Remarks Overview, logistics Recent events, status Outlook, concerns Conclusions Jon Kotcher Collaboration Meeting October 11, 2000

2 Collaboration Mtg Cotober 11, 2000 Opening Remarks  Installation/detector evolving very nicely u Huge progress on many fronts s Detectors delivered/mounted s Critical electrical & mechanical infrastructure installed – necessary ingredients s Cabling of all flavors (delicate, tricky) s Electronics (deliveries will remain problem) s Commissioning! (J. Yu) u Focus of hardware upgrade almost completely at DAB (SMT finishing up) s Tight organization, working well together u We are all indebted to excellent support staff s Buy them a cigar, cognac sometime…  Much left to do in time allotted u Some of it detailed work that can only go so quickly without unacceptable amount of risk u Not without concerns for March 1 startup s Will discuss later in talk  Two major “innovations” have opened up our ability to progress rapidly: u Split silicon into two halves u Put large pieces in place on final installation “runways” as early as possible s EF irons on platform, EMC trusses brought down to pit s (Awaited delivery of CFT)

3 Collaboration Mtg Cotober 11, 2000 Since NIU Workshop  Fiber Tracker installed Thu/Fri, June 29-30 u Transport from Lab 3, light-tighting in Hi Bay, insertion into bore, transfer to final mounts u Went very smoothly s Used 2 days of the 2 wks we’d allotted u Surveyed into position s CFT well-centered on solenoid, axially and transversely s Solenoid ~ 5/8” south –Critical area, need clearance for CFT/CPS/CFT waveguides –Sophisticated “putty test” in inter-cryostat gap demonstrated ample space – quite definitive u Kudos to D0 Mechanical Group, CFT Group s Completion, installation represents major technical achievement u Starting gun for motion of large pieces back into position…  ECS on center beam Tues, July 11 u Surveyed, repositioned, resurveyed, … s Positioning constraints much tighter for Run 2 (beam pipe, silicon) s Some outstanding issues remain u Cryogenic hookup, recabling of ECS, beryllium beam pipe placed in CFT Barrel 1 s Bubble wrap, PVC, foam, purge

4 Collaboration Mtg Cotober 11, 2000 Since NIU Workshop  After ECS, platform moved west, end irons picked up, returned 8/4 (one week – faster than anticipated)  Trusses brought down immediately thereafter, completed 8/15  VLPC cryostats installed 8/7, commissioned 8/17 u Working very reliably, without incident u Copper ground straps installed for electronic noise u Handful of production VLPC cassettes installed to do waveguide checkout s Data looks great – another important milestone  Waveguide installation ran into some snags u Spatial constraints btwn calorimeters at outer radius not properly accounted for u 4:1 model made of entire face, incl silicon cable runs u Waveguide running on south face completed this week s A necessary prerequisite for SMT-S installation s Actually will be ahead of schedule u Detailed modeling demonstrated need for more room for waveguides/silicon cables & services s Two inner H-disks will be moved 1.75” away from interaction point u Waveguide checkout continues, much progress s Using kludged stereo boards for front end

5 Collaboration Mtg Cotober 11, 2000 Since NIU Workshop  All Forward Muon detectors complete (Sep) u Congratulations Dmitri, et al.  Forward Muon A-layer pixels and MDTs mounted u Manipulation, alignment of large pieces – manpower, effort u Mounting of full A-layer major accomplishment s Has typically required iteration – a worry for completion of full system s Final articulating drawbridges not yet in place  C-layer north MDTs installed, being surveyed into position u Lead time for turnaround of survey information can be painful  C-layer north pixel plane assembled on shield wall u Quite impressive (go see it) u Being surveyed, then “hung” into place on truss after rear C-layer MDTs positioned  Expect north truss ready to roll in to Collision Hall mid Oct, south truss mid Nov u Truss installation to Collision Hall begins Nov 13  Accelerator shutdown, warm up, low  retraction  System is progressing, but engineering is proving to be a significant bottleneck  4.5 months ain’t much time…

6 Collaboration Mtg Cotober 11, 2000 Since NIU Workshop  Calorimeter electronics arriving u Almost 2 full quadrants of upgraded electronics available u Vendors an issue, as always  Purity of liquid argon in dewar 0.4 ppm   test cell, stand-alone test cryostat   measurements being taken now u Ready to be used to fill cryostats s Thanks to G. Sajot & Co.! u Considering filling prior to roll in s Purity monitoring & thermometry (C. Zeitnitz, Mainz), HV, electronics s Manpower, amount of activity an issue s Will be discussed in Yu’s commissioning mtg this week  Beam loss monitors, radiation sensors, Run 1 luminosity counters installed in Collision Hall (NIKHEF, Brown, others) u Readout, feedback to accelerator  Silicon is doing very well u Cabling of SMT-S finishing at SiDet within next two weeks u Expect SMT-S installed early November, SMT-N around Xmas u Noise, error rates on 70k channels at 10% test looks quite good u Talks by Zdrazil, Lehner on Friday

7 Collaboration Mtg Cotober 11, 2000 Outlook, Concerns  Hardware: u Both SMT half-barrels should be in before roll in s Won’t be necessary to do in Collision Hall u B-layer pixels are in jeopardy s Design of mounting hardware not quite complete s If late, will likely require roll out to complete (crane) s Would be a blow (detectors complete) - pushing very hard u Alignment, positioning accuracy of detector elements far more stringent for Run 2 s Beryllium beam pipe + bellows, silicon, calorimeters… s Difficult problem - much thought, survey u Amount of work in limited space, time  Arrival of electronics for tracking & other systems is very, very late u Interface cards for silicon: start arriving mid-Nov u Adapter cards: partials Nov? u Power supplies for CFT AFE: Feb 12 (partials?) u 8-chip AFE boards for CFT: end Dec (RH), mid- Jan (LH) s 3-4 in hand til then, no partials s 12-chip AFE (stereo, preshowers): Spring u Completion of CAL BLS motherboards: mid-Feb u Level 2 trigger commissioned: 25 April s Alpha boards – smoke hasn’t settled here… u Vendors a canonical problem – much work focusing on expediting these orders, but… u Robust economy is not helping us

8 Collaboration Mtg Cotober 11, 2000 Outlook, Concerns  Impossible to overstate delicacy of silicon hookup u Final connection of low mass cable must be made one and only one time s Full checkout upstream of adapter card prior to hookup of detector s Detectors damaged, fried with little effort – has been proven in the field by other exp’ts u Electronics will be trickling in u Dressing of inner cables very delicate, convoluted u Properly functioning interlocks an integral part of process (complex system) u Extreme care essential here u Parallel activities a worry s Locked gate at intercryostat gap! u Beginnings of commissioning team in place, needs coalescing u Si hookup will take a while – no corners can be cut s Need access to intercryostat gap, cathedral  Time allotted for detector commissioning time prior to roll in has all but disappeared u Replaced by electronics installation & hookup:  Being synched to accelerator downtimes for electronics installation & hookup in a system of this complexity will severely hamper our readiness for acquiring physics-quality data u Detector, front end, DAQ, online, trigger experts will be absolutely crucial

9 Collaboration Mtg Cotober 11, 2000 Conclusions  D0 is doing extremely well, an excellent year for the hardware portion of upgrade u Si, CFT, Muon, Cal, infrastructure, online, commissioning  Systems are coming up, behaving as hoped in most cases  Serious, dedicated young people have been, and continue to be, instrumental in getting us there  Much remaining to do, activity in hall escalating organically – OK for moment, but approaching saturation u Spatial/temporal constraints may mean some things cannot get done prior to roll in  Pressure rapidly mounting u Danger now is breaking something, hurting somebody u Taking appropriate care more important than speed!

10 Collaboration Mtg Cotober 11, 2000

11 Collaboration Mtg Cotober 11, 2000 Data Taking Position  Clamshells closed, shielding mid-piece extended, EF & calorimeters closed

12 Collaboration Mtg Cotober 11, 2000 Calorimeter Access  Retraction of shielding mid-piece & EF travel allow access to region between calorimeters u FPS, ICD, LUM, SMT installation & cabling u CFT cabling on face of CC u Collision Hall access – servicing, repairs, etc. EF travel only 42/47” for Run 2

13 Collaboration Mtg Cotober 11, 2000 Access to B/C layers  Requires scaffolding supported off Collision Hall floor (not shown) u Small (~ 7”) footprint